This is a Statement of Work (SOW) issued by the U.S. Department of Agriculture, Agricultural Research Service, for the supply and installation of two 30-ton HVAC chillers at Building 13 of the Poultry Research Unit located at 606 Spring Street, MS State, Mississippi 39762 (Asset ID: 640600B013).
The contractor must provide all materials, labor, and equipment to demolish the existing 12-year-old 30-ton Carrier chiller and install two new matching 30-ton air-cooled chillers (Trane, Carrier, or approved equal) on a modified concrete equipment pad. Services must be performed by a Mississippi-licensed contractor. The work includes modifying the existing concrete pad per specifications, installing the two chillers programmed for lead-lag operation if the electrical panel permits (or single-unit operation as alternative), installing a Bell & Gossett Series e-90 chilled water pump with variable frequency drive, performing factory-certified startup, heat-tracing and insulating all exterior piping to match existing standards, and disposing of all debris at an off-site location. The project completion deadline is 120 calendar days from the Notice to Proceed, with a detailed project schedule due 14 days after award. Work hours are 7:00 a.m. to 3:30 p.m., Monday through Friday, excluding federal holidays. The contractor must obtain all required building and trade permits, submit a site safety plan within 14 days of award, coordinate with USDA personnel to schedule service interruptions, comply with local, state, and national building codes, provide quality control oversight, and maintain the site free of debris. Final payment requires submission of Release of Liens, Release of Claims, Employee Payroll/Timesheets, and Invoice.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Sign-In 05202026.pdf | ||
| Site Visit Sign-In 05212026.pdf | ||
| SF30 - Amendment 01.pdf | ||
| RFIs.pdf | ||
| Wage Determination.pdf | ||
| SF-1442.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agricultural Research Service
U.S. DEPARTMENT OF AGRICULTURE
Last Updated 4/10/2026
STATEMENT OF WORK
Supply and Install 2 - 30 Ton HVAC Chillers for Building 13
Poultry Research Unit 606 Spring Street
MS State, Mississippi 39762
Asset ID: 640600B013
Install B-13 Chillers Page 2 of 10
1. PROJECT INTRODUCTION
1.1. PROJECT TITLE
Supply and Install 2 – 30 Ton Chillers at Building 13.
1.2. PROJECT BACKGROUND AND PURPOSE
The United States Department of Agriculture (USDA), Agricultural Research Service (ARS), Poultry Research Unit is housed in its own fenced-in compound at 606 Spring Street, MS State, MS 39762. Some of the live bird related research activities for this unit are housed in Building 13 which was originally built in 1966. Building 13 is served by a single 30 ton Carrier chiller which was manufactured in 2014. In 2020, the present HVAC system was designed and installed utilizing the existing 30 Ton Carrier Chiller.
Excerpts from the stamped plan sheets are included in this SOW and are available for inspection. The present 12 year old chiller is experiencing some issues which have been addressed with a temporary chiller. Due to the lack of redundancy of the cooling system, the research housed in this building is presently in jeopardy should these repairs fail. The purpose of this project is to restore the cooling portion of the HVAC system and provide needed redundancy by demolishing the existing 30 ton Carrier Chiller and replacing it with 2 – 30 ton chillers which will be programmed to operate lead lag with an alternating schedule. The present electrical, plumbing, and controls shall be modified under this contract to work in concert with the remainder of the existing B-13 HVAC system to provide the necessary conditioned air for the poultry research housed in the building. The contractor will need to coordinate with USDA Location personnel to schedule service interruptions and perform the installation in accordance with local, state, and national building codes.
2. SCOPE AND OBJECTIVES
2.1. DESCRIPTION OF WORK
Provide all materials, labor, and equipment to install two new 30 ton air cooled chillers, concrete slab, and all necessary equipment, controls, electrical, and plumbing to deliver a fully functional HVAC system for Building 13. Contractor services must be performed by a Mississippi Licensed Contractor.
