Statement_of_Work.pdf
PDF 105 KB Posted
- Solicitation number
- 140P5426R0005
About this file
This is a Statement of Work (SOW) for replenishing the FOCA Pier Revetment Landing Rip Rap project. The work addresses severe sloughing and erosion seaward of the existing in-place rip rap at the pier's shore-side base. The contractor must prepare the site, re-adjust and stabilize the current rip rap, and add up to 60 cubic yards of Type III Granite Rip Rap centered 30 linear feet along the pier footing while maintaining a 2:1 slope. All work must comply with USACOE permit #SAJ-2000-03468.
The contractor is responsible for providing all labor, materials, and equipment except as noted. Required tasks include: installing temporary safety measures (barriers, temporary fencing) and a soil retention cloth barrier along the waterside of the staging area; providing and placing 60 cubic yards of Type III Granite Rip Rap with advance sample approval; re-adjusting existing rip rap to create a stable base for additional material; cleaning and restoring staging and work areas with debris disposal; removing temporary safety measures and soil retention barriers; and demobilization. The National Park Service will provide the staging area if needed and will remove the wooden boardwalk prior to contract start. The contractor may locate a dumpster in the staging area as needed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P5426R0005_Amd_0001.pdf | ||
| Pier_USACOE_20230918-Permit_NWP-13.pdf | ||
| Past_Performance_Questionnaire.pdf | ||
| Wage_Determination.pdf | ||
| Photos__Blueprints__and_Drawings.pdf | ||
| Sol_140P5426R0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPLENISH FOCA PIER REVETMENT LANDING RIP RAP
This project is to replenish the FOCA Pier Revetment Landing Rip Rap. It will result in the filling in of the severe sloughing and erosion seaward of the in-place Rip Rap from the shore-side base of the pier. (See pictures). The contractor will be responsible for preparing the site, re-adjusting/stabilize the current Rip Rap & then adding up to an additional 60 CU/YDS of type III Granite Rip Rap, centered 30 LF along the pier footing (See the 2 sketches) to maintain a Slope of 2:1. All work will be done in accordance with the USACOE permit # SAJ-2000-03468 (Attached)
THE FOLLOWING IS A PROPOSAL FOR THE WORK TO BE PERFORMED:
Contractor will provide all labor, materials & equipment unless specifically noted below;
1. Install Temporary Safety measures for the work area, staging area and trail system (barriers, temporary fence, etc.). Install soil retention cloth barrier along waterside of the staging area.
2. Provide 60 CY of Type III Granite Rip-Rap (sample will be submitted in advance for approval). Staging area, if needed, will be provided by the NPS. See attached Map.
3. Re-Adjust current Rip Rap allowing for a stable base to place the additional Rip Rap to infill area as shown on the attached drawings. Slope of 2:1 must be maintained.
4. Clean/restore staging and work areas and dispose of all debris. Contractor Dumpster can be located in the staging area if needed/desired.
5. Remove temporary safety measures/soil retention cloth barrier.
6. Demobilize
The government will remove the wooden Boardwalk prior to start of contract.