STATEMENT OF WORK (SOW)

For

SC Outside Plant (OSP) Fiber Cable Project

B1646 to B1107 Fiber Cable Installation and

Supporting Manhole Duct Bank Repair/Replace

66th Air Base Group Communications and Information Division (66ABG/SC)

Hanscom AFB MA

Date: 29 July, 2020

Prepared by:

66ABG/SC

Hanscom AFB, MA 01731

Overview:

The 66th Air Base Group Communications and Information Division (66ABG/SC) provides

Hanscom AFB with network services to all the buildings. The 66ABG/SC division has one outside plant cable requirements:

A. Outside Plant Fiber Run from Bldg. 1646 to Bldg. 1107 including:

B. Bldg. 1646 Manhole Duct Bank Repairs.

Location

Material shall be delivered to:

66 AGB/SC

132 Grenier Street Bldg. 1814

Hanscom AFB, MA 01731

Attn: Dennis Menick 781-225-0022

Points of Contact

Project Manager:

Name: Dennis Menick

Email: dennis.menick@us.af.mil

Telephone: 781-225-0022

Telecommunications Engineer:

Name: Don Doolin

Email:donald.doolin.ctr@us.af.mil

Telephone: 781-225-6033

Government Quality Assurance POC:

Name: Gary Smith

Email: gary.smith.58@us.af.mil

Telephone: 781-225-0019

Contracting Officer:

Name: Robert Gill

Email: robert.gill.12@us.af.mil

Telephone: 781-225-0193

Optional RFQ Site Visit

Site Visit to view working area will be held on 9:00 PM EST on Tuesday, 25 August 2020.

Please contact the above Contracting Officer if you plan on attending. Site Visit information will be forwarded along once your response is received.

General Requirement

1) A. Upon being awarded the contract, the contracting company will be required to schedule and perform a site survey and walk thru to confirm the OSP underground duct spacing, manhole availability, pathway confirmation, racking locations, elevations. The Base

Communications office will require a five (5) business day notice prior to this scheduling.

2) The Contractor shall provide, in advance, names of all technicians that will be working on this project for Facility Security. All technicians must be US citizens and have proof of ID.

All drivers shall have a valid driver license and proof of insurance in order to drive on

Hanscom AFB. All documentation will be checked before a visitor’s pass will be issued.

3) Working hours shall be 7:00 am to 3:00 pm (adjustments can be made), Monday-Friday. No work will be done on days the base is closed, to include, but not limited to Holiday and closure due to storms. Saturdays work shall be scheduled in advance with Project Manager.

4) The Contractor shall schedule and perform a site survey and route walk thru to confirm the

OSP underground duct spacing, pathway confirmation, racking locations, and elevations. The

Contractor shall provide the government Project Manager five (5) business days’ notice prior to performing this activity.

5) Safety and Confined Space Requirements:

a) All personnel entering/working in any Confine Space Permit deemed areas of Hanscom

Air Force Base will adhere to all mandatory laws and regulations of the following OSHA

29 CFR 1910.146 / AFI 91- 203 / Hanscom Base Communications CSE program. No one will enter any telecommunications manholes/CSE deemed locations without preapproved confine space entry permit issued.

b) The Contractor shall obtain a dig permit for the park lot termination location.

c) The Government will assist the Contractor in the process to obtain a confined space entry permit and also a dig permit.

d) Confine Space Entry/Manhole Work: A safety briefing will be provided by Base

Communications prior to job start. The Base Communications office will require a minimum of five (5) business day notice prior to scheduling any CSE briefings.

e) The Contractor shall provide certified flaggers or traffic control while working in the streets and building grounds. The Contractor shall notify and coordinate with Base

Safety, Police, Fire and all other required organizations to perform the project etc.

Contacts: Security Forces: 781-225-5000, Base Safety: 781-225-5584, Fire Department:

781-225-3330, and Base Communications: 781-225-6028/6029.

6) Labeling:

a) For each manhole / Handhold / Vault the F.O. cable passes through, the contractor shall have a minimum of two (2) tags, the point of entering the manhole and exiting the manhole.

b) The F.O. cable(s) will be labeled utilizing the following labeling schematic. The tag will be an OSP rigid vinyl, aluminum or stainless-steel tags with the following information.

