This solicitation requests quotes to remove and replace an air handling unit and install humidity control equipment at an Indian Health Service hospital in accordance with the attached statement of work. The contractor must furnish all labor, materials, equipment, and services to demolish the existing unit and install a new air handler that maintains proper temperature, humidity, and pressure relationships in a sterile supplies storage area. Quotes are due by February 25, 2022 and the period of performance is 90 calendar days from notice to proceed. The procurement is set aside for small businesses under NAICS code 238220 with a size standard of $16.5 million. The award will be made to the responsible, responsive offeror providing the lowest reasonable price who meets all technical specifications.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ#

AHU2A EMERGENCY REPLACEMENT PROJECT

I. PURPOSE:

To obtain required commercial services to remove and replace air handling unit (AHU) 2A with new equipment meeting the requirements of this SOW, install humidification equipment within the new AHU, and to supply hydronic heating water to the new AHU and (1) steam-heated unit heater which is capable of using either steam or water as a heat source at the Claremore Indian

Hospital (CIH).

Worksite location is within the AHU2A and 2B penthouse located on the roof of the Claremore

Indian Hospital – Building 3767, and in the interstitial space above the ceiling of Support

Services - RM 301, which is located almost directly below the penthouse.

II. BACKGROUND:

AHU2A was installed in the early 2000s. This unit’s purpose is to maintain proper environmental conditions for sterile storage within Support Services – RM 301. The currently required conditions are as follows:

A. Temperature: 68-73F (Temperature range limited to occupant comfort range)

B. Relative Humidity: 30-60%

C. Pressure relationship: positive to adjacent spaces/areas and building exterior.

D. Air changes per hour (minimum): 2 outside ACH, 4 total ACH

These required conditions are based on ASHRAE Standard 170 - 2017 for Ventilation of Healthcare Facilities, ASHRAE Standard 170 - 2008 for Ventilation of Healthcare Facilities, and current hospital policy relating to this space.

During the design period of AHU2A, little concern was given to latent load, with the design mainly focusing on obtaining required sensible temperature range. This was the current engineering practice at the time, although it was recognized that latent load shall be taken into consideration shortly thereafter. The current design of AHU2A is capable of maintaining required room temperatures, but has no provision for more than just incidental dehumidification when the cooling coil happens to be at a temperature below dew point. This design makes it all but impossible to maintain proper environmental conditions for storage of sterile supplies during warm, wet outdoor air conditions. Also, during the winter months this AHU lacks any provision to provide humidification, causing the room to suffer from low humidity levels. Equipment selected for this project shall address all currently required environmental conditions, and have the capacity to maintain them under the most adverse outside air conditions, as it is never acceptable to operate under out-of-spec conditions.

Currently, AHU2A provides heat utilizing a steam-heated preheat coil. There is no provision for reheat at this time. Equipment selected for this project incorporate hydronic heating water maintained within a range of 130-180F for both preheat and reheat coils, completely eliminating the requirement for steam. It is desired to use existing hydronic heating water piping that was abandoned during the AHU replacement project in the early 2000s to supply hydronic heating water to this AHU, assuming the pipe is of proper size for required hydronic heating water flow and is still in an acceptable condition. Water is supplied via 2” steel pipe, per print.

To provide freeze protection within the AHU penthouse, the existing steam-heated unit heater is to be supplied with hydronic heating water, and existing steam supply removed back to the common Tee, and condensate piping removed back to the first natural joint under the roof.

III. REQUIREMENTS / SCOPE OF WORK (SOW):

Contractor shall provide all labor, equipment, materials, supplies, and subcontracted services to remove and replace AHU2A with equipment capable of meeting required environmental conditions as follows:

A. Temperature: 68-73F (based on occupant comfort)

B. Relative Humidity: 30-60% (based on ASHRAE 170 – 2017 requirements for sterile storage)

C. Pressure relationship: positive to adjacent spaces/areas and exterior. (.05” w.c.) based on ASHRAE 170 – 2017 requirements for areas providing clean supplies.

D. Air changes per hour (minimum): 2 outside ACH, 4 total ACH based on ASHRAE 170 – 2017 requirements for sterile storage rooms. (This requirement does not supersede outside air requirements of item G. below)

E. Dew point shall be maintained between 39.5F and 54F at all times. (Derived from the psychrometric chart and maximum dew point temperature recommended to prevent mold growth in ASHRAE standard 62.1. Dew point Range is limited below the 60F requirement based on temperature and relative humidity ranges required in the area.)

F. Equipment shall have (2) filter banks installed meeting the minimum requirements of

ASHRAE 170-1017 section 6.4 for areas used for sterile storage.

G. Equipment shall be capable of meeting the above requirements while supplying up to 30% outside air.

H. All equipment supplied shall meet the applicable requirements of ASHRAE 170-2017 section 6.

See Attachment L for required space operating range.

