This Statement of Work (SOW) details a contract for the Bureau of Alcohol, Tobacco, Firearms and Explosives (ATF) National Center for Explosives Training and Research (NCETR) at Redstone Arsenal in Huntsville, Alabama. The contract requires a contractor to provide custom test fabrication and onsite support for the SQRL IV Test Structures, which involves preparing and supporting explosive research testing. Key tasks include site preparation, fabrication of 5 specific CMU (concrete masonry unit) buildings with varying wall and roof configurations, daily labor during testing, demolition of existing structures, and potential rebuilding of CMU buildings.

The project timeline spans from August 2025 to April 2026, with contract award in August 2025, construction from August to November 2025, testing in February 2026, and demolition/potential rebuilding in March-April 2026. The contractor must provide a 2-person crew for 120 hours, all necessary tools and supplies, and perform precise construction and repair tasks between test shots. The buildings will have specific technical requirements, including 20 1-inch holes drilled through CMU walls, no lintels over openings, and 50% roof material overage for wooden-roof buildings. The performance location is ATF's McKinley Delta Range, Blast House at Redstone Arsenal, with a period of performance from September 1, 2025 to August 31, 2026.

View the file

Other files for this federal contract opportunity

Other files attached to Range Custom Test Fabrication, Onsite Support, SQRL IV, newest first.
File Type Posted
IFB 15A00025B00000113 Amendment 0002.pdf PDF
IFB 15A00025B00000113 Amendment 0001.pdf PDF
IFB 15A00025B00000113.pdf PDF
Past Performance Questionnaire.docx DOCX document
DBA - Madison County AL.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bureau of Alcohol, Tobacco, Firearms and Explosives National Center for Explosives Training and Research

Statement of Work Custom Test Fabrication, Onsite Support, SQRL IV

1 BACKGROUND

The Bureau of Alcohol, Tobacco, Firearms and Explosives (ATF) National Center for Explosives Training and Research (NCETR) is located on Redstone Arsenal in Huntsville, Alabama. NCETR staff conduct research in support of enhancing the prosecution of explosives cases to serve ATF and the larger law enforcement community, improving the safe disposal of explosives, and improving the safe storage of explosives. NCETR maintains several laboratory facilities on Redstone Arsenal in support of the explosives research mission.

1.1 ORGANIZATION

The National Center for Explosives Training and Research (NCETR) is located on Redstone Arsenal, Huntsville, AL. (Madison County). NCETR’s main facility is home to the Bureau of Alcohol, Tobacco, Firearms and Explosives (ATF) explosives training and research programs.

The NCETR facility maintains proprietary control of approximately 1,000 acres of land that is comprised of one training and research building containing three laboratories and three explosive range complexes, which contain additional classrooms and laboratories. These ranges and laboratories possess assets that are a unique resource in the mission against explosive-related crime and the counter-improvised explosives device effort.

1.2 SCOPE

The objective of this contract is to provide labor for onsite personnel support for the test execution phase, and for custom pre-test fabrication for the SQRL IV Test Structures.

1.3 OBJECTIVE(S)

The objective of this requirement is to provide ATF with pre-testing fabrication of custom CMU buildings, as well as onsite personnel to support the quick and efficient fabrication of custom test articles during the SQRL IV testing.

2 REQUIRED TASKS

The following phases will constitute the scope of work.

Phase 1: Site Prep

• Removal and disposal of wooden decking.

• Relocation of sand from the Blast house area to a dump area nearby within range.

• Demolition and removal of (1) existing CMU building.

• Extend foundation of existing CMU by 1’ around

• Pouring of (4) new CMU foundations o 2 will match elevation of existing CMU foundation o 2 will match elevation of existing Blast House

• Pouring of (2) new Concrete Pads around these (2) sets of CMU foundation pad.

Overall area of each pad is (75’ x 37’) with the 3 foundations in each pad area.

• Gravel base then 6” pad poured (with reinforcement) to be able to withstand machinery weight, without cracking.

Phase 2A: Fabrication

• Fabrication of (5) CMU buildings 13’4” x 13’4” x 10’ (exterior dimension)

• Building Matrix:

Building # Wall Roof CMU-1 Un-grouted Wood-Bearing CMU-2 Partially grouted Wood-Bearing CMU-3 Fully grouted Wood-Hanging CMU-4 Partially grouted Concrete CMU-5 Fully grouted Concrete

• Building # Locations:

• Walls:

o Un-grouted = No Rebar no grout o Partially grouted = #4 rebar with grout every 24 inches

Walls to be marked at base indicating which cells have rebar o Fully grouted = #4 rebar every 24 inches, grout in all cells

Walls to be marked at base indicating which cells have rebar

• Roof:

o Wood-Bearing:

• Wood-Hanging:

• Concrete:

• All Finished buildings will have the following overall requirements.

o Must include (20) 1” Holes drilled through CMU all around.

o No Lintel over doors or vent opening.