The owner of the cable: HAFB-AB66/SCOI

Cable number: AB66/SCOI (SEE ENGINEER)

Cable type: XXXX

Termination points/Date: [location A] to [location B]/ MM/DD/YYYY, for example: B1107 DC to UP Lot - MM/DD/YYYY or B1646 DC to B1107 –

MM/DD/YYYY

7) Service Outages.

The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 4 weeks in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

8) Active Circuits

A phased communications plan developed by the contractor and government will be required to address the needs of building 1646 termination. Government will provide assistance in scheduling and coordinating with base users.

9) Mandatory Site Survey:

Following contract award, the Contractor will be required to schedule and perform a site survey and route walk thru to confirm the OSP underground duct spacing, manhole availability, pathway confirmation, racking locations, elevations. The Base Communications office will require a minimum of five (5) business day notice prior to this scheduling of any site surveys/walk thru’ s. The Contractor shall contact the Hanscom Air Force contracting office POC for any scheduling. Please do not contact the Base Communications Department directly.

Projected Implementation Dates: To be completed no later than 31 May 2021

Specefic Requirements

A. Outside Plant Fiber Optic run from Bldg. 1646 to Bldg. 1107

Provide and install one (1) Corning (or equal) 72 pair (144) Strand Single Mode (SM-

8.3/125um), with no factory splices OSP (Outside Plant) Armored indoor/outdoor rated fiber optic cable. The Fiber Optic Cable to be installed will be installed as a ‘Home Run’ between buildings via the underground manhole/duct pathway system as one continuous fiber optic backbone run without any splices to include bonding and grounding per NEC if applicable. Suggested Route: From Bldg. B1107 to B1646 Manhole(s) B1107 *MH

48, 47, 46, 45A, 42, 41-2, 41-1, 41, 2, 1* B1646 (Other paths can be used, at the time of installation only after prior site survey and approval have been completed).

The fiber optic backbone will be dressed onto the existing manhole racking system within each manhole/vault/hand hole it passes through. If manhole racking is not available or completely full, it will be the contractor’s responsibility to install a complete high impact non corrosive (additional system) plastic non-corrosive racking supports. TBD during the contractor’s site survey (See General Line Item # 1).

The fiber optic cable will be terminated at a predesignated rack location within each of the building’s corresponding MDF’ S (Exact Rack Location/elevation by Base Comm.

TBD upon award of contract). The Fiber Optic Cable will be terminated onto a rack mounted, 19” Fiber Optic Termination Panel/LIU (FOTP) (Light Interface Unit).

All fiber optic patch panels shall be rack mounted. Fiber Optic Patch Panels will not have a sliding tray or other moving parts which move the terminated fiber strands. All fiber optic

LIU’s will be Corning product line (or equal) CCH 2U or 4U, (preloaded panels, high density LC) all fiber optic connectors shall be Fusion Spliced LC style fiber optic pigtails/3 meter. TIA – 604 (FOCIS) 2-6.1.3.1 WBDG UFC. All test results should be submitted for approval, prior to installation acceptance within ten - (10) business days of completion by contractor. The deliverables package should include a soft copy of the test results on a CD with the test results in .pdf format.

B1646 Data Center:

a) B1646: Racking: The fiber optic cable shall be terminated at a predesignated rack location (existing customer owned rack) within the building’s B1646’s MDF. The exact rack location/elevation by direction of HAFB telecommunications engineer TBD. The

F.O. cable will be terminated onto a Corning standard rack mountable black in color

(4RU) 12 panel fiber optic enclosure with a fully 12 preloaded High Density LC /

SM/UPC panels.

b) B1646: Fiber Terminations: All fiber optic terminations will be by a 12 strand, LC SM color coded 3 meter fusion spliced pigtails. Laser labeling (Black Font / Yellow background) will put utilized onto the rear of the pigtails identifying each of the individual 12 strand pigtail fusion splice. Telecommunications Engineer can provide examples if requested. All FOTP will have the proper labeling corresponding to each LC duplex F.O. pair. Administration 606. TIA – 604 (FOCIS) 2-6.1.3.1 WBDG UFC.