Equipment selected shall be capable of being installed utilizing existing ducting, although sheet metal transitions shall be required. Platform modification is allowed but should be minimal, if at all required. Contractor is required to perform all measurements to ensure equipment fit.

Required Equipment / Services

Air handler shall include the following:

A. Supply and return fan arrays meeting the following requirements:

1. A combination of fans utilizing backward curved impellers capable of providing 9000cfm at an external static pressure of 3” w.c. during normal operation.

Squirrel cage impellers shall not be acceptable.

2. Electronically commutated (EC), permanent magnet, direct-drive fan motors, sized at 10hp or less for each motor (lead-time and availability allowing)

3. Fan configuration providing N+1 redundancy. Although this shall be accomplished by providing at least (2) fans per fan array, the number of fans is not limited to (2). Any combination of fans in each fan array that prevents total capacity available from decreasing below 100% due to a single fan failure is acceptable.

4. Include installed automatic backdraft dampers for each fan to prevent air bypass through an out of service fan .

5. Include manufacturer-provided EC motor controllers for the fan arrays. Should fan arrays not be provided with manufacturer-specific controllers, variable frequency drives (VFD)s providing EC control shall be acceptable. VFDs shall be YASKAWA GA500 drives or equivalent. VFDs shall include local fusible disconnect directly adjacent to each VFD and in accordance with manufacturer’s installation requirements.

B. Minimum of 2” Double-wall thermally broken casings – R-13 or better thermal performance, no internal, exposed insulation of any type

C. No fiberglass insulation shall be accepted as pertaining to the AHU. All panel insulation shall be closed-cell polyurethane foam, including roof panel of unit and under the drain pans.

D. All casing material shall be corrosion-resistant for both interior and exterior liners.

E. Thermally broken posts, panels, corners, etc.

F. Aluminum low-leakage outside air, return air, and relief dampers.

G. Primary filter bank – Meeting ASHRAE 170-2017 section 6.4 requirements for clean supplies. (MERV 7 efficiency)

H. Secondary filter bank (after all wet coils) Meeting ASHRAE 170-2017 section 6.4 requirements for clean supplies. (MERV 14 efficiency)

I. Access/blank section located properly for installation of steam humidification array.

Factory installed humidification arrays compatible with selected humidification equipment shall be acceptable, if available. (humidifier addressed under Humidification section)

J. Stainless-steel drain pans.

K. Slide-out hot water (no glycol) preheat coil with stainless-steel casing.

L. Slide-out hot water (no glycol) reheat coil with stainless-steel casing.

M. Slide-out chilled water coil with stainless-steel casing.

N. All water coils shall have a minimum of 12” clearance for both entering and leaving faces to allow for coil cleaning/installation of UV array unless minimum required clearance for selected UV array is greater. The greater of the two clearances shall be required.

O. All access doors shall be hinged and provide tool-less entry.

AHU shall meet the following minimum performance requirements:

A. Capable of delivering 9000 cfm supply air flow @ 2” w.c.

B. Preheat –486,000 btu/hr (EAT 0F / LAT 50F) [EWT 160F / LWT 130]

C. Reheat – 291,600 btu/hr (EAT 50F / LAT 80F) [EWT 160F / LWT 130]

D. Cooling – 567,000 btu/hr based on the following parameters and worst case conditions:

1. 30% outside air at 100.6F DBT and 139.7 Gr/lb humidity ratio (.4% conditions)

2. RAT of 75F DBT (worst case)

3. RA humidity ratio of 77.8 Gr/lb (worst case)

4. MAT of 82.7F DBT (calculated from above conditions)

5. MA humidity ratio of 96.8 Gr/lb (calculated from above conditions)

6. Delta-H of 14btu/lb (rounded number)

7. Entering Water Temp 42F max / Leaving Water Temp 57F min (15F delta-T coil)

8. Leaving Air Temp 52F max.

Humidifier:

A. Natural gas-fired humidifier with properly sized and installed distribution array within the AHU capable of meeting the humidification load for the space. Calculated load is 84.59lbs/hr at the following conditions:

1. 9000 cfm total air flow

2. 30% outside air @ 0F/15%RH

3. RAT 70F DBT, 50%RH

4. MAT49F DBT, 74.9%RH

5. Room RH to be maintained in a range of 40-55%RH

B. This equipment shall include all regulators, regulator vents, mounting pads/enclosures, exhaust flues, combustion air intake stacks, and ventilation fans/intakes required by code for an indoor installation.

C. Humidifier shall include native BACnet connectivity.

D. Immediately prior to the humidifier, a refillable water softener cartridge sized for proper flow and for the current hardness of the CIH cold domestic water supply and with integral particulate filtration shall be installed. Size shall be determined based on an operational period of November through March. One cartridge change during the operational period is acceptable. One spare cartridge shall also be provided.

