Statement of Work - B825 Chiller dated 5 Nov 2024.pdf

PDF 109 KB Posted

Attached to
VLSB 26-2011 - B825 Replace Chillers and Boilers
Solicitation number
FA480325RO001
Issued by

About this file

This is a Statement of Work (SOW) for replacing chillers and boilers at Building 825 at Shaw Air Force Base. The project requires demolition and disposal of three existing chillers, associated piping and accessories, and installation of government-furnished 20-ton and 80-ton chillers.

The contractor must provide and install new water accessories, pumps, buffer tanks, piping, gauges, and controls to connect the new equipment to existing DDC systems. A new 750 BTU/HR Riello boiler (or government-approved equal) must be installed with associated pumps, expansion tank, and controls. The project timeline includes 21 days for material submittals, 90 days for construction, and 15 days for closeout, totaling 126 calendar days. Critical requirements include maintaining HVAC service to the Base Defense Operations Center (BDOC) during demolition through temporary heating/cooling, measuring and documenting chilled water flow rates before and after installation, and providing manufacturer startup services. All work must comply with Shaw AFB Design Standards and applicable federal/state regulations, with a one-year warranty required from the beneficial occupancy date.

View the file

Other files

File Type Posted
Sources Sought Notice - B825 Boiler.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Draft - STATEMENT OF WORK B825 Chiller and Boiler Install Project

VLSB 24-2011

11.05.2024 Project: VLSB 26-0011

Scope Of Work:

This is a project with the goal of replacing the chillers and boiler at building 825.

The replacement chillers have been purchased on a prior contract and will be supplied as government furnished equipment.

No design is required for this project. Only material submittals are required.

Material can be ordered once material submittals are approved by the Government. The material submission and approval process is estimated to take 3 weeks (21 calendar days).

General Requirements:

• Before any demolition occurs, the contractor shall measure the maximum chilled water flow through each air handler that will be affected by all chiller installs. The measured flow rate shall be recorded and submitted to the government.

• After each chiller installation is complete the contractor shall measure the chilled water flow through each air handler that was affected by the chiller installation. The measured flow rate shall be submitted to the government for approval.

• The contractor shall modify each concrete pad to accommodate the new chillers.

• The contractor shall install the necessary controls to connect the new chillers, boiler, and all pumps into the existing DDC controls.

• The Base Defense Operations Center (BDOC) cannot operate without heating or cooling; therefore, the chiller demolition shall be planned at best to not interfere with the facilities and a temporary heating or cooling shall be provided for the BDOC.

• The contractor shall insulate and wrap all new piping to meet current standards and the Shaw Design Guides.

• The contractor shall provide a factory start up by a manufacturer approved technician.

• All refrigerant is to be returned to the government. The HVAC shop will provide the refrigerant containers.

VLSB 24-2011

Chiller Requirements:

• The contractor shall demolish and dispose of the existing chillers (three), piping, and accessories. Only the outside chilled water piping shall be demolished. The cutoff point shall be just outside of the exterior wall.

• The contractor shall demolish all chilled water pumps and specialties tied to the existing chillers.

• The contractor shall install the 20 and 80 ton chillers provided by the government.

• The contractor shall provide all water accessories (piping, tanks, gauges, heat trace, etc.) needed to reconnect the chillers. The gauges included shall be temperature, pressure, and flow gauges.

Each chiller shall have gauges on both the supply and return lines.

• The contractor shall install new water specialties (pump, buffer tank, gauges, etc.) for the 20 ton chiller outside on a concrete pad in the mechanical yard if there is not enough space in the mechanical room.

The pump and water specialties shall have specifications to support the new 20 ton chiller.

• The contractor shall install new matching pump and water specialties for the 80 ton chiller.

• The contractor shall install new outdoor chilled water piping. A new piping layout shall be submitted to the government for approval before installation.

• The contractor shall install a tee tie in connection with manual valves for temporary chiller connection in case of chiller failure.

• The contractor shall install new chilled water piping form the cutoff point on the exterior wall to the new chillers.

