REPLACE FUEL SYSTEM LINES & COMPONENTS AT DRY TORT Federal contract opportunity
Solicitation number
140P5425R0014
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This Statement of Work (SOW) details a utility repair project for the Garden Key Waterfront at Dry Tortugas National Park. The project involves replacing damaged utility infrastructure caused by tropical storm events in Fall 2024, specifically focusing on repairing four critical systems: a diesel delivery line, gasoline fuel line, 208vac electrical feeders, and 120vac electrical lines. The work requires relocating these utilities to higher ground away from the shoreline, using new coaxial double-wall piping, and installing new conduits and electrical connections.

The project is to be completed within 45 days after contract award, with specific requirements including obtaining necessary permits from the Florida Department of Environmental Protection, submitting a detailed safety plan, and following strict environmental compliance guidelines. Contractors must navigate challenging logistics, including transportation to the remote location via ferry or seaplane, limited park housing for up to 6 crew members, and working within specified hours (8:00 am to 6:00 pm, Monday through Saturday). The project also requires careful planning for potential hurricane evacuations and adherence to strict safety and environmental regulations.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE FUEL SYSTEM LINES & COMPONENTS AT DRY TORT, newest first.
File Type Posted
Sol_140P5425R0014_Amd_0001.pdf PDF
Questions_and_Answers_0001.pdf PDF
Sol_140P5425R0014.pdf PDF
Drawings.pdf PDF
Past_Performance_Questionnaire.pdf PDF
Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

Garden Key Waterfront Utility Repairs Statement of Work DRTO Page 1 of 9

Replace Diesel and Gasoline Fuel Piping, Electrical Lines, Transition Sump

Garden Key Waterfront

Dry Tortugas National Park

PMIS 343767A

April 2025

DRTO Page 2 of 9

NATIONAL PARK SERVICE

TABLE OF CONTENTS

1. PARK INTRODUCTION

2. PROJECT OVERVIEW

3.REQUIRED SERVICES / TASKS……………………………………………………………………………………………….…………….4-5

4. OTHER CONTRACTOR REQUIREMENTS…………………………………………………………………………………………..…………………….6

5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES

6. SITE VISITS

7. PARK HOUSING ...................................................................................................................................................... 7-7

8. TELEPHONE/INTERNET

9. WORKING HOURS

10. PERIOD OF PERFORMANCE

11. SAFETY AND ENVIRONEMTN COMPLIANCE

12. GENERAL TREATMENT

13. EMPLOYEE IDENTIFICATION

14. SUBMITTAL REQUIREMENTS (POST AWARD) ...................................................................................................... 8-9

15. ATTACHEMENTS………………………………………………………………………………………………………………………………………………..9

ACRONYMS

CFR Code of Federal Regulations CO Contracting Officer COR Contracting Officer’s Representative CP Competent Persons DRTO Dry Tortugas National Park EPA Environmental Protection Agency NPS National Park Service OSHA Occupational Safety and Health Administration PM Project Manager PMIS Project Management Information System SOW Statement of Work

DRTO Page 3 of 9

1. PARK INTRODUCTION

Almost 70 miles (113 km) west of Key West lies the remote Dry Tortugas National Park. This 100-square mile park is mostly open water with seven small islands. Accessible only by boat or seaplane, the park is known the world over as the home of magnificent Fort Jefferson, picturesque blue waters, superlative coral reefs and marine life, and the vast assortment of bird and aquatic life that frequents the area.

Fort Jefferson is a 19th century “Third System” coastal defense fortification located approximately 60 nautical miles west of Key West, Florida in the Gulf of Mexico. Military engineers began construction on the fort in 1846 and stopped before it was completed in 1874. It was part of an organized effort by the United States government beginning in 1817 to generate a system of national defense. Each of these coastal defense works were designed to contain artillery, garrisons, and magazines of which could defend against an attack until further reinforcements could be dispatched. Fort Jefferson represents one of the highest achievements of 19th century American military architecture and engineering and is one of the largest Third System forts constructed. The hexagonal fortification has three tiers and surrounds a parade ground with auxiliary structures and ruins.

