Statement of Work.pdf

PDF 173 KB Posted

Attached to
Water Service Line Mayetta, KS Federal contract opportunity
Solicitation number
246-25-Q-0039r1
Issued by
Department of Health and Human Services Indian Health Service

About this file

This Statement of Work details the requirements for installing a 2½-inch water service line in Mayetta, Jackson County, Kansas, at 17869 T Road. The project involves furnishing and installing the water service line with specific technical specifications, including using virgin rigid PVC pipes manufactured in the United States that conform to NSF International Standards 61 and 14. The contractor must perform trench excavation to a minimum 32-inch depth, install the pipe on undisturbed soil, conduct pressure and leakage testing, disinfect the water line, and restore the site to its original condition.

Key technical requirements include using mechanically compacted imported bedding, river sand covering, comprehensive testing procedures, chlorine disinfection, and bacteriological sampling. The contractor must also perform topsoiling, seeding, and mulching of disturbed areas, using a specific seed mixture of Kentucky 31, Fescue, and annual rye grass. The project includes a one-year warranty on materials and labor, and requires coordination with the project engineer throughout the installation process, with all work subject to technical inspection and approval.

View the file

Other files for this federal contract opportunity

Other files attached to Water Service Line Mayetta, KS, newest first.
File Type Posted
KS152 Wage Determination.pdf PDF
Bid Sheet.pdf PDF
SF18-95a R1.pdf PDF
Construction Clauses-DEVIATION FEB 2025.docx DOCX document
Drawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Service Line January 16, 2025

Water Service Line

STATEMENT OF WORK

WATER SERVICE LINE

1.01 SUMMARY OF WORK TO BE DONE BY CONTRACTOR

A. Furnish and install a 2 ½-inch water service line as shown on the drawing.

1.02 ACCEPTANCE

A. Work covered by this section will not be accepted until the backfilling and testing connected with the work has been completed satisfactorily.

1.03 SITE LOCATION

17869 T Road Mayetta, Jackson County, Kansas 66509

1.04 CONSTRUCTION SCHEDULE

A. Contact the Construction Inspector three business days before the start of any work.

B. Failure to preform work on the date scheduled will require 24-hour notice to rescheduling the work.

C. Leave all work exposed until inspected and approved. Work not inspected before it is covered, will be re-exposed at the Contractor’s expense.

1.05 QUALITY ASSURANCE

A. Perform work under the direction of personnel licensed in the state including, but not limited to Plumbing.

1.06 WARRANTY

A. Provide a minimum one-year warranty for all materials and labor, covering defects in the materials or workmanship.

1.07 PRODUCTS

A. Water Service Lines and fittings:

1. Pipe size, material, and pressure rating

2. Pipe and fittings will be manufactured in the United States. Pipe and fittings shall conform to NSF International Standard 61 or the health effects portion of the NSF Standard 14. Pipe and fittings will be manufactured as a system and be the product of one manufacturer. Pipe and fittings will be manufactured form virgin rigid PVC (polyvinyl chloride) vinyl components with a Cell Class of 12454 as identified in ASTM D 1784.

3. PVC SDR pipe shall be Iron Pipe Size (IPS) conforming to ASTM D 2241 for plain-end pipe, ASTM D 2672 for bell-end pipe and ASTM F477 for bell-end reinforced gasket.

4. Turf and Grasses (Topsoil, Seed, Fertilizer, and Mulch)

a. Topsoil: Native topsoil from stockpile within project area.

1) Containing organic material and nutrients suitable for plant growth.

2) Free of debris, trash, large roots, sticks, frozen material, rocks 3-inches and larger.

3) Moisture content suitable for spreading and tilling.

b. Fertilizer nutrients in either of the following proportions

1) 12% nitrogen

2) 24% Phosphorous

3) 12% Pot Ash.

c. Seed Mixture: Blend of Kentucky 31, Fescue, and annual rye grass.

d. Mulch: Prairie (native) hay, not more than 2 years old and free of noxious weeds.

1.08 INSTALLATION

A. Install 2 ½-inch water service lines and appurtenances in the locations, sizes and materials shown on the drawings or staked in the field.

B. Lay pipe from the meter to the home in trench free of rocks and on undisturbed soil.

1.09 TRENCH

A. Depth: Minimum 32 inches.

B. Bottom: Free from stones greater than 1-inch, large dirt clods, any frozen material.

C. Bedding: If the trench bottom is hardpan, rock, or has stones larger than 1-inch in diameter in the largest direction:

a. Over excavate 6 inches.

b. Place 6 inches of mechanically compacted imported bedding

c. Place pipe in trench.

d. Place 6 inches of mechanically compacted river sand over the pipe.

D. Backfill: restore trenches to initial grade.

E. Seed, Fertilize, and Mulch

1. Seed, fertilize, and mulch all areas disturbed by the installation of water service line.

1.10 PRESSURE AND LEAKAGE TESTING - PVC

A. Whenever practical, before backfilling is fully placed or joints fully covered, test pipe for leaks in the presence of a technical representative.

B. Furnish necessary material, equipment, and labor for testing including, but not limited to: water, pump, water storage vessel, piping, pressure gauge, valve, hydrant, and corporation stop.

