About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace the existing HVAC system at the maintenance building of the John Day Fossil Beds National Monument in Kimberly, Oregon.

The SOW requires the contractor to remove the existing HVAC equipment, including an electric air handler, heat pump, and associated ducting and electrical components, and replace it with new TRANE brand or equivalent HVAC equipment of equal or better efficiency and performance. This includes installing a new air handler unit, backup heat strips, heat pump with snow legs, home automated thermostat, and completing all necessary electrical and ducting modifications. The contractor must verify proper system operation, provide documentation, and conduct training for NPS staff on the new equipment. The project site will remain open to NPS staff during construction but closed to the public. The contractor must follow all NPS regulations regarding work hours, site access, staging, and property damage. The contractor must provide operation and maintenance manuals, warranties, and a one-year workmanship warranty.

The related federal contract opportunity is Solicitation Number 140P8324Q0060, issued by the Department of the Interior National Park Service Pacific West Region, to replace the heat pump HVAC system at the John Day Fossil Beds National Monument in Kimberly, Oregon.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Heat Pump HVAC, NPS Kimberly OR, newest first.
File Type Posted
Photograhps_of_Existing_Equipment.pdf PDF
Sol_140P8324Q0060.pdf PDF
Wage_Determination_Kimberly_OR.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ 140P8324Q0060 National Park Service

Replace Heat Pump HVAC

Statement of Work

A. General: All work outlined below will be performed under a single contract.

B. Project Location: Maintenance shop located at John Day Fossil Beds National Monument.

32651 Highway 19, Kimberly Oregon 97848

C. Project Background: The Maintenance Building at John Day Fossil Beds National Monument is in need of replacement. The current HVAC system consists of an electric LENNOX air handler with a backup electric heater and a LENNOX heat pump. All of this equipment has reached the end of its life cycle. NPS is requesting TRANE equipment as a replacement.

D. Project Scope of Work: The Work consists of the following:

1. This project will replace the existing HVAC equipment with equal to or better than the requested brand equipment. Manufacture make and model of new units to be equal to or better than the requested unit in performance and efficiency. All existing ducting, and all associated components must be inspected by contractor for compatibility with the replacement HVAC unit’s manufacturer specifications.

2. All needed alterations to ducting and electrical shall be completed by contractor.

Contractor must install HVAC equipment, duct transitions and all other components in accordance with manufacturer's specifications.

3. The Contractor is to provide all labor, equipment and materials unless otherwise stated in this scope of work. The contractor is responsible for all costs associated with this project, including all travel, per-diem, and the disposal if any waste generated by this project. A staging area will be determined at the work site. Electrical power, water and restrooms are available.

4. Work shall include but is not limited to:

5. Mobilization and Cleanup; a. All refrigerant will be disposed of following the state of

Oregon environmental regulations and receipts or proof of proper disposal may be required. Current system is charged with approximately 6 lbs 3 oz of HCFC-22 refrigerant.

6. Remove and dispose of existing equipment and all product specific parts.

7. Install new air handler unit and back up heat strips. New air handler shall be equal in efficiency and performance or better than a TRANE TEMP6 air handler with backup electric heat strip.

8. Install new home automated thermostat (TRANE XL824 or equivalent) and configure to new system.

9. Install replacement Heat Pump on existing concrete slab with new snow legs (heat pump riser for snowy climate). New Heat Pump shall be equal in efficiency and performance or better than a TRANE XR14.

10. Contractor shall verify operation in accordance with manufacturer specifications through testing and documentation. Must provide operation test results as well as operation and maintenance manuals.

11. Provide proof that the system will deliver specified efficiency and conduct load calculation for proper equipment selection.

12. Measure and document airflow

13. Measure and document refrigerant charge

14. Modify or install new electrical service to fan, coils or air handler units if none exists including installation of new breakers labeled at associated breaker panel box. All electric work will follow manufacturer’s specifications and all Oregon State Electrical

Codes, e.g. wire gauge, breaker amperage, power supply.

15. Install new home automated thermostat that meets HVAC equipment manufacturer specifications. Test thermostat, and submit results.

16. Assure approved drain lines will be installed to manufacture specifications and drain away from existing structure.

17. Provide as-builts and operations and maintenance manuals

STAFF USE OF THE SITE

A. General: The project site will be open to the staff during construction but closed to the public. The Contractor shall at all times conduct his operations to ensure the least inconvenience to the staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.

B. Other Contracts and Work: During the contract performance period, there may be other contracts or work occurring in the park or within the project area limits. The Contractor shall conduct his operations in consideration of these other activities.

CONTRACTOR USE OF SITE

A. General: Limit project operations to the project area.

B. Park Regulations: Ensure all personnel (contractors, subcontractors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

C. Site Access: The contractor shall access the project site along pavement, do not drive vehicles off road or access non-project areas without permission from the Contracting Officer or their representative.

D. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until

5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires advance approval from the Contracting Officer.

E. Staging and Storage: Confine the staging and storage of equipment and materials to the work area.

F. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to the LE rangers upon discovery.

G. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation.

Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

CLOSEOUT SUBMITTALS

A. Operation & Maintenance (O&M) Manual: Submit hard copy to the onsite Point of Contact

(POC).

1. Preventative maintenance schedule for all major components.

2. Operating instructions, if applicable.

3. Product / material cut sheets (all approved products used on the project).

4. Updated system diagrams or shop drawings, as applicable.

5. Product manufacturer warranties for individual products and systems.

6. At least one (1) year Contractor-issued warranty on all workmanship starting from the date of final acceptance.

DEMONSTRATION & TRAINING

Provide onsite demonstration and training to NPS operators and staff on safe operation and maintenance of equipment and components, including thermostat operation.