This Statement of Work (SOW) details a UHF radio installation project for the 4th Fighter Wing Command Post at Seymour Johnson Air Force Base. The project involves replacing an outdated radio communication system with four CM-350 UDX Radios, two Jotron Desktop Consoles, and a comprehensive antenna and cabling system to ensure mission-critical Command and Control (C2) communications capabilities. The contractor will be responsible for procurement, delivery, installation, system integration, and post-installation training, with work to be completed at the base located in Goldsboro, NC.

The pre-solicitation notice indicates this opportunity (Solicitation Number FA480925Q0060) is set aside for small businesses, with the Request for Quote (RFQ) anticipated to be released on or about 17 July 2025. The project is being managed by the 4th Contracting Squadron under the Department of the Air Force Air Combat Command. Key requirements include providing certified technicians, installing equipment in designated locations, ensuring system interoperability, and offering a 90-day service warranty. Interested parties must register in the System for Award Management (SAM) and can obtain solicitation information through sam.gov.

View the file

Other files

File Type Posted
Brand Name J and A_UHF Radios_CO Signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

UHF Radio Installation for 4 FW/CP

1. BACKGROUND: The 4th Fighter Wing Command Post (4FW/CP) relies on Ultra High Frequency (UHF) radio capabilities to execute Command and Control (C2) operations in accordance with multiple U.S. military regulations and directives. AFMAN 10-207, Command Post Operations, directs the implementation of the radio on the console for controller’s use in executing C2 support for all airborne assets, to include mission monitoring and emergency response coordination for all transients.

Currently, 4 FW/CP’s UHF system consists of three single-channel radios and one multichannel radio. However, the system has exceeded its life expectancy, and replacement components are no longer available on the market, rendering the three single-channel radios non-functional. At present, all UHF communications depend on the multichannel radio, creating single point of failure for a mission-critical system. Should this final radio fail, 4 FW/CP will be completely incapable of executing C2 operations via UHF, making the Command Post non-compliant with one of its core responsibilities. Given this operational risk and regulatory framework mandating effective C2 communications, a system replacement is imperative to sustain mission readiness and compliance with established Department of Defense (DOD) and Air Force requirements.

2. SCOPE: The contractor shall bear responsibility for procurement and delivery of all associated equipment listed in the bill of materials. Further, the contractor will bear responsibility for providing certified and insured technicians that are equipped with all necessary tools to complete the installation. Contractor will assist in removal of outdated equipment for GOV disposal, and bear responsibility for disposal of all excess equipment/material accumulated throughout the installation of the radio system. Upon project’s completion, technicians will provide instructions and materials with which to train all 4 FW/CP personnel on use and care of the new UHF radio equipment. Contractor will provide a 90-day service warranty under existing statement of work in addition to the manufacturer’s standard warranty in addition to one preventive maintenance inspection.

3. QUALIFICATIONS: The contractor shall provide site personnel with the skills necessary to support and accomplish the tasks as required in description of services to include the following key personnel:

· Tower climbers required to install cable and antenna equipment

· Order/Project fulfilment staff, to include shipping, lodging, and logistics personnel to provide all required materials to accomplish the project.

4. DESCRIPTION OF SERVICES:

4.1. Pre-Installation: Conduct an on-site survey, finalize system engineering data, and prepare for installation. They will also handle site access coordination, insurance verification, and compliance with industry standards. Contractor will procure, stage, connect, and test equipment before shipment, ensuring a customized GUI for the Jotron console.

4.2. Installation: The project requires the removal of the existing UHF system to create space for the installation of an upgraded communication system. The effort includes the procurement, delivery, and installation of the following key components:

Four (4) CM-350 UDX Radios integrated into an equipment rack to enhance secure and reliable C2 communications (existing rack if compatible with equipment).

Two (2) Jotron Desktop Consoles installed at designated locations within the Emergency Action (EA) Cell and Crisis Action Team (CAT) floor, ensuring seamless operation. System integration over the customer’s IP network to link the Jotron consoles with the CM radios in the COMMS closet, ensuring full interoperability.

Installation of an antenna and cabling system including:

Four (4) RF antenna transmission cables and One (1) TACO UHF antenna mounted on the existing monopole tower. The government will provide the necessary infrastructure. Tune and program the system to the required frequencies for full operational capability.

4.3. Post Installation: Upon completion, Contractor will provide brief training on CM-350 radio operation and basic maintenance, covering controls, remote access, troubleshooting, and software updates. Contractor will ensure daily cleanup and disposal of excess materials, provide a formal acceptance document upon system completion, and offer a 90-day installation warranty alongside the manufacturer’s standard or extended warranty.

5. LOCATION: The installation and training will be accomplished on Seymour Johnson Air Force Base, Goldsboro, NC, at 1510 Wright Brothers Ave, building 2902.

6. SCHEDULE: The contractor will coordinate schedule and other contractual requirements with 4 FW/CP POC or MSgt Jonathan Davis at jonathan.davis.23@us.af.mil.

7. SAFETY:

7.1. The contractor will comply with all Occupational Safety and Health Administration standards.

7.2. The contractor will adhere to best practices of safety in the workplace.

8. INSPECTION AND ACCEPTANCE: When services are complete, 4 FW/CP personnel will receive training on use of the new UHF system and its integration into the Command Post’s console.