2. PROJECT OVERVIEW

Multiple tropical storm events lashed the Dry Tortugas, Florida area and Dry Tortugas National Park in the Fall of 2024. Strong winds, heavy rains, and excessive tides damaged and scoured the southeastern facing shoreline of Garden Key over a three week period.

The southeast facing waterfront consists of the main government dock, numerous small boat finger piers, dock decks for access, the remnants of a Spanish-American War era dock / building foundation that was a coal refueling station for the U S Navy, underground electrical utilities, and storage farms for diesel and gasoline fuels for ongoing park operations with associated fuel delivery and distribution lines.

Severe erosion of the sand beaches behind the docks and over the associated utilities and assets from the tropical storms a.) unearthed and destroyed a section of the diesel delivery line that was used to deliver ship to shore fuel transfers to underground storage tanks, b.) unearthed and made useless a gasoline line transition sump box and ingoing / outgoing piping near the main government dock, c.) severed a conduited 208vac electrical line leading from a main dock circuit panel to the tank farm, and d.) severed a conduited 120vac electrical line from gasoline storage tanks and serving the gasoline dispensing station on the main government dock. This project replaces and returns to service the 4 utilities described above and damaged by the storms.

The diesel delivery line will be replaced from a point underneath the dock decking to a new transition sump at a distance of higher elevation and upland away from the beach, which provides a connection to new coaxial double wall piping to the tank farm.

DRTO Page 4 of 9

The gasoline pipe will be replaced and re-routed similarly to a higher elevation and upland away from the existing beach to a connection point at a new transition sump with existing piping not damaged by the storms.

The damaged 208vac feeders from the main dock circuit panel to the tank farm will be replaced completely.

The damaged 120vac electrical line from the dock dispenser will be removed from the dispenser connection to a new sump connection at a point on higher ground where pipe integrity was not compromised by the storms.

3. REQUIRED SERVICES / TASKS

The Contractor shall provide all labor, tools, equipment, materials, and supervision required to perform the following tasks:

• Complete all tasks required to achieve necessary permits. All requirements and cost to achieve the permit is the responsibility of the contractor. All requirements to follow and complete the permit through construction and permit closeout is the responsibility of the contractor. Controlling organization for permitting is the Florida Department of Environmental Protection (FDEP).

• Delivery all materials, supplies, personnel, and equipment required to complete the scope of work including but not limited to barricades, safety equipment, power generators, sand screeners, digging equipment mechanical and by hand, materials, tools, food, drink, recreation equipment.

• Set up safety devices / obstacles around work area to prevent the public from entering the job site 24 hours per day

• Provide employees with clothing (t-shirts for example) identifying company employment

• Hardware fasteners used during the project shall be of 316 stainless steel

• Provide FID / OVA, soil sampling for lab work for VOAs, PAHs, TRPH as Fla-Pro to perform and submit Piping Closure Assessment Report to FDEP as required

• Electrical lines shall be Class 1 Div 1

• All wiring shall be pulled per NEC 70, NFPA 30, and 30A article 5

• All new piping shall be FDEP approved OPW coaxial double walled

• Install pipeline markers above piping

• Perform required integral tightness testing on new lines

• New pipelines shall be purged and placed back in service for customer inspection and exhibit proper performance prior to final payment submittal

• Repairs shall be performed by qualified contractors. Contractor shall submit references to demonstrate prior construction expertise and experience for the type of work required

• Contractor work updates shall include daily project reporting and weekly progress calls.

• Remove and dispose of all demolished materials created by work and equipment from Dry

Tortugas National Park upon completion of the project.

• Offerors are encouraged to propose process improvements and industry best practices in their proposals.

