Statement of Work.pdf
PDF 303 KB Posted
- Attached to
- Dual-channel fiber-coupled IR wavemeter
- Solicitation number
- 1333ND25QNB030061
About this file
This Statement of Work details NIST's requirement for one multichannel wavelength meter to support CHIPS R&D work within the Microsystems and Nanotechnology Division of the Physical Measurement Laboratory. The wavelength meter will be used to measure wavelengths from a singly-resonant, continuous wave optical parametric oscillator for atomic layer deposition research.
The technical specifications require the wavelength meter to measure wavelengths between 1050-2150 nm, be fiber coupled with FC/APC or FC/PC connectors, allow USB connection to an external computer, and enable automatic multichannel operation for both signal beam (1450-2150 nm) and pump beam (1050-1070 nm) measurements. Additional requirements include operation on 120V power, accuracy better than 300 MHz, measurement rate of at least 100 Hz, and ability to display interferogram data. Delivery is required within 6 months after receipt of order to NIST Gaithersburg, with FOB destination shipping terms. The system includes a one-year warranty and payment will be made after successful installation, testing, and acceptance by NIST. NIST maintains the right to perform acceptance testing by comparing the wavelength meter to an existing mid-infrared wavemeter.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CSS Wavemeter.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Title: Multichannel wavelength meter
Lab: PML
I. BACKGROUND INFORMATION
The semiconductor supply chain is global, specialized, and interconnected. Chipmakers do business with thousands of individual suppliers that provide the highly complex materials and tools used to produce semiconductors. To address the lack of full visibility into the semiconductors markets supply chain and R&D ecosystem gaps NIST will conduct the measurement science, or metrology, critical to the development of new materials, packaging, and production methods in chip manufacturing.
This purchase, which is part of CHIPS R&D work within the Microsystems and Nanotechnology Division within the Physical Measurement Laboratory at NIST is needed as part of our research on atomic layer deposition we will utilize a singly-resonant, continuous wave optical parametric oscillator. The Microsystems and Nanotechnology Division advances nanofabrication technologies and uses them to develop innovative integrated measurement microsystems. This optical parametric oscillator allows for the spectral translation of near-infrared laser light into the mid-infrared spectral region. The mid-infrared region contains strong absorption features of a wide variety of atomic and molecular species of interest to the chemistry and physics communities. A singly-resonant, continuous wave optical parametric oscillator is well suited for this type of spectroscopy due to its wide tunability, high optical power, narrow linewidth, and the ability to translate modulation with high fidelity. In order to measure the wavelength of the pump, signal, and idler beams which the optical parametric oscillator emits we require a high accuracy wavelength meter.
II. PURPOSE
The Contractor shall deliver a quantity of one (1) wavelength meter which can measure both the signal and pump wavelengths of an optical parametric oscillator, inclusive of FOB destination shipping and warranty.
III. MINIMUM REQUIREMENTS
The Contractor shall provide a system that meets all technical specifications identified below. All items must be new. Used or remanufactured equipment will not be considered for award.
Experimental, prototype, or custom items will not be considered. The use of “gray market” components that are not authorized for sale in the U.S. by the Contractor is not acceptable. All line items shall be shipped in the original manufacturer’s packaging and include all original documentation and software, when applicable.
Line Item 0001: Wavelength meter Description: Multichannel wavelength meter Quantity: 1
Technical Specifications:
The wavelength meter must have the following functionalities:
1. The system must run off 120 V power (i.e., standard USA power).
2 | P a g e
2. The wavelength meter must be able of measuring wavelengths between 1050 nm and 2150 nm (in order to cover the range of pump and signal wavelengths of the optical parametric oscillator).
3. The wavelength meter should be designed to measure continuous wave optical inputs.
4. The wavelength meter should be fiber coupled and allow for fibers with FC/APC or
FC/PC connectors.
5. The wavelength meter should allow for USB connection to an external computer.
6. The wavelength should allow for multichannel operation where both the signal beam
(1450 nm to 2150 nm) and the pump beam (1050 nm to 1070 nm) can be measured without adjusting any fibers or connections. In addition this multichannel operation should be automatic without the need for user intervention or the programming of new software by the user.
7. Optical powers less than 1 mW should be required to reach the specifications listed here.
8. The wavelength meter’s accuracy should be better than 300 MHz.
9. No external reference laser should be required to reach these specifications.
10. The measurement rate should be at least 100 Hz.
11. The wavelength meter should allow for the display of the associated interferogram in order to assess the optical parametric oscillator’s output state.
IV. SCHEDULE OF DELIVERABLES
Deliverable
Number Description Quantity Due Date
Place of Delivery 1 Wavelength meter 1
6 months after receipt of order
NIST Gaithersburg
V. DELIVERY TERMS
Delivery shall be F.O.B Destination (or equivalent incoterms, such as DDP) and shall occur in accordance with the delivery due dates provided in the below table.
FOB Destination means: The contractor shall pack and mark the shipment in conformance with carrier requirements, deliver the shipment in good order and condition to the point of delivery specified in the purchase order, be responsible for any loss of and/or damage to the goods occurring before receipt and acceptance of the shipment by the consignee at the delivery point specified in the purchase order; and pay all charges to the specified point of delivery.