2.1.1. Existing concrete equipment pad shall be modified to accommodate the new chillers and shall comply with the detail below. Chillers must be oriented and positioned to provide adequate maintenance access.
Install B-13 Chillers Page 3 of 10
2.1.2. Demolish existing chiller and install 2 new, matching 30 ton air cooled chillers (Trane, Carrier, or approved equal) on the modified and sufficiently cured concrete equipment pad. These units will be programmed to operate preferably in a lead lag chiller operation if the current electrical panel will accommodate. If the existing electrical panel cannot accommodate the necessary electrical connection, the controls shall be modified so that only one chiller can be operational at a time. The requisite electrical connection work, plumbing, controls, etc. for the new chillers are to be installed by the contractor under this contract to work in concert with the remainder of the existing circa 2020 B-13 HVAC system to provide the necessary conditioned air for the poultry research housed in the building. All exterior piping is to be heat traced, insulated, and jacketed in a similar fashion to the existing piping. The contractor shall coordinate with USDA Location personnel to schedule service interruptions and perform the installation in accordance with local, state, and national building codes.
Install B-13 Chillers Page 4 of 10
2.1.3. Install a Bell & Gossett Series e-90 close-coupled in-line centrifugal chilled water pump immediately adjacent to the existing chilled water pump, a variable frequency drive to operate both chilled water pumps, together will all requisite plumbing and electrical work to provide a fully functional chilled water system.
2.1.4. Perform Factory Certified Startup and operate unit
2.1.5. Clean up all debris and dispose at a proper location off site.
2.2. The Contractor will verify all dimensions and site conditions prior to beginning work. No Government equipment will be available for use by the Contractor. The Contractor must provide their own restroom facility.
2.3. LOCATION OF WORK
The project is located at 606 Spring Street, MS State, Mississippi 39762.
Install B-13 Chillers Page 5 of 10
3. PROJECT SCHEDULE
3.1. The completion of the project must not exceed one hundred and twenty (120) calendar days from the date of the Notice to Proceed (NTP).
3.2. The Contractor must prepare an overall project schedule including milestone dates for all phases of work and completion date; submit to the COR for approval. This schedule is due fourteen (14) days after contract award. The Contractor must track all work progress to ensure that the project is completed according to the schedule. Include work week schedule with daily starting and stopping time.
3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If necessary, any request for a time extension must be submitted to the Contracting Officer in writing before the expiration of the Period of Performance. Each request must include specific and detailed reasons in support of the schedule alteration and provide an updated schedule for completion. No extension of the period of performance may be given without the written authority of the CO.
3.4. Project work hours are 7:00 am and 3:30 pm, local time, Monday through Friday; federal holidays excluded. The contractor is not required to provide services on recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work schedule must be submitted to CO for written approval prior to any schedule change.
Install B-13 Chillers Page 6 of 10
3.5. This work location is inside of a locked compound that houses animal research, therefore site security and animal welfare are serious concerns due to disease transmission, etc. All work must be coordinated with the LPOC and RL to ensure that safety and health protocols are observed and the research animals as well as workers are protected.
4. GENERAL REQUIREEMENTS
4.1. PERMITS
The Contractor must obtain all building and trade permits necessary to include any drawings, plans, permit and inspection fees, utility location, site surveys, and any other items necessary for compliance with state, local, and federal building authorities.
4.2. SAFETY
The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (Plan) in industry recognizable format to the COR within Fourteen (14) days of contract award. The Plan must include phone numbers and maps to local physician offices and the nearest hospital. The Government will review and approve the Plan before issuance of the NTP.
4.3. EXISTING INSTALLATIONS/DEMOLITION
Coordinate all activities with COR. All disruptions of existing systems must be coordinated with the COR to prevent disconnecting equipment that may jeopardize on-going research.
