Engine Overhaul/Replacement for TA-35 Tow Tracker. Federal contract opportunity
Solicitation number
20270PR25000341
Issued by
Department of Homeland Security US Coast Guard

About this file

This Statement of Work (SOW) details the requirements for overhauling or replacing a 6BT 5.9L engine (Serial Number: 44308086) in a TA-35 tow tractor at the United States Coast Guard (USCG) Air Station in Kodiak, Alaska. The project offers two options: (1) rebuild the existing engine, including cylinder repairs and component replacement, or (2) replace the engine with a pre-rebuilt unit. The work involves removing the current engine, installing a new or rebuilt engine, transferring necessary components, and replacing the oil cooler.

The project is scheduled to begin within 3 weeks of contract award and be completed within 12 weeks, with post-work reporting expected by 14 weeks after award. The contractor is responsible for providing qualified personnel, ensuring repair procedures meet manufacturer specifications and safety standards, managing travel logistics, and delivering comprehensive documentation. Acceptance criteria include successful engine removal/replacement, functional testing, and timely submission of a detailed report. The entire project will be performed at the USCG Air Station Kodiak, with the Coast Guard facilitating access to facilities, equipment, and coordination support.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Project Title:

6BT Engine Overhaul or Replacement for TA-35 Tow Tractor

1. Introduction

This Statement of Work (SOW) outlines the requirements for the overhaul or replacement of a 6BT 5.9L engine (Serial Number: 44308086) used in a TA-35 tow tractor. The work includes two options:

1. Option 1: Rebuild the existing engine.

2. Option 2: Replace the existing engine with an already rebuilt engine.

The work will include the removal of the current engine, installation of a new or rebuilt engine, and the transfer of components from the old engine to the new engine as needed. The engine will also require a new oil cooler. All work will be performed at USCG Air Station Kodiak and is scheduled to be completed 12 weeks after award.

2. Objectives

• Remove the existing 6BT engine from the TA-35 tow tractor.

• Provide two options for execution:

o Option 1: Rebuild the existing engine, including cylinder repairs and replacement of defective components.

o Option 2: Replace the existing engine with an already rebuilt engine.

• Install the rebuilt or replacement engine into the TA-35 tow tractor.

• Transfer components from the old engine to the new/rebuilt engine as needed.

• Replace oil cooler.

• Conduct functional testing to verify proper operation of the engine.

• Provide documentation of the process, including diagnostics, repairs performed, and recommendations for future maintenance.

3. Scope of Work

The contractor shall:

• Travel to Air Station Kodiak Alaska: Ensure all logistics are coordinated for the engine replacement or overhaul process.

• Engine Removal:

o Remove the existing 6BT engine (Serial Number: 44308086) from the TA-35 tow tractor.

o Prepare the engine for either overhaul or replacement.

Option 1: Rebuild the Existing Engine

• Disassemble the engine to the bare block.

• Inspect all components for wear, damage, and defects.

• Send the engine block to a machine shop for cylinder repairs (including damage to #5 and

#1 cylinders).

• Replace the oil cooler with a new unit.

• Replace or repair defective components, including bearings, gaskets, pistons, and other critical parts.

• Reassemble the engine using repaired or replacement components.

Option 2: Replace the Engine with an Already Rebuilt Engine

• Install a rebuilt 6BT engine that meets manufacturer specifications.

• Transfer components from the old engine to the rebuilt engine as needed (e.g., mounting brackets, accessories).

• Replace the oil cooler with a new unit.

• Reinstallation and Testing:

o Install the rebuilt or replacement engine into the TA-35 tow tractor.

o Conduct functional testing to ensure proper operation of the engine.

• Documentation:

o Provide a detailed report of the process, including diagnostics, repairs performed, parts replaced, and recommendations for future maintenance.

4. Tasks and Deliverables

Task 1: Pre-Work Coordination

• Coordinate logistics (travel, accommodations, workspace setup) with USCG Air Station Kodiak.

Task 2: Engine Removal

• Remove the existing engine from the TA-35 tow tractor.

• Inspect the engine and determine the appropriate option (rebuild or replacement).

Task 3: Execution of Option 1 or Option 2

• Option 1: Rebuild the existing engine, including cylinder repairs, replacement of defective components, and reassembly.

• Option 2: Replace the existing engine with an already rebuilt engine, transferring components as needed.

Task 4: Engine Reinstallation and Testing

• Install the rebuilt or replacement engine into the TA-35 tow tractor.

• Conduct functional testing to ensure proper operation.

Task 5: Documentation and Reporting

• Provide a detailed report of the process, including diagnostics, repairs performed, parts replaced, and recommendations for future maintenance.

Deliverable: Detailed report and confirmation of successful engine operation.

5. Period of Performance

The work is scheduled to begin within 3 weeks of the award and be completed by 12 weeks after award Pre-work coordination will commence upon contract award, and post-work reporting is expected by 14 weeks after award.

6. Place of Performance

The work will be performed at USCG Air Station Kodiak.

7. Responsibilities

Contractor:

• Provide qualified personnel to perform the engine overhaul or replacement.

• Ensure all repair and reassembly procedures meet manufacturer specifications and safety standards.

• Manage all aspects of travel and logistics for their team.

• Deliver all documentation and reports as outlined in this SOW.

USCG Air Station Kodiak:

• Provide access to facilities and equipment.

• Facilitate coordination with relevant personnel to support the activities.

• Ensure timely feedback and communication throughout the process.

8. Acceptance Criteria

• Successful removal, repair/replacement, reassembly, and reinstallation of the 6BT engine.

• Successful functional testing and operational verification of the engine in the TA-35 tow tractor.

• Submission of all deliverables (report) within the specified timelines.

1. Introduction
2. Objectives
3. Scope of Work
Option 1: Rebuild the Existing Engine
Option 2: Replace the Engine with an Already Rebuilt Engine
4. Tasks and Deliverables
5. Period of Performance
6. Place of Performance
7. Responsibilities
8. Acceptance Criteria