Statement of Work - 70Z03826QB0000156.pdf

PDF 130 KB Posted

Attached to
MH-65 Fuel Tank, Front RH Repair
Solicitation number
70Z03826QB0000156
Issued by

About this file

This is a Statement of Work for the repair of a Fuel Tank, Front RH component (NSN 1560-14-516-1081, Part Number 704A44-500-071) utilized on the United States Coast Guard's MH-65 helicopter. The contractor must perform test and evaluation upon receipt to determine component condition and classify items as Ready for Installation (RFI) or Non-Ready For Installation (NRFI), with repairs to be completed at a firm fixed price. Work may be performed at the contractor's facility or a USCG-approved facility, with all necessary test equipment and facilities provided by the contractor.

The contractor must complete test and evaluation within 15 calendar days of component receipt and full repair within 90 calendar days of receipt. The contractor must maintain certification as a FAA or European Aviation Safety Agency (EASA) Part 145 Certified Repair Facility, OEM, and/or USCG SRR Engineering approved repair facility for the entire contract duration and comply with ISO 9001, AS9100, or equivalent quality management system requirements. Each repaired component must be accompanied by a DD Form 1574 Serviceable Condition Code Tag or FAA Form 8130-3 Airworthiness Approval Tag, a Certificate of Airworthiness, a Certificate of Conformance signed by an authorized official, a failure data report documenting the maintenance performed, and for tracked components, a Component Repair Record (CRR) mailed to USCG ALC within five business days of completion. The contractor must also provide documentation of complete unbroken ownership history from the approved manufacturing source and retain copies of all records for 90 calendar days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

70Z03826QB0000156

Contractor Requirement

1. This requirement is for the REPAIR of the item(s) listed in the following table utilized on the United

States Coast Guard (USCG)’s MH-65 helicopter.

FUEL TANK,FRONT RH 6 1560-14-516-1081 704A44-500-071

2. Upon receipt of the components, the contractor shall perform a test and evaluation to determine the condition of the items. If, after visual and functional inspections, an item is found to meet manufacturer's minimum performance specifications and is determined to be Ready for Installation

(RFI) or Non-Ready For Installation (NRFI), the contractor will be allowed to fix at the firm fixed price for the repair only. The contractor shall prepare a failure data report IAW paragraph 13 which shall be included with the returned component. The parts shall be marked "RFI” or “NRFI” and returned as-is.

3. Non-RFI components shall be noted and returned to the USCG with an Unsatisfactory Report Tag, which will be attached to each non–RFI item.

4. Work under this purchase order shall be performed at the contractor’s facility or USCG approved facility. The contractor shall provide all necessary test equipment and facilities to evaluate the components listed in this purchase order at the firm-fixed prices listed in the schedule. Any deviations must be approved by the USCG.

5. The contractor must have access to required CMMs, specifications for test/acceptance criteria and any other required data to ensure all components are tested IAW the OEM’s current specifications and procedures. Original design or functional capabilities of the end item and parts thereof shall not be changed unless authorized or directed by the requirements of this SOW.

6. The Contractor must have access to all applicable documents and obtain current editions of all applicable documents. The USCG does not own, nor can it provide the technical documents specified herein. Neither the closing date for receipt of offers nor contract award will be delayed pending receipt of these documents for any offeror.

7. Additionally, the MH-65 helicopter is used primarily around salt water at low altitude for search and rescue missions. Therefore, corrosion is to be anticipated and is considered "normal" for the aircraft.

The USCG will be notified if found to have excessive corrosion

8. The Government shall not be liable for any amount expended by the contractor in excess of the applicable firm fixed price reflected in the schedule unless prior written authorization has been given by the KO.

9. The contractor shall submit a failure data report for each unit. This report shall include NSN, Part

Number, Serial Number, nomenclature, date of test, contract delivery order number, line-item number, description of repair failure, the USCG’s reported failure. This report shall be attached to the packing slip and shipped with the repaired component.