B1107 MDF-Main Distibution Frame:

c) B1107: Racking: The Contractor shall terminate the fiber optic cable at an existing customer owned predesignated rack location within the building’s 1107 Data Center. The exact rack location/elevation by direction of telecommunications engineer TBD. The F.O.

cable will be terminated onto a Corning standard rack mountable black in color (4RU) 12 panel fiber optic enclosure with a fully 12 preloaded High Density LC / SM/UPC panels.

All fiber optic terminations will be 12 strand, LC Single Mode color coded 3 meter fusion spliced pigtails. Laser labeling will put utilized onto the rear of the pigtails identifying each 12 strand pigtail fusion splice. All FOTP will have the proper labeling corresponding to each LC duplex F.O. pair. Administration 606. TIA – 604 (FOCIS) 2-

6.1.3.1 WBDG UFC.

d) B1107: Fiber Terminations: All fiber optic connectors will be Corning Fusion Spliced

LC style fiber optic pigtails 3 meter or equivalent. Provide all associated fiber optic LC adapters panels and connectors in accordance with the appropriate TIA – 604 (FOCIS) 2-

6.1.3.1 WBDG UFC. TIA-604 Fiber Optic Connector Intermateability Standard (FOCIS).

Contractors Minimal Requirements For Installers:

A. Fiber Optic Cable Installers and Splicer Qualifications: The Low Voltage /

Telecommunications Installation Company’s installers shall have at a minimum of the following documented certifications. All fiber optic installers will have 5 years of documented experience installing, terminating, and testing fiber optic and will have one or more documented CFOT or BICSI INSTF or BICSI OSP w/Fiber Cert.

B. FO-Technicians installing/handling any FO cable, media, splices, terminations and performing system tests must be certified and trained in accordance with an approved manufacturers training program, with a minimum of 5 years FO documented experience in installing FO systems. Certification includes the training, and experience of the individual on specific type and classification of FO media to be provided under this contract.

Certification / Testing / Warranty:

A. Fiber Optic Cable Testing: Tier 2 level testing shall be performed initially for all fiber optic testing and certifications of I.T.S. Perform end to end tests of all installed fiber media.

Conduct tests on single mode fiber in accordance with TIA-526-7 for single mode fiber.

Single Mode attenuation tests will be performed at 1310 Nano Meters (Nm) and 1550 Nano

Meters (Nm) wavelengths and in Bi-Directional Testing (both directions) per AF/UFC DOD standards.

B. Failures of Fiber Optic Cabling: Both Tier 1 and Tier 2 shall be performed on all FO failures. (See Test Plan Instructions).

Testing Plan:

C. The Contractor shall: prior to any testing must submit for Government review (Base

Communication’s Manager) a draft test plan of all proposed cabling and or equipment being installed under the project. The contractor’s telecommunication’s engineer must approve both the test plan and the test report before submitting to the government. Upon the draft’s approval, the contractor will complete the installation and testing of the I.T.S. The contractor then must submit a test report for all fiber and or copper cabling.

D. The Contractor’s: Test plan, must include, along with all testing system reports, a complete project test summary spreadsheet with indexed room numbers, panel labels, outlet labels and the pass / fail status of each location. The contractor will also include separately in the report the causes for test failures along with a total number of fiber and or copper outlets installed.

E. The Contractor: Shall also provide separately the total number of FO connectors, jacks, cable runs that were installed and the total number of connectors, jacks, cables runs that passed and failed all of the testing. All failed tests, will require the contractor to correct the failures with all related documentation prior to the turnover of the system.

F. Fiber Optic Cabling: Tier 1: Testing, data, analysis is always required by the government of all fiber optic cabling, any additional testing, repairs etc. shall be at the contractor’s expense. If Tier 1 testing does not prove adequate for identifying causes of failures, the government is not responsible for paying for any additional repairs that are not within or stated in the original scope of contract. The contractor shall bear the burden of all additional costs for repairs as well as any cabling that must be replaced that arise from failed testing.

G. The Contractor: Shall supply a copy of the final marked up “as builds” to the Hanscom Air

Force Base Engineer, an electronic copy (CD) AutoCAD 2018 LT or later and printed copy of all test results (include test result plots) in a three-ring binder. The contractor shall have a printed copy in each of the core MDF, IDF’s reflecting each floors cabling. All testing / installations shall be in accordance at minimum of DOD UFC 580-1; ICS ICD 705; BICSI

TDMM; EIA/TIA.