• Specifically:

DRTO Page 5 of 9

Diesel Fuel Lines

• Remove and dispose of approximately 700 ft (350 X 2, supply and distribution) of existing damaged / destroyed 2” primary and secondary pipe from dock decking to along shoreline to tank farm

• Install and connect approximately 80 ft new fiberglass pipeline from dock decking to a new upland transition sump

• Install and connect approximately 345 feet of new OPW coaxial double wall from the new upland sump to tank farm

• Remove and replace tank farm 5’ piping valve sump

Gasoline Fuel Lines

• Remove and dispose of approximately 80 ft existing damaged OPW coaxial double wall from the dock dispenser to the existing damaged dock decking transition sump

• Install approximately 150 ft of new coaxial double wall from the dock dispenser to the new upland transition sump

208vac Tank Farm Electrical Feeder Lines

• Remove and dispose of approximately 345 ft of damaged wiring and conduit from dock house circuit panel to tank farm electrical distribution box

• Install approximately 345 ft of new wiring and conduit from dock house circuit panel to tank farm electrical distribution box thru new upland transition sump

Gasoline Dispenser Controls Wiring

• Remove and dispose of approximately 80 ft of damaged wiring and conduit from the dock house gasoline dispenser to the damaged transition sump

• Remove section of redundant (unused) conduit from damaged transition sump to new upland transition sump

• Install approximately 160 ft of wiring and conduit from the dock house gasoline dispenser to the new upland transition sump and merge to existing conduit available there to the tank farm. Total length approximately 345 ft.

--a trenched pipe alley currently exists from the tank farm to the new upland transition sump location which contains a OPW coaxial double walled gasoline line that will remain in use.

Same trench. at no more than 18” wide and 30” deep and composed entirely of sand, will be excavated and used for the new diesel OPW coaxial double wall piping and both wire replacements to the tank farm

--In all cases, field verification supersedes approximate conditions

DRTO Page 6 of 9

4. OTHER CONTRACTOR REQUIREMENTS

• Prices shall be presented in a Schedule of Values form to facilitate pricing analysis for

Proposal. The sum of the total construction cost on the Schedule of Values shall be equal to the proposal price.

• A Contractor Safety Plan is required for this project. Refer to the Safety and Environmental Compliance Section of this document.

5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES

None anticipated.

6. SITE VISITS

Due to the remote location, specific site logistics, and challenging working conditions of any project at the Dry Tortugas, a site visit may be required at the contractor’s discretion prior to submission of the proposal. Site visits can be used to collect or verify measurements and quantities, quantify materials, establish construction methods, and to have site familiarity.

Site visits shall be organized by the COR assigned to the project under this SOW. The NPS reserves the right to limit site visits to those which the CO or the COR determines to be sufficient.

Site visits prior to award will not be reimbursable by the government.

Transportation to Dry Tortugas is offered daily by two separate commercial operations:

Yankee Freedom III ferry; roughly 2.5 hours each way, 0800 departure from Key West to Dry Tortugas and a 1430 departure from Dry Tortugas to Key West. Key West Seaplane Adventures offers multiple seaplane departures from Key West to Dry Tortugas daily. Travel time is roughly 45 minutes each way.

Ferry – www.drytortugas.com and 305-294-7009 (contractor rates are available) Seaplane – www.keywestseaplanecharters.com and 305-293-9300 (contractor rates are available)

Contractor may coordinate transportation of construction materials and supplies with the park staff, pending availability and schedule of park vessel.

http://www.drytortugas.com/ http://www.keywestseaplanecharters.com/

DRTO Page 7 of 9

7. PARK HOUSING

Park housing will be made available to contractor for a crew of up to (6) individuals. Park housing is a shared living situation in a bunkhouse setting. A walk through can be completed with a site visit and/or more information can be provided upon request. Housing rates are $45/person/night to be paid to park at the end of each month of occupation.

8. TELEPHONE/INTERNET

The internet provided to transient quarters in the park is very limited, with capability for texting and browsing webpages. Very strict usage rules apply as it is a community system.

No government-provided phone service will be available to the contractor. Contractor may utilize satellite systems at own expense.

Contractor will be responsible for all telecommunications needs and systems beyond the capabilities of what is provided currently by the NPS. This must be heavily coordinated with the designated CO as options for phone and internet are severely limited on Garden Key.