10. The contractor is required to be certified and maintain a quality system that complies with the requirements of ISO 9001 Quality Management Systems – Requirements, AS9100, or equivalent. The contractor is responsible for performing or assuring all inspections, tests and calibration necessary to substantiate that the goods or services furnished conform to Government’s requirements. The contractor shall take prompt action to correct conditions that have or could result in goods or services that do not conform to contractual requirements. Records of conformance shall be maintained on file at the contractor’s facility and made available or provided for review by the Government upon request. The Government reserves the right to conduct surveillance at contractor’s facility to verify the existence, adequacy and effectiveness of the quality system. Upon request of the Government, the contractor(s) shall forward a copy of their current certification and Quality Assurance Manual for review.

11. The contractor shall maintain, at a minimum, one of the following: FAA or European Aviation Safety

Agency (EASA) Part 145 Certified Repair Facility, OEM, and/or USCG SRR Engineering approved repair facilities for repair of components identified in the Schedule for the entire duration of this

Purchase Order. The Contractor shall provide immediate notification to the KO upon loss of any required certifications. The contractor shall also:

• Comply with the certification/documentation requirements specified herein.

• Attach certifications/documentation to the outside of the shipping container.

12. All units under the provisions of this contract must be airworthy and suitable for installation on USCG aircraft. Each returned component shall be tagged with a DD Form 1574 Serviceable Condition Code

Tag or a FAA Form 8130-3, Airworthiness Approval Tag, completed in its entirety. The contractor shall furnish a Certificate of Airworthiness in accordance with FAA procedures (or USCG approved alternate procedure) and a Certificate of Conformance (COC) IAW FAR 52.246-15 for all components. These forms shall be packaged with each component.

13. The COC shall be signed by an authorized official of the approved source and must specify the nomenclature, manufacturer's part number and date of manufacture. For Production Approval Holder, a COC AND a copy of the FAA Parts Manufacturer Approval (PMA) or other manufacturing authorities shall be provided. Contractors shall also provide documentation reflecting the complete unbroken history of ownership of the parts from purchase from the approved manufacturing source until delivery to the USCG.

14. ALC considers components ready for issue (RFI) upon acceptance.

Purchase Order Requirements

1. The following table shows the required delivery for each priced line item listed in the schedule. Early deliveries, when appropriate, are desired and acceptable.

Line items Item Description Due No Later Than:

1-11 Repair Ninety (90) calendar days after receipt of components

1-11 Test and Evaluation Fifteen (15) calendar days after receipt of the components

Tracked Items

When checked the contractor shall comply with the following documentation requirements:

The components under this Purchase Order are tracked in the USCG’s Asset

Computerized Maintenance System (ACMS). ACMS is the management information system used to schedule and record all USCG equipment maintenance actions and calibration intervals.

Significant Component History Report (SCHR)

Tracked components will be shipped to the contractor with an SCHR. The SCHR records the maintenance history of the serial number tracked components. It remains with its corresponding part until reinstalled on an aircraft or is annotated “BER” and scrapped. (NOTE: written approval from the KO is required prior to scrapping a serial number tracked component). The SCHR for scrapped components shall be returned with the component. The Contractor shall retain a copy of the SCHR for 90 calendar days.

Component Repair Record (CRR)

The Contractor will provide a CRR with the repaired components. The CRR records the maintenance performed on a serial number tracked component and enrolls or disenrolls components from ACMS when those components are scrapped, added to, or removed from the USCG inventory. At a minimum, the

CRR shall identify the equipment and contain a description of the maintenance action performed, parts replaced, service bulletins and modifications. The Contractor shall mail one (1) copy of the CRR to

USCG ALC, ATTN: AVENG/ACMS, Elizabeth City, NC 27909-5001 no later than five (5) business days following completion of the rework effort. The original CRR shall be packed with the component.

The Contractor shall retain a copy of each CRR for 90 calendar days. The Contractor may request that their in-housework order be accepted to fulfill the CRR requirement. The KO will provide a written determination in response to the request.

File details come from the government source that posted it. Updated .