H. The Contractor: Shall follow the guidelines of this written SOW for the fiber optic cable project installations. This installation shall comply with current UFC-580-1, EIA/TIA 568B and 569-C and all other governing specifications unless otherwise specified by the Base

Communications Manager

I. All Copper and Fiber Optic: materials i.e. patch panels, wire managers, all racking, ladder tray, connectors, splice trays, fiber optic cabling should be warranty interchangeable.

Test and Final Acceptance:

A. Test and Acceptance Requirements: The Contractor shall provide As-Built Rack

Elevation, Inside Cable Plant and Outside Cable plant drawings and distributed to the

Government’s Base Communications Manager. The Contractor shall test the system in the presence of the Government Quality Assurance representative to demonstrate the functionality of the system.

B. Atmospheric Testing: The Contractor shall submit confined space safety requires air testing data to the base safety upon completion of the project. (Gas Monitoring)

C. OTDR Test Results: The Contractor shall provide the fiber optic OTDR test results with plots in standard pdf Link ware format. All fiber optic testing results shall be in a format that shows (Link Ware Bi Directional formatting.

D. AutoCAD Drawings/Prints: The Contractor shall provide a professional level pathway/route drawings will be in an AutoCAD 2018 or newer format will and shall include the manhole butterfly blowouts, GPS location(s) of manhole locations are required to be identified on the drawings.

E. Acceptance Review: The Government reserves the right to review all submitted reports for a period of 10 working days prior to acceptance. No test result or drawing will be assumed to be acceptable by the Government until the 10 day period has passed, unless the Government explicitly states otherwise.

F. Final Acceptance: The Contractor shall schedule a final project walk-through with the Base

POC no less than two (2) business days prior to acceptance.

Fiber Optic Field/Reel Testing Plan:

A. Reel-Field Testing: Prepare and provide technicians and test equipment for field tests of FO media. Conduct OTDR reel tests at the job site prior to installation.

B. Requirements: Provide all information in a combined packet to the Hanscom Air Force

Base Telecommunications Engineer a minimum of five (5) working days prior to start of work with all testing results from onsite field testing.

Field Delivery and Storage Requirements:

A. Contractor: Ship media to job site on factory reels or in factory cartons. Provide a reel drum radius no smaller than the minimum bend radius recommended by the manufacturer for the media. Wind cable on the reel so that unwinding can be done without kinking the cable.

B. Provide 2 meters (6’ .5”) pigtails of cable at each end of the reel readily accessible for testing.

C. Attach a permanent label on each reel showing length, media, identification number, and date of manufacture. Provide water resistant label and ink on the labels.

D. Apply end seals to each end of the media after testing and before terminating to prevent moisture or damage from entering the cable while stored at the job site.

E. Ensure reels are suitable for outside storage conditions when temperature ranges from minus 40 degrees C to plus 65 degrees C minus 40 degrees F to plus 150 degrees F, with relative humidity from zero to 100 percent. Store equipment, other than FO media, delivered and placed in storage with protection from weather, humidity and temperature variation, dirt and dust, or other contaminants.

Grounding and Bonding:

A. MDF/IDF Racks: All equipment racks will have a grounding lugs with a 10 foot #6

AWG green insulated grounding conductor minimum for proper bonding/grounding. A licensed electrician shall be responsible for the installation of the Telecommunications

Grounding Bar. All Ladder Tray / / Support mechanism shall comply with a continuous grounding/ bonding system utilizing #6 AWG green whips in accordance with DOD

UFC, NEC, and NFPA 70. Bond all telecommunications spaces and infrastructure in accordance with TIA 607-B where applicable.

B. NFPA 70 / NEC: Must comply for grounding and bonding requirements. Provide a telecommunications bonding and grounding system in accordance with TIA-607-B. Refer to Figure 2- 4 below. ITS grounding systems are covered in UFC 3-520-01 Interior

Electrical Systems. TIA-607-B identifies a bonding conductor known as the telecommunications bonding backbone (TBB) which is intended to equalize potentials between TRs. It should be recognized that the impedance of the TBB increases with length, thereby reducing its ability to equalize potentials between TRs.