Ultraviolet UVC Emitters:

A. Contractor shall supply and install UVC emitters with associated drivers and hangars for the purpose of cooling coil maintenance. Sterile-Aire brand or equivalent is required.

UVC emitters shall be installed in the optimal location for ensuring a clean cooling coil while also maintaining proper proximity from humidification arrays. This shall include installation of a local power disconnect located near the appropriate AHU access door.

Demolition

1. Contractor shall remove the currently installed AHU designated as AHU2A and all controls/room sensors associated with the Siemens Apogee BAS. This includes (1) room sensor, (1) unitary controller, associated control power transformers, conduit within the penthouse, and any other components that shall be unused for the new AHU installation.

2. All steam piping associate with AHU2A is to be removed back to the supply line tee and blank-flanged as this line will continue to supply steam to AHU2B.

3. All condensate piping shall be removed back to the first common joint for AHU2A

& 2B. Cap end as appropriate.

4. Contractor shall coordinate the demolition with the COR & Facilities

Management. This work shall be conducted over a weekend and will immediately precede the new AHU2A installation.

5. Contractor shall coordinate all crane operations with the COR and shall provide a minimum of (1) weeks’ notice prior to desired demo/installation date.

6. All equipment and debris shall be removed from the penthouse and roof, and shall be disposed of off-site by the contractor. Use of CIH trash dumpsters for disposal of construction debris is strictly prohibited.

Sheet metal:

A. Existing outside air, relief, supply, and return ducts shall be reused to the maximum extent possible. No ducting below the roofline is to be replaced.

B. Transitions from the air handler to existing ducting shall be sheet metal and constructed per SMACNA HVAC Duct Construction Standards • Metal and Flexible, current edition, and SMACNA HVAC Systems Duct Design, current edition.

C. No duct board or ducting with internal insulation shall be permitted.

D. Duct transitions shall be sealed properly, and use of spray foams is strictly prohibited.

E. Installed ducting transitions shall be reinsulated to, match existing. Any insulation deficiencies noted during installation shall be reported to the COR and corrective actions determined.

F. Contractor shall configure outside air and relief ducts to mate properly with new outside and relief dampers.

Piping/valve package:

A. Various methods of piping are appropriate for this installation, however, below roof piping in the interstitial space shall be completed in manner that minimizes non-permanent joints in order to avoid the risk of leakage above the ceiling. Copper, steel, and high density polyethylene (HPDE) piping shall be acceptable if suitable for the particular application.

B. Insulation with PVC jacket shall be installed for all piping installed or replaced. Should HPDE be employed in chilled water systems, piping shall be evaluated to determine the need for insulation to prevent condensation accumulating on the penthouse floor. HPDE to be insulated and PVC jacketed as necessary.

C. Cooling valve – Belimo Energy Valve or equivalent

D. Heating valves – High-temperature Belimo Characterized Control Valve or equivalent

E. Circuit-setters required for proper balancing of heating water supply.

F. All Pete’s Plugs required to perform a proper test and balance for each control valve and coil. Contractor to determine what method, device, or flow curve to be used for test and balance and install plugs in the appropriate location.

G. Particulate strainers installed prior to heating and cooling coils sized to provide adequate protection while minimizing pressure drop.

H. Automatic air vents for heating and cooling loops in the proper location

I. Isolation butterfly valves for supply and return piping for heating and cooling water loops at the penthouse floor penetration. No existing valves shall be reused.

J. New piping to supply heating water from the main headers to the AHU. There are (2) 2” heating water pipes available within the interstitial space between the roof and RM 301 Support Services. If suitable, these pipes shall be used for AHU heating water supply. If not, hot-taps for new supply lines shall be required. (These pipes are capable of supplying 85gpm at a velocity of 8ft/sec. @30F Delta-T and 100% load for both heating coils, total flow required is approximately 52gpm)

K. New supply and return heating water piping to installed unit heater, which is currently utilizing steam as a heat source.

L. Unit heater control valve – Belimo Characterized Control Valve or equivalent

M. Unit heater circuit-setter for balancing unit heater water flow

N. Ultrasonic flow meter equivalent to the Belimo FM200 meter installed within the heating water supply pipe both the preheat and reheat coils.

O. Wells for supply and return temperature sensors for all heating and cooling coils.

P. Cooling coil wells shall meet requirements for the selected thermal energy control valve.

Q. Wells and thermometers for local supply and return temperature indication.

R. Connections and gauges for local indication of heating water and cooling water supply header pressure at the supply and returns.

S. Cold domestic water supply line with isolation valves at initial connection point and at the terminal end for supplying water to selected humidification equipment. This connection shall also include a standard garden hose connection with required freeze protection/backflow prevention devices for use in servicing AHUs. This supply line shall be located entirely within the penthouse, and shall not be exposed to weather.