9. WORKING HOURS

The contractor shall complete on-site work during normal business hour period of 8:00 am to 6:00 pm, Monday through Saturday, and may include federal holidays when scheduled in advance. Working outside these times and dates shall require a written request. Each request to work outside of normal business hours shall be date specific and shall be pre-approved by the CO and require minimum of 72 hours’ notice. Requests without this specified notification period will not be approved. The contractor shall coordinate specific on-site work schedule with the CO and COR with the submittal of a complete Project Schedule. Refer to the Submittal Section of this document. Approval of a submitted project schedule shall not consist of inherent approval for work outside of normal hours. While on site, the COR or CO may be reached within specified normal business hours.

10. PERIOD OF PERFORMANCE

Timing of the work shall be coordinated with the COR and will be based on the availability of government housing.

Dry Tortugas National Park is subject to seasonal Atlantic Hurricane conditions from June to November. Contractor will be responsible for planning, scheduling, and executing any temporary closures or shutdowns of the work site due to severe weather, any time of the year, but particularly during the hurricane season. Evacuations and seasonal shutdowns may be required.

No official contract work shall begin until after award and a Notice to Proceed have been provided by the Contracting Officer.

DRTO Page 8 of 9

All work shall be completed within 45 days after CO issues the contract Notice to Proceed.

11. SAFETY & ENVIRONMENTAL COMPLIANCE

• The contractor shall submit a Contractor Safety Plan and identify a single Safety Person in Charge with a clear transfer of responsibility in cases when there are alternates for all on-site work. In additional to these requirements, designated person(s) shall meet and demonstrate competency in all Occupational Safety and Health Act (OSHA) standards related to Competent Persons (CP) under 29 CFR 1910 through 1926 for the applicable areas related to this project.

• The contractor shall comply with pertinent Environmental Protection Agency (EPA) laws and regulations.

• The Park Safety Coordinator shall have the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten Government or contractor employees or damage to Government property.

• The contractor shall notify the CO and COR immediately if issued a cease-and-desist order.

12. GENERAL TREATMENT

Delivery of all materials, supplies, personnel, and equipment required to complete the scope of work including but not limited to barricades, safety equipment, power generators, sand screeners, scaffolding, water pumps/containers, materials, tools, food, drink, recreation equipment is the responsibility of the contractor.

Contractor shall remove all leftover or not used materials, supplies, and equipment from Dry Tortugas National Park upon completion of the project.

13. EMPLOYEE IDENTIFICATION

All Contractor and Subcontractor employees shall wear identifiable clothing on the work site, so Park visitors know they are Contractor employees.

14. SUBMITTAL REQUIREMENTS (POST-AWARD)

The following items are to be submitted after the contract award. All submittals shall be approved prior to ordering or starting any work.

• Completed Schedule of Values form. Refer to Attachment B.

• Proposed Project Schedule (one week or three week look-aheads) and updates.

• Debris Disposal Plan is required. This plan shall describe how records of debris taken from the site are tracked to a specific debris disposal facility. No materials shall be dumped or disposed of improperly.

• Contractor Safety Plan is required, which shall include sections on fall prevention plan, and an inclement weather response plan. Refer to the Safety and Environmental Compliance Section.

DRTO Page 9 of 9

• All materials required to be used and/or purchased to complete the project require material submittal documents.

• Contractor shall submit a Hurricane Evacuation Plan to COR for park approval.

15. ATTACHMENTS

Damaged Transition Sump

DRTO Page 10 of 9

--120vac gasoline dispenser controls conduit to tank farm (Front)

--208vac junction box to tank farm (Rear)

Both are under dockhouse dock decking.

1. Park Introduction
2. Project Overview
3. Required Services / Tasks
4. OTHER Contractor ReQUIREMENTS
5. Government Furnished Property, Materials & Supplies
6. Site visits
7. Park housing
8. Telephone/internet
9. Working Hours
10. Period of performance
11. Safety & Environmental Compliance
12. general treatment
13. Employee IDENTIFICATiON
14. Submittal Requirements (Post-Award)
15. ATTACHMENTS