• The 3 wooden roof buildings will include 50% overage of roof material for repair during testing

Phase 2B: Daily Labor (During Testing), Each Day:

• (2) ATF Cleared Technicians onsite during testing for reset / repair of roofing or other Cell needs for a time frame of 120 hours

• Between shots, wood framed elements will be repaired to the greatest extent possible to allow re-use of test structures for multiple shots

• Work will be completed between tests in an expedited fashion to maintain schedule.

Phase 3: Demolition

• Demolition and removal of a minimum of (2) and upwards of (5) existing CMU buildings.

• Clean pad and surroundings of any material and debris.

Phase 4: Rebuild

• Price each CMU # 1-5 individually as an option to build

2.1 Estimated timeline is as follows:

DRAFT Timeline

Aug 2025 Contract Award August - September 2025 Construction Begins

November 2025 Construction completed

February 2026 Testing occurs, Onsite Support March 2026 – April 2026 Demolition and Removal of existing CMU buildings, clean pads of materials and debris, disposal

April 2026 Rebuild CMU building

Please keep in mind that the timeframe may shift right or left depending on weather and range availability.

2.2 All construction supplies and materials will be provided by the Contractor, including all tools and equipment necessary to quickly and efficiently perform the custom test fabrication, brooms, flat shovel for debris pickup, garbage cans for moving debris to Dumpster Area, Generator, Chairs or any Personal Items including lunches and drinks.

The Government will provide Dumpsters and onsite Port-A-Toilets.

2.2.1 Throughout the day between test shots, it will be necessary to replace plywood on ceiling if needed, and / or fix framing issues. These repairs must be performed with accuracy and precision, with no additional nail holes.

2.2.2 Clean the entire interior floor and exterior test area are of debris between shots.

2.2.3 Downtime should be anticipated during shots and throughout the day. Contractors should remain available onsite during downtime and prepared to execute test fabrication when the need arises.

2.2.4 The contractor shall provide all parts and tools to successfully, efficiently, and quickly complete the custom test fabrication required by the Government.

Test Structures will be constructed per the plan views as follows in Figure 1.

3 DELIVERABLES

The contractor shall ensure the accuracy, completeness, professional quality, and overall compliance with government guidelines/requirements of the deliverables.

3.1 The contractor shall provide the following:

Labor: 2 Man Crew, 120 hours All Necessary Tools and supplies to Complete the Tasks Required

3.2 DELIVERY SCHEDULE

Section Title Due Date Distribution

3 PCR Upon Request BC/COR

4 CONTRACTOR PERSONNEL

It is the contractor’s responsibility to; provide sufficiently educated/trained staff to perform the requirements of this contract and; to ensure an adequate level of support is maintained at all times.

5 KEY PERSONNEL

Not Applicable.

6 PLACE OF PERFORMANCE

The place of performance will be at ATF’s McKinley Delta Range, Blast House; located at Redstone Arsenal, Huntsville, AL.

7 PERIOD OF PERFORMANCE

The period of performance of this requirement is from September 1, 2025 to August 31, 2026.

8 OTHER CONSIDERATIONS

Not applicable.

8.1 TRAVEL

Not applicable.

8.2 SECURITY

No background investigations are required. However, any representative from the contractor company who is required to visit the NCETR facility will be subject to police records check to gain access to Redstone Arsenal and the ATF NCETR facilities. Access to Redstone Arsenal, AL is required to complete this task.

8.3 CONTRACTING OFFICER’S REPRESENTATIVE (COR):

COR: TBD

1 BACKGROUND
1.1 ORGANIZATION
1.2 SCOPE
1.3 OBJECTIVE(S)
2 REQUIRED TASKS
2.1 Estimated timeline is as follows:
DRAFT Timeline
Aug 2025 Contract Award
2.2 All construction supplies and materials will be provided by the Contractor, including all tools and equipment necessary to quickly and efficiently perform the custom test fabrication, brooms, flat shovel for debris pickup, garbage cans for moving ...
2.2.1 Throughout the day between test shots, it will be necessary to replace plywood on ceiling if needed, and / or fix framing issues. These repairs must be performed with accuracy and precision, with no additional nail holes.
2.2.2 Clean the entire interior floor and exterior test area are of debris between shots.
2.2.3 Downtime should be anticipated during shots and throughout the day. Contractors should remain available onsite during downtime and prepared to execute test fabrication when the need arises.
2.2.4 The contractor shall provide all parts and tools to successfully, efficiently, and quickly complete the custom test fabrication required by the Government.
3 DELIVERABLES
3.1 The contractor shall provide the following:
3.2 DELIVERY SCHEDULE
4 CONTRACTOR PERSONNEL
5 KEY PERSONNEL
6 PLACE OF PERFORMANCE
7 PERIOD OF PERFORMANCE
8 OTHER CONSIDERATIONS
8.1 TRAVEL
8.2 SECURITY
8.3 CONTRACTING OFFICER’S REPRESENTATIVE (COR):