T. Contractor shall supply and install approximately 25ft of carbon steel natural gas piping from the Claremore Indian Hospital natural gas supply line originally servicing an incinerator and make connection to natural gas piping installed on the roof and terminating at the AHU2A/2B penthouse. Pipe shall be painted yellow. Existing piping on the roof was installed by CIH in-house maintenance staff, and has been pressure-checked to 50 psi, with no leakage detected over a 24hr period.

Electrical:

A. Contractor shall provide and make all electrical services required to power newly installed equipment, including all control panels, fan motors, etc.

B. All electrical work shall be completed in a manner consistent with the National Electrical Code, NFPA 70, 2011 edition.

C. Contractor shall utilize available utilities powering the current AHU to the maximum extent possible.

D. Contractor shall provide and install equipment disconnects for any equipment that does not include a local factory disconnect.

E. All electrical services shall be run within electrical metallic tubing (EMT) and all connectors shall be of the compression type.

F. All conduit shall be properly supported.

G. Use of MC Cable shall not be allowed. For flexible joints, flexible metal conduit or seal-tite shall be allowed, but length shall be limited to 3ft. Flexible conduit shall not be run in a manner that would promote tripping or entanglement.

H. All connections to CIH electrical panels with arc-flash labels shall require the arc-flash label for the panel/breaker to be updated to reflect the new wiring and equipment. Any new electrical supply panels installed shall require arc-flash study and proper labeling.

All labels shall match existing arc-flash label format unless code revisions require an updated format.

I. If AHU is supplied with a single-point connection panel with disconnect, arc-flash update and labeling shall be required.

Controls package:

A. FIRE PROTECTION - If existing smoke detectors require relocation, contractor shall be responsible to relocate detectors and ensure all alarm and automatic shutdown functions are present and functional after the work. Smoke detectors shall have auxiliary relays wired and programmed to also indicate active alarms through the BAS.

B. Control of the AHU, unit heater, humidifier and other associated equipment shall be accomplished utilizing the currently installed WebCTRL building automation system (BAS). Contractor shall provide required controls services for installation and programming of controls providing functionality similar to AHUs 3A/3D. Note: These are dual-duct AHUs, but AHU2A is to be a single duct unit.

C. The current controls contractor for CIH is ES2, located in Tulsa, Oklahoma. Although the contractor is not required to utilize this controls contractor, the selected controls contractor shall provide proof of Automated Logic (ALC) WebCTRL system training through ALC, shall be authorized to purchase controls equipment through ALC (no third-party vendors allowed due to warranty issues), and must have a local office within 50 miles of CIH due to the critical nature of this system.

D. AHU main controller shall be an Automated Logic OF1628 controller/router with necessary IO expansion modules for control of this AHU. This controller is part of the established WebCTRL building automation system and third-party controllers, protocol translators shall not be permitted. This is to preserve network integrity and operating speed. Third-party devices for all other sensors, air flow stations, etc., shall be permitted as approved by the Contracting Officer’s Representative (COR).

E. All AHU temperature, humidity, room pressure, duct pressure, filter differential pressure, smoke detection, freeze-stat, and air flow sensors/stations in accordance with the attached control points list shall be provided and installed by the contractor.

F. Main control cabinet shall include the following:

1. Contractor shall provide and install UPSs wired to power all installed controllers/IO modules. UPSs shall be DIN rail mounted within the control cabinet. UPS shall be sized to supply the full load of installed controls/actuators/measurement devices for a minimum of 30 seconds.

2. Contractor shall provide and install 24V regulated DC power supply in lieu of standard 24VAC transformers. These power supplies shall be sized to accommodate all panel equipment, damper actuators, air flow stations and other equipment plus (2) additional Opti-flex FIO modules. Power supply shall be DIN rail mounted within the control cabinet.

3. Contractor shall provide and install convenience receptacles and a master shut-off in panel.

4. Control cabinet shall be sized to accommodate wire duct around each component section, panel mount uninterrupted power supplies (UPS), regulated

DC power supply, and other installed components with an additional 25% of free space or the equivalent space required to add (3) additional Opti-flex FIO modules, whichever is greater. This includes accommodating additional wire duct for the FIO modules. Example panel layouts, UPS examples, and power supply examples are provided in the Attachment section of this SOW.

5. All components contained within the control cabinet shall be DIN rail-mounted components to the maximum extent possible. No items shall be mounted to the outside of the cabinet.

6. Cabinet shall contain a laminated IO points list reflecting the control system as built. This list shall be affixed inside the door of each cabinet.

G. Control and data wiring:

1. All wire, cable, and conduit runs shall be neat in appearance. Crossings shall be minimized. Use of a common wire duct extending the length of the AHU with conduit dropping to sensor locations shall be permitted and is preferred if equipment orientation permits.

Page 10 of

2. All control and data wiring installed within the Penthouse shall be installed within properly supported EMT utilizing compression fittings.