• The contractor shall reuse the existing electrical disconnect for the 80 ton chiller.

• The contractor shall upgrade the electrical breaker, wire, and conduit for the 20 ton chiller.

• The contractor shall replace electrical wiring from the disconnects to the chillers and pumps.

• The contractor shall test and balance the new chillers.

• The contractor shall install a 5 ton 2 pipe fan coil unit with cooling only to condition the A1105 comm room. The fan coil unit shall have humidification controls.

VLSB 24-2011

Boiler Requirements:

• The contractor shall demolish the existing boiler with its associated pumps and air separator.

• The contractor shall install a new 750 BTU/HR Riello (or government approved equal) boiler. The boiler shall have a high temperature limit control with manual reset, low water cutoff switch with manual reset, and a relief valve.

• The contractor shall install new primary and secondary pumps for the hot water system.

• The contractor shall install a new expansion tank for the hot water system.

• The contractor shall install temperature and pressure gauges at the boiler and pumps inlet and outlet piping.

• The contractor shall install isolation valves and piping such that maintenance to the heating water system shall never require the system to be offline to service a pump or boiler.

• The contractor shall install new electrical wiring from the disconnects to the boiler and hot water pumps.

Total Project estimated time:

Material submittal is to be 21 calendar days.

Construction can begin when all materials for the building is approved and when all materials for that building is on site.

Total construction time is to be 90 calendar days.

Project closeout is expected to take 15 calendar days.

Total project time is 126 calendar days.

Submittal:

The contractor shall submit all materials to the government prior to purchase.

General Construction Notes:

Any references to State Government, Federal Government, or Industry standards or specifications made herein shall form a part of this specification to the extent referenced thereto and all materials and workmanship under this contract shall

VLSB 24-2011

comply with or exceed these standards and references. All referenced standards shall be the latest edition.

The Contractor shall supply manufacture’s cut sheets with the submittal where the component is identified.

Where specific part numbers or manufactures are referenced, it shall be understood that the contractor may use an approved equal.

All manufactured equipment and products shall be new materials in good condition and installed as per manufacturer's latest printed instructions, unless specified otherwise herein. The Contractor shall pay particular attention to the government non-movable equipment/furniture and work around it. The contractor will be held accountable for any damage that occurs during construction.

The user is responsible for providing an escort if required at any point during construction.

Contractor shall take into account the special treatment of hazardous waste, as well as the environmental implications related to building demolition management (i.e., fluorescent lighting tubes, t-stats, etc.). Every effort shall be made to recycle eligible materials, and those not suitable, shall be disposed of off base in accordance with all (SCDHEC) South Carolina Department of Health and Environmental Control regulations.

Contractor superintendent cannot be quality controller (CQC) and site safety and health officer (SSHO) at the same time. Meanwhile, contractor superintendent can be the SSHO. This project requires a full-time contractor superintendent and a CQC/SSHO. The CQC/SSHO is as needed with at least one visit per week.

Any refrigerant amounts removed or installed shall be documented and the information shall be provided to Shaw AFB.

If any submittal doesn’t, in the opinion of the Contracting Officer, meet or exceed the requirements contained within this SOW, in the Shaw AFB Design Standards or in any referenced design guidance or nationally recognized code then it shall be considered to be unacceptable and returned to the Contract for correction and resubmission. The Contracting Officer has the option, in lieu of disapproval, to provide acceptance of a submittal with required corrections identified if it is determined the submittal is substantially complete and correct.

Ensure that any demolition, utility cut and capping, and debris removal service performed at Shaw AFB, South Carolina in completed in such a manner that will restore a neat and professional appearance of base areas.

VLSB 24-2011

The facility/area shall be cleaned in its entirety, including exterior areas, before being returned the government.

Warranty:

Contractor shall furnish a minimum one-year warranty against defects in material and workmanship starting on the beneficial occupancy date.

