Statement of Work.pdf

PDF 204 KB Posted

Attached to
Replace HVAC unit in B1, Room PB4 (Athens, GA) Federal contract opportunity
Solicitation number
1232SA25Q0458
Issued by
Department of Agriculture Agricultural Research Service

About this file

This Statement of Work (SOW) details the replacement of a water-cooled packaged HVAC unit at the U.S. National Poultry Research Center in Athens, Georgia. The project requires a contractor to provide all professional services, labor, equipment, and materials to replace the existing water source heat pump HVAC unit in B1, Room PB4 with a new unit of equivalent capacity. Specific requirements include connecting to existing supply duct, condenser loop, and electrical service; modifying the duct system for proper fresh air intake; ensuring the new unit supports BACNet communications; and providing a minimum 5-year compressor warranty with a local authorized service provider within 60 miles.

The project is a total small business set-aside under NAICS Code 238220 with a size standard of $19M, with the contract value estimated between $25,000 and $100,000. The work must be completed within 180 days of the notice to proceed, with most work performed Monday through Friday from 7:00 AM to 4:30 PM. The contractor will be responsible for site safety, property protection, material submittals, and providing a one-year guarantee on workmanship. The facility will remain occupied during construction, requiring careful coordination to minimize disruption to daily operations and research programs.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Agricultural Research Service

STATEMENT OF WORK

Replace HVAC unit in B1, Room PB4

U.S. National Poultry Research Center 950 College Station Road

Athens, Georgia 30605

1. Scope of Work

The contractor shall provide all professional services necessary to replace the existing water source heat pump HVAC unit serving the PB4 area with a new unit of the same capacity.

The contractor shall include all services and field labor, equipment (including cranes, rigging and material handling equipment), materials, testing and personal protective equipment necessary to perform the work.

Equipment and services provided by the Government for contractor use are listed below:

- None provided

1.1 Base Bid

The contractor shall provide a detailed proposal and cost breakdown for the entire project including submittals for proposed equipment and materials.

1.2 Site Visit

Contractors are strongly encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid.

2. Codes and Standards

Applicable Codes and Standards apply and are not limited to the following

ANSI - American National Standards Institute.

ASME - American Society of Mechanical Engineers.

NEC - National Electrical Code, NFPA 72.

OSHA - Occupational Safety and Health Administration ADA – Americans with Disabilities Act

All work must meet Local, State and Federal codes, and latest IBC codes.

3. Project Summary

Replace existing water-cooled packaged HVAC unit.

1) Connect to existing supply duct, condenser loop and electrical service

2) Modify duct system as needed to ensure proper fresh air intake

3) New unit shall be equipped for BACNet communications with existing BAS (connection by others)

4) Minimum 5 year compressor warranty by unit manufacturer

5) Unit must have local authorized service provider (within 60 miles of location)

The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to traffic, daily operations and research programs.

4. Safety

The contractor will submit a Site Safety Specific Plan (SSSP) in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.

Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor.

The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel.

5. Contractor Requirements

The contractor shall provide a complete and func onal installa on, including all labor, supervision, tools, materials, equipment, apparatus, transporta on, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.

The project work shall be performed per the following guidelines:

1) Contractor will verify all dimensions and site conditions prior to beginning work.

2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.

3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site weekly.

4) Contractor is required to manage the project and consult with the Government prior to beginning all work.

5) Contractor shall perform work in a manner that minimizes the impact to daily opera ons of the facility and its workers. The building will be occupied during construc on work.

6) All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances, and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.

6. Material Submittals

Submittals and O&M documentation must be provided for all materials used on this project.

7. Pre-Construction Submittals

Contractor’s Site Specific Safety Plan (SSSP) must be provided to and approved by USDA before installation can begin.

8. Damage to Property:

The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the USDA.

9. Inspection and Acceptance A government representative shall inspect and approve the work. The Contractor shall schedule inspection a minimum of 2 days in advance.

10. Period of Performance

The completion of this project shall not exceed 180 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

10.1 Work Hours:

Generally, contractor work hours shall be Monday through Friday, 7:00 A.M. to 4:30 P.M. except on Government holidays for most of the installation work. Tie-in or other work requiring outages will be performed after hours (pre-arranged at least 48 hours in advance).

Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to the schedule change.

11. Guaranty

The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period of one (1) year from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.