4.4. QUALITY CONTROL
Provide quality control to ensure that all components of project work meet the requirements of the contract specifications. Ensure that all work not acceptable or compliant with the specifications is corrected prior to inspection or review by the COR. Quality control is the exclusive responsibility of the Contractor.
4.5. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS
4.5.1. The Contractor must protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work.
Any damage to property must be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.
4.5.2. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor must furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
4.5.3. Open depressions and excavations occurring as part of this work must be adequately barricaded or fenced to prevent vehicle or pedestrian traffic into the work area.
4.5.4. Provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public and workers and to the occupants of adjacent premises and surrounding areas.
Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.
Install B-13 Chillers Page 7 of 10
4.5.5. The contract documents may not represent all surface conditions at the site and adjoining areas.
The known surface conditions are as indicated and must be compared with actual conditions before commencement of work and the cost must be included in the Contractor’s quote.
4.5.6. The Government will not furnish any labor or equipment to unload or move materials or supplies.
5. UTILIZATION OF BIOBASED PRODUCTS
The Contractor must utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the Government. All supplies and materials must be of a type and quality that conform to the applicable federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: www.biopreferred.gov.
6. HAZARDOUS MATERIAL
Building 13 is not suspected to contain asbestos containing materials or lead based paint that would be involved in the work of this project. Existing conditions are reflected correctly to the best of USDA’s knowledge. The USDA makes no representation, warranty, or guaranty that the conditions indicated either are representative of those conditions existing throughout the area, or that unforeseen developments may not occur, or that materials other than, or proportions different from those indicated may not exist. If hazardous materials are found to be present, it must be reported to the CO & COR for further action.
7. DISPOSAL OF REMOVED MATERIALS AND DEBRIS
7.1. The Contractor must dispose of removed, materials, waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.
7.2. Burying of trash and debris on the site is prohibited. Burning of trash and debris at the site is prohibited.
7.3. Remove trash and debris from the site at frequent intervals so that its presence will not delay the progress of the work or cause hazardous conditions for workers and the public.
7.4. Removed materials, trash, and debris must become the property of the Contractor and must be removed from the project site and be disposed of in a legal manner. Location of disposal site and length of haul are the Contractor's responsibility.
7.5. The contractor should make every effort to recycle as much of the construction debris as possible.
7.6. Any waste materials encountered during the demolition that are found to contain lead, asbestos, polychlorinated biphenyls (PCB), fluorescent lamps, or any hazardous substances are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste as well as any specific hazardous waste requirements stated in different sections.
7.7. Comply with hauling and disposal regulations of authorities having jurisdiction, per federal, state, and local requirements.
http://www.biopreferred.gov/
Install B-13 Chillers Page 8 of 10
8. TEMPORARY FACILITIES
Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor must maintain and protect all such utilities during the course of construction and must repair or replace any items damaged through its own actions. Should the Contractor require any power or utility shutdowns during construction, the Contractor must obtain approval for such shutdown from the COR three (3) working days prior to the need.
9. CLEANUP
The construction site must be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor must remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
10. SUBMITTALS
Submittals on all material incorporated into the work, including shop drawings and specifications used on this project must be submitted to the EPM, COR, and Contracting Specialist. Electronic submittals are acceptable, otherwise three (3) written submittals are required.
10.1. Project Schedule within fourteen (14) calendar days of award (see Section 3.2).
10.2. Safety Plan within fourteen (14) days of award (see Section 4.2).
10.3. Any additional material, including shop drawings and specifications, used on this project.
11. INSPECTION AND ACCEPTANCE
A government representative will inspect and approve the work performed on this project. The Contractor must schedule inspection a minimum of three (3) days in advance, in writing, to the COR and CO.
12. FINAL PAYMENT/CONTRACT CLOSEOUT
The following documents are required prior to final payment (other documents may also be required):
Release of Liens, Release of Claims, Employee Payroll\Timesheets, and Invoice.
Install B-13 Chillers Page 9 of 10
13. Schematics
Install B-13 Chillers Page 10 of 10