1. Utilize liquid filled pressure gauges with 5psi increments or less.

C. Test duration: 2 hours minimum.

D. Testing procedures – Test in accordance with the hydrostatic Testing Method outline in

ANSI/AWWA C605.

1. Slowly fill test section with water and expel air from lines.

2. Install corporation stops at high point to facilitate removal of air, if necessary.

3. Verify that all valves in line are open if there are any.

4. Place test section under constant pressure.

5. If pressure drops more than 5 psi during test, immediately repressurize the line to the original test pressure and continue the test.

a. Record amount of water required to re-pressurize the line.

6. At end of test, repressurize the line to original test pressure.

a. Record amount of water required to re-pressurize the line.

7. Add the total amount of water required to re-pressurize the line during and at the end of the test and compare with the allowable leakage as calculated below.

a. If leakage is greater than allowable leakage, test fails.

8. Allowable leakage determination.

Q = (L*D*P^1/2)/7400

Q = Allowable Leakage (gph) L = Total Length Tested by The Standard Pipe Length D = Nominal Diameter of Pipe (inches)

P = Test Pressure (psi)

9. Repair at no cost any section of the line that fails this test.

1.11 DISINFECTION OF WATER LINES AND FITTINGS

A. Conform to AWWA C651 for disinfection. Tablet method is not allowed.

B. Obtain water at site for disinfection.

C. Flush chlorinated water in accordance with AWWA C651.

1. Waste flushed disinfection water in an environmentally safe manner. Chlorine residual of water being disposed will be neutralized by treatment of sodium bisulfate as per Appendix C of AWWA C652. The method used is subject to the approval of the Project Engineer.

D. After disinfecting and flushing but before the water line is place in service, collect and test water samples for bacteriological quality.

1. Sample in accordance with the Standard Method for Examination of Water and

Wastewater.

2. Take two consecutive tests, 24 hours apart.

3. Collect one sample from the new water line.

a. Addition samples may be required on extremely long lines.

4. Take samples to an EPA certified testing lab.

5. Permanent sampling taps may be required at the direction of the Project Engineer.

E. If initial disinfection fails to produce satisfactory bacteriological results, re-chlorinate the line, flush and take new samples until two satisfactory results are obtained.

1. Do not place service line in service until the Project Engineer has received safe bacteriological results.

F. No additional payment will be made for any equipment, material, testing or labor required to disinfect the service line. Include all costs associated with disinfection in the contract bid price for the service line.

1.12 CONNECTIONS TO EXISTING DISTRIBUTION SYSTEMS

A. Depressurizing of mains will not be permitted overnight, over weekends, or on federal holidays.

B. Coordinate system tie-in with the Owner and /or operator of the existing utility a minimum of three working days before any connection is made.

C. Notify residents affected by the water shutoff of the time and day of shutoff a minimum of two working days in advance.

D. Connect using stainless steel tapping sleeve with a tapping gate valve.

E. Clean all connection components with a 200-ppm chlorine solution prior to installation.

F. Once work on the connection has been commenced it must proceed as rapidly as possible until completed.

G. Visually inspect any joints not pressure tested for leakage.

1. Test under system pressure prior to back filling.

2. Test in the presence of the technical representative.

3. Repair and retest any joint with leakage until no leakage is visible at not cost to the contract.

1.13 TOPSOILING, SEEDING, FERTILIZING, AND MULCHING

A. This section covers topsoiling, seeding, fertilizing, and mulching all areas disturbed by construction activities.

B. Topsoiling

1. Spread topsoil over all disturbed areas.

2. Remove surface irregularities within the area to be seeded by blading or by other suitable methods.

3. Till soil to a depth of 2 inches, but not to exceed 3 inches.

4. Complete tillage in a manner eliminating clumps of dirt larger than 2 inches in diameter.

C. Fertilizing:

1. Apply using mechanical equipment.

2. Uniformly distribute.

3. Incorporate into soil using harrow or other suitable equipment.

4. Conform to recommendations of local county extension agent.

5. Fertilize the area at an application rate of 100 pounds per acre.

D. Seeding:

1. Sow seed using either equipment suited to that purpose or scatter seed uniformly over area with hand seeders when the weather is sufficiently quiet to prevent seeds from blowing away.

2. Plant when soil temperature is 60° F or greater.

3. Application rate

a. 200 pounds per acre of the Kentucky 31, fescue, and rye grass.

4. Lightly rake soil to cover the seed with approximately ¼ inch of soil.

E. Mulching:

1. Place hay mulching on seeded area loose enough to allow some sunlight to penetrate and air to circulate but thick enough to shade the ground, conserve soil moisture, and prevent/reduce erosion.

2. Do not perform mulching activities during periods of excessively high winds, which would preclude the proper placing of the mulch.

3. Apply straw or hay uniformly over the disturbed area to a loose depth of ½ to 1½ inches using 2 to 2 ½ tons of mulch per acre.

4. Immediately after spreading, anchor mulch using a mulch tiller consisting of a series of dull flat discs with notched edges or other approved equipment.

1.14 CLOSEOUT ACTIVITIES

A. Restore the site as close as is practical its original condition.

B. Provide record drawings to the Project Engineer.

STATEMENT OF WORK