3. Use of flexible conduit, Seal-tite, and flexible metal conduit is allowed where appropriate, but length shall be limited to 3ft, and runs shall be supported and not hung in a manner that would promote entanglement.

4. Contractor shall install all required wiring, surface mount boxes, and receptacles/terminations to provide (2) Ethernet data drops in the AHU penthouse. The COR shall mark actual location within the penthouse at time of installation. Data receptacles/cables shall terminate at the Penthouse and at server closet marked on the attached floorplan drawing. Wire routing will be determined and finalized during the Penetration Briefing.

5. Twisted pair wiring utilized for these Ethernet drops shall be solid copper CAT6 wire, plenum-rated, and outer jacket shall be of a color other than blue, white, purple, or yellow. An example of required wire type is located in the attachment section of this SOW.

6. All data wire shall be labeled at both ends to denote which AHU that wire serves.

Surface-mount data receptacles shall be labeled to reflect the data port at which the circuit terminates. CIH IT Department shall specify the format by which the data ports are to be labeled and the final terminating location at the server/switch closets.

7. Any control wire utilized shall be plenum-rated and color selected to match previously installed wiring based on its function. (e.g. white for control, yellow or green for BACnet)

8. All control/sensor wiring shall be labeled at the terminating ends as to purpose and include the IO point designation number.

9. Contractor shall perform demolition of unused Siemens controls, sensors, and remaining wiring upon completion of this project. Contractor shall not remove main Siemens controllers that control terminal boxes. These shall be identified by the COR prior to any demolition work. No deactivated items are to be left installed, but shall be removed from the penthouses and disposed of in the CIH trash roll-off.

Page 11 of

10. Before any wiring penetrating any wall of the CIH main building is installed, a penetration briefing shall be conducted by the Contracting Officer’s

Representative (COR). This briefing shall cover:

i. Appropriate level of penetration fire protection required for each penetration

ii. Proper installation of wire utilizing EZ-Firestop Grommets

iii. Proper suspension of wire, especially on either side of a penetration

iv. Methods/requirements for penetrating non-rated walls

v. Termination of each cable run

vi. Required above ceiling permits and inspections

Contractor is required to strictly adhere to the requirements presented in this briefing.

11. All wall penetrations shall be approved by the COR prior to the penetration of any wall. Penetrations shall be made in a manner that maintains the fire/smoke rating of all walls. All penetrations through firewalls shall be made utilizing STI

EZ-Firestop Grommets. Details for these products are included in the attachment section of this SOW

12. Contractor shall not impair the installed building fire protection system in any way during this project. Contractor is liable for any damage or interruption to the system and shall be responsible to immediately make any repairs necessary to restore the system to proper operation. This shall include fire protection system subcontractor charges incurred, should a service call be required.

13. Data/control wire installed by contractor shall not contact any sprinkler piping or pipe supports. Wire shall not be routed in a manner in which intertwines it with other wiring or piping

14. All data wire within the interstitial spaces shall be properly suspended/supported in J-hooks at a minimum height of (1) foot above the ceiling grid. The use of existing IT J-hooks is allowable so long as all previously stated requirements are met and the J-hooks are not full. J-hooks supporting camera or security access cabling shall not be used. Particular attention shall be paid to properly supporting wire on either side of a fire-rated penetration so as to protect the integrity of the fire protections system as designed/approved.

H. Graphics/Sequence of Operation:

Page 12 of

1. “Industry Standard” prepackaged sequences are often not sufficient to provide required control to maintain environmental conditions with installed equipment.

Prior to any programming, contractor shall meet with the Contracting Officer’s

Representative (COR), to verify all sequences/functions are compatible with current HVAC system operation with respect to known building HVAC design deficiencies and current operating procedures. Sequence of operation is subject to COR approval prior to implementation.

2. Contractor shall utilize AHU view provided by CIH Facilities Management to the greatest extent possible as they have been configured to more closely match the physical orientation of CIH equipment. Minor modifications shall be permitted to produce views providing the most accurate and efficient visual acquisition of necessary operational data.

3. Contractor shall compare standard points list and ensure that all equipment represented in the points list is also represented on the graphic.

4. Supply air fan array shall be programmed to modulate in order to maintain a duct pressure set-point adjustable in the Control Program tab of the graphic for each

AHU.

5. Return fan array shall be programmed to modulate to maintain an adjustable duct pressure set-point. This is to implement direct pressure control as recommended by ASHRAE Guideline 16. Pressure sensor shall be located in the plenum between the return fan array discharge and the relief damper.

6. Relief dampers shall be programmed to modulate to maintain an adjustable pressure for the service envelope of the AHU. Pressure sensor sensing point shall be located near the center of RM 301

7. Contractor shall update the floorplan print of the BAS to reflect new air handler installation in similar fashion to AHUs 3A/3D.

