Statement_of_Work_-_Attachment_A.pdf
PDF 170 KB Posted
- Attached to
- Visitor Center HVAC System Planned Maint Federal contract opportunity
- Solicitation number
- 140P6426Q0110
About this file
This is an Itemized Tasks attachment from the National Park Service that specifies the maintenance and inspection requirements for multiple HVAC, boiler, pump, and humidification systems.
The document details semi-annual and annual maintenance tasks for the following equipment: one York Chiller with 24 itemized maintenance tasks (mostly semi-annual, with condenser coil washing and oil sampling performed annually); two Riello Boilers with 16 itemized tasks performed annually including burner inspection, hydrostatic testing, safety valve certification, combustion analysis, and annual maintenance kit installation; four Taco Pumps with 6 semi-annual inspection tasks covering leaks, vibration, bearing lubrication, electrical connections, and flow rate verification; one Carrier Air Handler with quarterly filter and belt replacement requirements plus semi-annual and annual inspections of blower assembly, coils, electrical components, condensate drain systems, and system performance parameters; two Condair Humidifiers with semi-annual and annual maintenance including pump unit servicing, solenoid valve testing, humidity sensor calibration, filter replacement, and system disinfection; twelve Titus Variable Air Volume (VAV) boxes with semi-annual and annual testing of damper operation, airflow measurement, control response, and sensor calibration; general system components (pipes, fittings, valves, ducts) requiring semi-annual inspection; and five Modine hanging heaters requiring annual inspection of motors, coils, water control valves, thermostats, and power switches. The tasks encompass performance testing, component cleaning, calibration, leak detection, electrical verification, and comprehensive documentation of all maintenance activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Equipment_Data_Plates_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Sol_140P6426Q0110_Amd_0001.pdf | ||
| DOL_Wage_Determination.pdf | ||
| Sol_140P6426Q0110.pdf | ||
| Statement_of_Work.pdf | ||
| Price_Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
National Park Service U.S. Department of the Interior
Attachment A – Itemized Tasks
York Chiller
Task Semi-
Annual Annually Check chiller operating performance and conduct control tests X
Review operator logs and provides recommendations X Inspect compressor under load/unload conditions and verify capacity controllers X
Inspect condenser and evaporator for cleanliness and performance X
Perform external leak tests X
Inspect and calibrate control systems X
Verify all control setpoints and adjust as needed X
Check for refrigerant and oil leaks, repair if necessary X Test sensors and safety devices (transducers, thermistors, signal transmitters) X
Verify water flow across condenser X
Inspect gauges and thermometers X
Service starter and control panel, clean and tighten connections X
Inspect electrical components (contactors, relays, switches) X
Check filters for pressure drop X
Inspect pressure relief valves and auto air bleeders X
Record operating voltage/current of compressor-motor assembly X
Run diagnostics on motor starter X
Clean/replace contact points (if applicable) X
Run diagnostics on system control panel X
Tighten terminal connections X
Verify data accuracy and setpoints X
Check water flow and pressure drop across condenser and cooler X
Test flow switch operation X
Conduct leak checks X
Wash Condenser Coils with Hot Water X Collect oil sample and submit for testing X
Riello Boiler (2)
Task Semi- Annual Annually Monitor pressure and temperature gauges X Inspect burner flame and flame failure response X Perform bottom blowdown to remove sludge X Observe operating and high-limit controls X Test limit and flame detection controls X Tune burner settings (performed by qualified technician) X Inspect and clean burner cone and combustion chamber X Check fuel pressure settings and regulator operation X Disassemble and inspect LWCO and auxiliary LWCO X Hydrostatic test for leaks in tubes and piping X Clean boiler interior (fire side and water side) X Inspect refractory for damage X Replace or re-certify safety valves X Bubble test fuel train safety shut-off valves X Provide and install annual maintenance kit per unit X Provide and Install condensate neutralizer per unit X Conduct Combustion analyzation of each unit, check for proper operation and adjust to manufacturers specifications. X
Taco Pumps (4)
Semi-
Annual Annually Inspect for water leaks, unusual vibration, or motor noise X Check and replenish grease in motor bearings X Inspect & tighten electrical terminals. X Ensure motor winding and terminal box remain dry and secure X Verify motor orientation and mounting alignment X Check flow rates and ensure operating within nameplate pressure limits X
Carrier Air Handler
Task Quarterly Semi-
Annual Annually General Inspection
Inspect air handler cabinet for signs of damage or corrosion
X
Check for unusual noises or vibrations X Verify secure mounting and connections X Inspect insulation for wear or moisture X
Blower Assembly Inspect blower wheel for dust and debris X Clean blower wheel and housing X Check motor operation and amperage draw X Lubricate motor bearings (if applicable) X Inspect and adjust belt tension (for belt-driven units) X Replace worn belts (recommended every 90 days for commercial units) X
Air Filters
Inspect filters for dirt and damage X Replace disposable filters X Verify proper filter fit and sealing X
Coils Inspect evaporator and heating coils for dirt and corrosion
Clean coil surfaces with approved cleaner X Check for refrigerant leaks or damage X Ensure proper airflow across coils X
Electrical Components Inspect wiring for wear, corrosion, or loose connections
Check control board and relays X Test safety switches and sensors X Verify thermostat operation and calibration X Condensate Drain System X Inspect drain pan for cracks or standing water X Clean drain lines to prevent clogs X Test float switch operation (if installed) X
System Performance Measure supply and return air temperatures X
Check static pressure across the system X Verify airflow matches design specifications X Confirm system cycles properly X Documentation X Record all findings and corrective actions X Note date of service and technician name X Update maintenance log and schedule next inspection X
Condair Humidifiers (2)
Task Semi- Annual Annually System Review
Overall system function test X Inspect nozzle spray patterns X
Pump Unit Filter(s) replacement (Annually) X Check condition of pump X Solenoid valve(s) test X Change gasket kit in high pressure relief X Functional test of the high pressure gauge X Functional test of pressure switch X Test ON/OFF Valve X Inspect electrical connections in control cabinet X
Humidity Sensor(s) Humidity sensor test/adjustment (replace if ±10% deviation) X Max humidity controller check (max hygrostat) X
Controls Unit Transfer relay replacement X Contactor test X Contactor/thermal relay replacement X
Hygiene Bactiquant® test X System disinfection/cleaning X
Titus VAVs (12)
Semi-
Annual Annually Visual inspection of VAV boxes and ductwork for damage or leaks X Check for signs of condensation or water damage X Verify access panels are secure X Test damper operation (open/close response) X Measure and verify airflow against design specs X Inspect control system response to thermostat changes X Check electrical connections and motor operation X Calibrate thermostats and sensors X Inspect actuator and damper linkage for wear or looseness X Verify minimum and maximum damper positions X Check insulation and box integrity X Test pressure sensors and airflow stations X Full system performance review X Recalibrate airflow sensors and controllers X Inspect and clean all internal components X Review and update BAS setpoints and zone configurations X Document all findings and schedule follow-up actions X
General Systems
Pipes, fittings, valves, ducts, dampeners, etc.
Semi-
Annual Annually General inspection of all system components (e.g. valves, insulation, etc.) X
Modine hanging heaters Inspect motor for proper fan operation X Make sure coils are clean X Make sure water control valves are working properly X Check thermostat operation X Check power switch operation X
| York Chiller |
| Riello Boiler (2) |
| Taco Pumps (4) |
| Carrier Air Handler |
| Condair Humidifiers (2) |
| Titus VAVs (12) |
| General Systems |
File details come from the government source that posted it. Updated .