General Information:

The contractor shall provide all management, tools, supplies, equipment, labor, and applicable licenses and permits necessary to complete the requirements within. All work shall be done in strict accordance with this Statement of Work and subject to the terms and conditions of the contract and in accordance with (UFC) Unified Facilities Criteria, Unified Facilities Guide Specifications (UFGS), the International Building Code (IBC), International plumbing code (IPC), South Carolina Department of Health and Environmental Control (SCDHEC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), South Carolina Department of Health and Environmental Control (SCDHEC) Shaw Air Force Base Design and Construction Standards, Change 2, 21 Aug 2018 and all other applicable codes.

Contractor is responsible for verifying all dimensions, quantities and square footages. All dimensions, quantities and square footages included are approximations. Construction and demolition shall be in strict accordance with the Shaw Air Force Base Design and Construction Standards. The information provided in this Statement of Work (SOW), the provided drawings, and the requirements of the Shaw Air Force Base Design and Construction Standards shall be determined to be the minimum standards required in this project.

The contractor shall video all areas in which work shall occur prior to starting work to include interior and exterior of the project site.

UFC’s take precedence over all standards, codes and Shaw AFB Design Standards and requirements that pertain to the work within this SOW.

During construction, the contractor shall take care not to damage existing structures, etc. that will not be replaced as part of this contract. Contractor shall

VLSB 24-2011

be responsible for the temporary support of all devices as required to perform work.

Any demolition work that needs to be accomplished to complete the contract is the responsibility of the contractor. All material shall be installed per manufacturers’ recommendations. All items listed in the SOW are to be supplied and installed by the contractor unless otherwise noted. The contractor shall be responsible for removing and reinstalling or relocating any obstructions, utilities, or components that will impede the work to be accomplished in this SOW.

A pre-construction meeting will be held at Shaw AFB to include the Contractor and Government representatives. The Government shall set up this meeting, to be held on Shaw AFB, with the Contractor and Government representatives, to discuss all remodel requirements, as well as any other construction issues the Contractor may have.

All Contractors shall be responsible for submitting a completed DD1354 (AUG 2013 edition, PDF file) with each progress payment request (beginning at 50% construction completion). This form shall be marked "Draft" until the Contractor has reached approximately 90% completion, or when it has been determined that funding will not be adjusted due to modifications. The Contractor shall have a reviewed and accepted DD1354 submitted to the Government Inspector two (2) weeks prior to the scheduled final inspection date (i.e. Placed In Service Date).

This reviewed and accepted DD1354 shall be marked "Interim" until the final inspection occurs.

Permits:

The contractor shall pay for and obtain any required permits. The contractor shall act in accordance with this Statement of Work, SCDHEC, Federal, and Shaw AFB guidelines.

The contractor must comply with all environmental provisions (see attachments).

Working Conditions:

The Contractor shall take all precautions to ensure that his operations are conducted in a manner as to minimally interfere with the normal operations of the base and the safety and convenience of the base personnel. The contractor shall coordinate utility outages with the Civil Engineering Squadron (CE) service call and the user.

Contractor shall use an approved hauling route to prevent interference with base operations. In order to prevent problems with traffic, noise, wear and tear on roads, or other problems having the potential to adversely affect health, safety, or the

VLSB 24-2011

environment, the government reserves the right to regulate routes, intervals, delivery points, and times for hauling.

All debris hauled by the contractor shall be enclosed to prevent leaking, spilling, or blowing. The Contractor shall ensure all debris or dirt is promptly removed from any transportation route if such debris is spilled, blown, or leaked from hauling equipment and vehicles. The contractor shall remove all dirt and mud caused by tracks of hauling equipment within one hour of notification by the Government. All demolition debris collected by the contractor shall be housed dumpsters and covered at all times and disposed of in an authorized landfill or transfer station. No disposal or burning is allowed on base. The contractor shall provide the government inspector with an electronic copy of each dump receipt on the following workday by 0800 with the daily report.

Daily Reports:

The contractor shall provide the government with an electronic copy of each dump receipt along with the daily report by 0800 the following workday. All daily reports will be submitted in RAKEN format and shall include pictures of work performed for each day. Daily reports shall be submitted in .pdf with report number and date for the file name (ex. 001 June 02, 2023).

End of Statement of Work.