8. Contractor shall provide cooling water valve-specific graphics for 2A. This shall be the stock valve graphic for the type of valve installed. Also, the basic energy management and delta-T management parameters are to be displayed on the

AHU graphic similar to those displayed on the AHU3A graphic. Screen-adjustable controls to allow disabling delta-T management shall be displayed on each AHU main graphic. Programmed logic shall include automatic disabling of delta-T management when the Central AC plant is operating on the plate heat exchanger (PHX).

Page 13 of

Commissioning/Test and balance

1. Contractor shall perform a complete test and balance of the air handler and provide report to the COR. This shall include at minimum:

Preheat coil water flow – verify installed flow meter

Reheat coil water flow – verify installed flow meter

Cooling coil water flow – verify installed flow meter

Unit heater water flow

Outside air flow – verify air flow station

Supply air flow – verify air flow station

Return air flow – verify flow station

Room pressure sensor – verify pressure reading

2. Contractor shall provide a commissioning report verifying at a minimum the operation of all fan arrays (current readings, drive settings, controllability), dampers, fire protection features (AHU shutdown), humidifier, UVC emitters, coil performance, an all other customary parameters.

Period of Performance, Timelines, and Worksite Conditions

1. This installation requires an abbreviated time line. This work is being completed in a critical area of the hospital and complete demolition and installation shall be completed between Friday at 1630 and the following Monday at 0700. “Completed” is defined as having the new AHU operating properly and completely under control of the BAS. Minor clean-up and final reports shall follow within 4 business days. RM 301 shall be ready to be reoccupied on

Monday morning at 0700.

2. The period of performance for installation shall be within 2 weeks of receiving

ALL required equipment, controls, and items to complete this work. Pre-staging and preliminary work to the maximum extent possible is allowed and encouraged.

3. AHU2A shall not be inoperable beyond the specified timeline for installation.

4. Special worksite conditions are as follows:

Large double-doors are located on the south side of the AHU penthouse to provide access for demolition and installation.

Penthouse is located near the roof edge and there is open pavement for the purpose of utilizing a crane to lift and remove equipment.

Page 14 of

Piping for the hydronic heating coils is located in the interstitial space above RM 301. This is a hard ceiling area and access is limited. This ceiling cannot be walked upon. Contractor shall provide and utilize boards, sheets, or other items to span the supports for the ceiling in order to move about in this area. Should the contractor need to open access beyond the provided access panels or movable registers, contractor shall be responsible to repair sheetrock or other damaged items to their original state.

IV. DELIVERABLES AND REPORTING REQUIREMENTS:

A. Contractor shall deliver the following:

1. Equipment submittals for approval, prior to equipment installation.

2. All equipment specified by this SOW installed and functioning as designed.

3. Worksites clean and all debris and supplies removed from CIH.

4. Copies of all Operation and Maintenance manuals for all installed equipment.

5. Printed sequence of operation for AHU.

6. Final as-built prints for all controls installed.

7. In-service training of CIH Facility Maintenance personnel on the operation of the installed units and controls, once the system is operational and properly commissioned.

8. Safety Data Sheets for all hazardous materials used in the completion of this project, including refrigerants, oils, chemicals used during project, etc.

9. Copies of all factory warranty certificates for all installed equipment.

10. Contractor shall warranty all work for a minimum of 1 year.

B. Contractor shall submit the following reports to the COR:

1. After performance of service, a detailed service report shall be submitted to CIH

Facility Management containing the following information:

Company name, address, and phone number.

Name of technician(s) performing the work.

Date work was performed.

Page 15 of

Detailed description of work performed.

Operational recommendations, if any.

List of parts replaced, equipment provided.

Any other recommended changes needed to ensure proper system performance.

C. SPECIAL PROCEDURES:

1. Contractor is required to call in advance to schedule the work.

2. The majority of work on this project shall be completed over a weekend and at night. CIH normal operating hours are 7:30 am to 4:30 pm, Monday through Friday.

Contractor shall coordinate and schedule the service with the COR.

3. Immediately upon arriving at the facility, contractor shall report to the facilities maintenance department in order to sign into the visitor’s log and obtain a visitor’s badge.

4. Contractor shall provide a copy of the appropriate license or certification prior to performing any work.

5. Contractor, upon completion of the work, shall return to the facilities maintenance department to sign out, return the visitor’s badge, and provide all required service reports prior to departing the facility.

6. The US PHS Claremore Indian Hospital is a tobacco/smoke free environment (buildings and grounds). No tobacco/smoking use shall be tolerated on-site.

7. Contractor shall comply with all posted rules and regulations in the hospital and on hospital grounds including parking, no smoking or tobacco, etc.

8. Contractor shall comply with all Life Safety, Infection Control, and Occupational Safety rules, regulations, and instructions, both written and verbal while at the facility.