C. ITS / RCDD Designer: must consider that the TBB for a large site may be very costly to achieve. As an alternative, the TGB in each MDF/IDF/TR can be bonded to the electrical panel board in the TR and to structural steel where applicable. Install bonding conductors in the shortest and most direct paths feasible.

D. Entrance Cable Grounding: Connect all metallic shields and strength members for outside plant cable as well as TIE/Backbone cables (as applicable) entering a building.

Grounding / Bonding will be tied into the electrical service grounding electrode system in accordance with NFPA 70, Article 800.

E. Bonding: the OSP cable shield, armor, and metallic strength member to the main building ground as close as possible to the building point of entrance with a No. 6 AWG or larger ground wire. Use a non-bonded splice case for the transition from OSP rated cable to interior rated cable. The metallic strength member to the TMGB with a No. 6

AWG or larger copper ground wire, as close to the conduit egress point as possible.

F. Conduits: Ensure all are bonded as well to the system. Ensure bonding surface contact is cleaned and verified at all points.

Suggested List of Materials (LOM)

*List of Materials-Note; the following is a SUGGESTED ONLY LOM. The Contractor is responsible for providing all materials in order to complete the entire project.

*The Contractor will provide all EXPENDABLE/CONSUMABLE materials.

Item or P/N Description Unit Quantity

Corning 192EU4- ALTOS Loose Tube, Gel-

Free, All-Dielectric Cable with Fast Access

(TM) Technology, 144 fiber, Single-mode

(OS2), max. (96-L-8.3/125), no factory splices ft 4000

12 Strand 8.3/9/125 Fiber Optic Pigtail 3m

LC/UPC Single Mode (Each pkg. contains 12 strands) Pack 24

36" Cable Rack Non-Metallic Stanchion

UDCR36-B ea 15

4 11" Cable Rack Arm UDRA11 ea 15

5 6" Cable Rack Arm ea 30

6 Cable Tags (Panduit-p/n PST-FO, 5 per pack) Pack 10

Corning Rack Mount 4RU 12 panel Fiber Optic

Enclosure - preloaded panels/inserts High

Density For LC / SM/UPC Fusion Spliced

Pigtails. ea 2

8 Consumables ea 1

Specefic Requirements (cont)

B. Bldg. 1646 Manhole Duct Bank Repairs - Repair/Replace of all crushed/damaged conduits from the exiting B1646 Data Center to supporting manhole number(s)

1,1A1, 2, 2A, 2A1 at HANSCOM AFB.

The contractor will provide, install and replace approximately 500’ of existing conduits that have been damaged/crushed at various locations.

The following manholes 1,1A1, 2, 2A, 2A1 duct banks/conduits which provide underground access into B1646 Data Center have been identified for replacement.

The contractor will repair or replace by means of a split duct conduit repair system consisting of a SCH 40 - 4” Split Duct and SCH 40 4” couplings.

All newly installed conduits will be installed and sealed per manufacture’s recommendations. All marked conduits will be carefully excavated not to disturb or further damage the active fiber optic backbone cabling which resides within them. A representative of Base Communications will be present during excavation for quality, inspection and documentation purposes. The Base Comm technician will be the main

SME for damage assessment of all fiber optic cabling.

The contractor will be responsible for dig safe permitting, confine space entry, OSHA rules and regulations governing the project. The contractor will ensure that the dig area will be returned to previous condition prior to construction.

Suggested List of Materials (LOM)

*List of Materials-Note; the following is a SUGGESTED ONLY LOM. The Contractor is responsible for providing all materials in order to complete the entire project.

*The Contractor will provide all EXPENDABLE/CONSUMABLE materials.

Item or P/N Description Unit Quantity

9 SCH 40 Split Conduit P4F 10' Section ea 50

SCH 40 Split Couplings W/ Clamps RC4F

4"x12" Split Coupling W/Clamps ea 10

SCH 40 Split Adapter Couplings W/ Clamps

C4F ea 10

SCH 40 24" Radius 90 Split Sweeps Horizontal

S4F24H90 ea 4

SCH 40 24" Radius 45 Split Sweeps Horizontal

S4F24H45 ea 4

14 Bon-duit Repair Kit BDKIT2 Kit 10