The contractor shall deliver all Line Items to:
National Institute of Standards and Technology Shipping and Receiving 100 Bureau Drive, Building 301 Gaithersburg, MD 20899
C/O: TBA (221/A165)
VI. INSPECTION & ACCEPTANCE
3 | P a g e
In addition to the inspection and acceptance terms articulated in the specific FAR clause that allows the Government reserves the right to perform such performance tests and evaluations as defined below to verify specified system performance. Such tests and evaluations, if performed, shall be conducted within the environment that the system is to be operated. The Contractor has the right to be present during the tests and evaluations, if performed, at the Contractor’s expense.
Performance Tests:
1. Measure that the wavemeter meets the listed specifications by comparing to an existing mid-infrared wavemeter and putting the same light source into both wavemeters simultaneously.
NIST may choose at its discretion to forego this part of acceptance testing.
A visual inspection of the equipment will be performed by the NIST POC to identify surface defects or any form of indication that any equipment was damaged during transport to NIST. The Government shall have sole discretion to require repair or replacement of damaged and/or nonconforming supplies at no cost to the Government. The Government at any time prior to acceptance shall reject the equipment due to defects and/or nonconformance. The vendor is responsible for latent defects discovered any time after final inspection. However, the extent of its liability shall be prorated over the useful life of the equipment.
Ownership of the equipment shall transfer to NIST upon acceptance by the Government.
The Government will test, inspect, and accept or reject the equipment within one (1) week of the receipt of the equipment unless otherwise indicated above. The Government reserves the right to conduct quality assurance testing to confirm that a given instrument(s) meets the manufacturer’s and/or the Government’s performance specifications. It is anticipated that the equipment will meet all manufacturer’s specifications and/or the Government’s performance specifications identified in the most recent operations and maintenance manual for each piece of equipment and/or in this document.
VII. WARRANTY
The contractor shall warranty the entire system for a period of a minimum of one (1) year after receipt of the equipment and shall be in accordance with terms in FAR 52.212-4. Warranty shall commence upon acceptance of the system by the Government and at a minimum shall include the following: That the wavelength meter meets or exceeds the listed specifications.
VIII. PAYMENT SCHEDULE
The Contractor will be paid, in accordance with the payments clause in the contract and as otherwise noted in this document, upon receipt of a proper invoice:
• 100% after installation and acceptance by the POC of fully installed system, AND
• After the successful completion of the testing requirements set forth in this document under section set forth in this document, AND
• After successful demonstration by the instrumentation that it performs in accordance with the requirements set forth in this document.
4 | P a g e
NOTE: Partial shipments and partial invoices will not be accepted, unless otherwise requested and accepted by the Contracting Officer prior to award offer. Proposed payment schedules shall be submitted with vendor’s response to the RFQ for consideration.
IX. CYBERSECURITY PRIVACY REQUIREMENTS
NIST seeks a solution that provides security and privacy protection consistent with requirements defined by applicable federal laws, regulations, policies, and standards (e.g., the Federal Information Security Management Act (FISMA), OMB Circular A-130, and FIPS Publication 200). The solution provider (including subcontractors) may meet these requirements through various means, including but not limited to FedRAMP authorization, current third-party assessments (e.g., SSAE, PCI), and/or responses to NIST special publication control set SP 800- 171.
Minimally Acceptable Controls
• System security plan describing physical, technical, and administrative controls implemented to protect systems and sensitive personally identifiable information (SPII).
• IT management processes to establish and manage secure configuration baselines including routine patching for all operating systems and applications.
• Access to SPII is restricted to those with a need to know. Personnel with access to SPII have background investigations performed (e.g. criminal, financial etc.), and are trained on secure handling of SPII.
• Access Controls for SPII meet or exceed industry best practices for access and identification control including, but not limited to, connectivity to servers and databases, multi-factor authentication for remote accesses for administration, secure configurations for any devices accessing the system, and strong physical security for any place where the data is accessed.
• The solution supports multifactor authentication for users and/or supports integration with customer federation services for Single-Sign capability.
• Processes for scanning on a continual basis for vulnerabilities and proper configurations for all aspects of the system, as well as processes for timely mitigation of findings.
• Auditing and Incident Response processes including customer notification of suspected or actual incidents and logging with sufficient information to perform forensics on any incident. Processes for notifying and providing appropriate mitigations, including but not limited to credit monitoring services, for subsidy applicants in the event of suspected or actual incidents.
• SPII is encrypted in transit using TLS 1.2 or better and encrypted at rest in all places the SPII is stored. All encryption algorithms and modules are FIPS 140-2/140-3 validated.
5 | P a g e
If unable to meet any of the requirements listed above, the solution provider may provide details of mitigations or alternative protections in place to ensure the appropriate handling and protection of SPII.
If the solution provider provides services to other Federal agencies, provide a general description of the security risk management approach and client point of contact.
Media Inquiries: The Contractor shall not respond to any media inquiries. Any inquiries from the media shall be immediately relayed to the NIST COR and/or Contracting Officer (CO). There shall be no interviews, comments, or any other response without the knowledge and approval of the NIST COR or Designated Government Official.