9. All on-site contractor workers shall perform infection control and safety training provided by the hospital.

10. Contractor shall coordinate with CIH Facilities Maintenance personnel to perform LOTO as required by NFPA 70E and 29CFR 1910.147.

Page 16 of

11. Contractor shall coordinate with CIH Facilities Management any operation that could impair or suspend the services provided by or the normal operations of any hospital department.

12. Contractor shall coordinate with CIH Facilities Management any segregating of parking spaces to accommodate cranes, and the crane operations themselves 24hrs prior to performance.

Attachment A – Worksite Location

This is the Claremore Indian Hospital campus. The orange arrow denotes the location of the AHU to be replaced. Top of the image orients north.

AHU2A / 2B

Penthouse

Page 17 of

Attachment B – Panel Example 1

This image represents a typical panel installation at CIH. Note that there is no expansion room. Also note that control power transformers are to be replaced with regulated DC power supplies in the new panel.

Page 18 of

Attachment C – Panel Example 2

Page 19 of

Attachment D – Firestop product

EZ-Firestop® Grommets are a molded, two-piece grommet with an integral fire and smoke sealing foam membrane for sealing small cable penetrations through framed wall assemblies. Grommet snaps together around cable(s) and locks tightly into the wall.

Applications

EZ-Firestop® Grommets are designed to permanently seal small cable penetrations through drywall.

Specifications

For small cables penetrating gypsum board/stud wall assemblies, the firestop shall consist of a molded, two-piece grommet having a foam fire and smoke sealing membrane that conforms to the outside diameter of the individual cable.

The grommet product shall be capable of locking into place to secure the cable penetration within the wall assembly. The grommet shall be UL Certified and tested to the requirements of

ASTM E814 (UL1479) and CAN/ULC-S115.

Specified Divisions

Performance

EZ-Firestop® Grommets were tested to meet the exacting criteria of ASTM

E814 (UL1479) and CAN/ULC-S115.

Tested systems provide up to 2 hour fire ratings for small cable penetrations in gypsum board/stud wall assemblies.

PHYSICAL PROPERTIES

Color Red

Plenum Grade Yes

Less than 1 CFM

(ANSI/UL1479)

In Service Temperature Less than 130°F (54°C)

VOC content N/A

Shelf Life No Limit

Overall Length 1-5/8” (41.3 mm)

Installed Depth (from wall surface)

1-9/16” (39.7 mm)

P R O D U C T D A T A S H E E T

EZ-Firestop® Grommet

Features & Benefits

• One or more cables with total O.D. up to 0.27” (7 mm) for RFG1

• One or more cables with total O.D. up to 0.53” (14 mm) for RFG2

• Easy firestop & smoke seal for a small cable penetrations through fire-rated walls

• For use in gypsum board wall (i.e. drywall) construction

• Tested to ASTM E814 (UL1479) and CAN/ULC-S115

• Rated for use in plenums

Leakage Rating

Division 7 07 84 13 Penetration Firestopping

Division 26 26 00 00 Electrical

Division 27 27 00 00 Communications

ORDERING

INFORMATION

Maintenance

No maintenance of the grommet is normally required.

System Selection

Required Opening for RFG1 9/16” (14 mm)

Weight for RFG1 0.01 lbs (5 g)

Required Opening for RFG2 1” (25 mm)

Weight for RFG2 0.03 lbs (14 g)

To find your firestop system or create a submittal, visit https://systems.stifirestop.com/ to use System Search & Submittal Builder. You may also visit the UL Online Certifications Directory/UL Product iQTM for complete listings. (Firestop Systems).

Technical Service

Specified Technologies Inc. provides toll free technical support to assist in product selection and appropriate installation design. UL System designs suitable for submittal or specification purposes are available on request. A complete library of technical information is provided at the company’s website www.stifirestop.com including Safety Data Sheets (SDS’s).

Precautionary Information

No unusual hazards are known or expected. Observe normal safety procedures during installation.

Availability

EZ-Firestop® Grommets are available from Specified Technologies Inc. (STI) authorized distributors. For additional purchasing and technical information or for the names and locations of the nearest representative and/or distributor, regarding this and other Specified

Technology products, please call 1-800-992-1180 or visit www.stifirestop.com.

Catalog Number UPC Number Description (UOM) Qty. Case Qty. Weight (Each)

RFG1 730573250587

Two-piece split cable grommet for single cable penetrations up to 0.27” (7 mm) diameter

RFG2 730573250594

Two-piece split cable grommet for single or multiple cable penetrations up to 0.53” (14 mm) diameter

1 Pack 10 Grommets per pack

1 Pack 10 Grommets per pack

10 Packs

0.21 lbs

(0.10 kg)

10 Packs

0.40 lbs

(0.18 kg) https://systems.stifirestop.com/ https://iq2.ulprospector.com/session/new?redirect=http%3a%2f%2fiq.ulprospector.com%2fen%2f_%3fp%3d10005%2c10048%2c10006%2c10047%26qm%3dq%3a http://www.stifirestop.com/ http://www.stifirestop.com/

HHSI Page 21 of 33

Attachment E – Data Cable Example

CABLE SPECIFICATIONS

DESCRIPTION 23 AWG Category 6 Unshielded Twisted Pair (UTP) Cable, Swept Tested to 550MHz. This Cable is Plenum

Rated and Verified to Category 6 Electricals

CONDUCTOR 23 AWG Solid Copper, .0217" OD +/- .00015"

INSULATION FEP, PE

COLOR CODE White-Blue/Blue, White-Orange/Orange, White-Green/Green, White-Brown/Brown

JACKET CommFlex .019" Nom.

JACKET COLOR Purple Jacket

MARKING 1000/0000 A B C D E 0 1 2 3 4 5 6 7 8 9 UTP 4/23 C(ETL)US CMP VERIFIED (ETL) CAT6

9700851 550 MHZ TIA/EIA 568-C.2 WINDY CITY WIRE

OVERALL DIAMETER .215" Nom.

CABLE WEIGHT 28 Lbs/Mft.

CAPACITANCE 14 pF/ft. Nom.

IMPEDANCE 100 +/- 15 Ohms (1.0 - 250 MHz)

DC RESISTANCE 6.66 Ohms/100m Max/2.5% Max

TEMPERATURE RATING -20C to 60C

VOLTAGE RATING 300 Volts

INDUSTRY STANDARDS

FLAME RATING Approved For Plenum Use Without Conduit Per NFPA 262 Flame Test

AGENCY APPROVALS ETL Listed Type CMP, C(ETL)US

HHSI Page 22 of 33

Attachment F – Points List

TYPE POINT NAME COMMENTS

Input SA Duct Pressure Input RA Duct Pressure Between return fan and relief damper Input Serviced Area Pressure Input Final Filter D/P Input SA Temp Input MA Temp Input- RNET Penthouse Temp Input SF Status (from Drive Running rly) Input RF Status (from Drive Running rly) Input SF VFD fault (from VFD Fault rly) Input RF VFD fault (from VFD Fault rly) Input SA Smoke Detector Input RA Smoke Detector Notification Input Freeze-stat Notification Input HHW Temp in Input HHW Temp out Input PHHW Temp in Input PHHW Temp out Input Unit Heater status Input HHW or PHHW Flow Meter Input Humidifier limit/fault Input Humidifier air switch Input Humidifier interlock Input Humidifier Reference

Output SF/RF VFD Fault Reset Output SF/RF VFD External Fault (Kill VFDs) Output SF VFD S/S Output RF VFD S/S Output SF Speed Ref Output RF Speed Ref Output OAD/MAD Position Ref Output Relief Damper Position Ref Output Humidifier Ref Output Humidifier enable Output Preheat Valve Ref Output Cooling Valve Ref Output Enable/Disable UV

BACnet OA flow station BACnet RA flow station BACnet SA Flow station BACnet Humidifier BACnet SA Fan array drive BACnet RA Fan array drive BACnet Thermal Energy Control Valve

HHSI Page 23 of 33

Attachment – G AHU 2A applicable print

HHSI Page 24 of 33

Attachment H - AHU2A applicable print

HHSI Page 25 of 33

Attachment I - AHU2A/2B Enclosure

HHSI Page 26 of 33

Attachment – J AHU SCHEDULES

HHSI Page 27 of 33

Attachment – K AHU IMAGES

View of AHU2A/2B penthouse facing north. Note double-doors.

View of area most likely to be utilized for crane operations. Note the uneven shipping docks. This is looking south, over the roofline.

Chilled water piping currently supplying AHU2A.

HHSI Page 28 of 33

Attachment – K cont. AHU IMAGES

Steam supply penetration. Heating water pipes to dock heaters (2”). Chilled water pipes.

Support Services interstitial space viewed facing south from access nearest entrance of space.

Unit heater. Note the steam supply line tee visible by the overhead light.

East side of AHU looking south.

HHSI Page 29 of 33

AHU2A west side looking northeast.

Gas line protruding into penthouse for humidifier.

Existing unitary controller. AHU2A is to the right.

HHSI Page 30 of 33

Close up of wire-way containing power cables supplying AHUs.

Breaker panel supplying power to AHU2A. This is located within the penthouse for AHU1B.

View looking west. AHU2A/2B penthouse located to the left in the background. AHU1B penthouse is visible to the right in the foreground.

HHSI Page 31 of 33

Panel schedule for panel PDH1, which supplies AHU2A.

AHU2A supply fan breaker.

AHU2A return fan breaker.

HHSI Page 32 of 33

Front panel labels for PDH1.

HHSI Page 33 of 33

Attachment – L