Statement of Work -28 Aug 2024.pdf

PDF 337 KB Posted

Attached to
Paving IDIQ at JBLM Federal contract opportunity
Solicitation number
W911S8
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Joint Base Lewis-McChord

About this file

This is a Statement of Work detailing the requirements for an Indefinite Delivery Contract (IDC) for roadway and airfield paving projects at Joint Base Lewis-McChord (JBLM). The contractor must provide labor, tools, equipment, and materials for maintenance, repair, and minor construction work on vehicle roadways and airfield paving projects across Lewis-Main, Lewis-North, and McChord Field areas.

The scope includes roadway pavement work (Hot Mixed Asphalt or concrete for vehicular traffic), airfield pavement work (surfaces for aircraft traffic including runways, taxiways, and hangar floors), range roads (combat vehicle trails), sidewalks, curbs and gutters, and parking lots. Key requirements include demolition, installation of HMA and concrete pavements, excavation, grading, pavement rejuvenation, crack repairs, and utility work. The contractor must provide qualified personnel including a Project Manager with 5-10 years of experience, a Superintendent with 5 years of experience, a Site Safety and Health Officer, and a Quality Control Manager. Environmental requirements include compliance with asbestos and lead paint regulations, stormwater management, soil testing, and archaeological preservation protocols. The contractor must also comply with AT Level 1 training, iWATCH training, and OPSEC requirements for base access and security.

View the file

Other files for this federal contract opportunity

Other files attached to Paving IDIQ at JBLM, newest first.
File Type Posted
Source Sought Synopsis - Paving (19 Dec 24).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Exhibit C 8/28/2024

SECTION 01 11 00

STATEMENT OF WORK

8/28/2024

PART 1. GENERAL

1.1 DESCRIPTION OF WORK:

The Contractor shall provide all plant, labor, tools, equipment, and materials (except as indicated otherwise in the specifications) and perform all work in strict accordance with the specifications and plans required for the Indefinite Delivery Contract (IDC). The IDC is for a broad range of maintenance, repair and minor construction work on vehicle roadways and airfield paving projects at Joint Base Lewis-McChord (JBLM). For this contract, Joint Base Lewis McChord includes Lewis-Main, Lewis-North, and McChord Field areas of JBLM. The work is required in support of Public Works (PW) activities headquartered at Joint Base Lewis-McChord (JBLM). During the contract period, the Government will identify tasks required to complete each specific job and will issue Requests for Proposals. The Contractor shall be required to furnish all materials, equipment and personnel necessary to manage and accomplish the Task Orders (TOs) as ordered from the IDC. The Task Orders may include construction, removal, replacement, and repairs associated with roadway and airfield projects, as defined below. Removal, replacement and repair of existing subgrade, utilities, shoulders, curbs, gutters, sidewalks and other real property common to roadway and airfield pavements shall also be included – depending on unique requirements of individual task orders.

1.2 DEFINTION OF “ROADWAY AND AIRFIELD PROJECTS”:

1.2.1 Roadway Pavement: Is a surfaced area designated to carry vehicular traffic that includes the entire pavement system structure above the subgrade. Hot Mixed Asphalt (HMA) or concrete required to support vehicle loadings whether they are the traveled way, shoulders, turn lanes, auxiliary lane, parking lots, is to be considered roadway pavement.

1.2.2 Airfield Pavement: Is a surfaced area designated to carry aircraft traffic and includes the entire pavement system structure above the subgrade. HMA or concrete required to support aircraft loadings, whether interior (hangar floors) or exterior, (runway, taxiway, taxi lane, aprons, shoulders, landing pads) is to be considered airfield pavement.

1.2.3 Range Roads: (Also known as Combat Vehicle Trails) are permanent roads used to access combat training areas on JBLM. Trails are to be useable by heavy tactical vehicles and equipment, construction equipment, log hauling operations, and lowboy truck and trailer. Typical Range Road can include:

- Speed 25 mph

- Subgrade 20 to 24 feet wide includes a 2 to 3 foot ditch

- Running Surface 16-20 feet wide

- Surfacing Crushed Rock

- Minimum Curve Radius 50-feet plus curve widening

1.2.4 Sidewalks: Is a safe path for people to walk along that is separated from motorized traffic.

Sidewalks may also be used as a paved path, trail or footpath that is not next to a road, for example, sidewalks between barracks, business, parking lots or recreational area. Surface material can be cement concrete, asphalt or gravel. Sidewalks are to be Americans with Disabilities Act (ADA) compliant, constructed on top of a prepared gravel base, and to match existing grades. Most sidewalks are constructed as part of larger road projects; however, task orders can be awarded primarily as sidewalk construction.

1.2.5 Curb and Gutter: Used to separate the road from the roadside, control traffic flow, discourage drivers from parking or driving on sidewalks or leaving the roadway at non-controlled access points. They also provide structural support to the pavement edge. Curbs and gutters can be used to channel runoff water from rain or melted snow and ice into storm drains. Typically curb and gutter will be made of Portland cement concrete with an approximate total height of 16-inches and a gutter width of 12-inches and curb width of 6-inches. Concrete can be placed by a slip form/extrusion machine, formed method, or by a combination of these methods.

1.2.6 Parking Lot: Is a cleared area that is intended for parking vehicles that has a concrete, asphalt or graveled surface. The area is organized into parking spaces, which are generally marked with paint lines or wheel stops for each vehicle and driving lanes in between so that vehicles can drive into and out of the spaces. The arrangement of the parking spaces relative to the driving lanes can feature perpendicular parking spaces, angle parking, or parallel parking, or possibly some combination of these.

1.2.7 Typical Work Requirements:

1.2.7.1 Principal work activities shall include preparation of roadways and/or airfield pavements to uniform grades and cross-sections for specific projects/task orders. These may include:

- Demolition, relocation and/or installation of Hot Mix Asphalt (HMA) and concrete pavement for roadway and airfields

- Demolition, relocation and/or installation of HMA and gravel for parking lots

- Clearing and grubbing, excavation, backfill, compaction, and grading.

- Grade and install gravel for Range Roads

- Pulverize and/or planning Asphalt, excavate and haul.

- Pavement rejuvenation to include crack and joint repair, pavement patch, bituminous surface treatment

- Demolition, relocation and/or installation of concrete sidewalk, curb and gutter.

- Airfield pavement crack, joint and spall repair

- Airfield concrete pavement panel replacement

1.2.7.2 Ancillary activities in a roadway and airfield project shall include :

- Demolition, relocation and installation of concrete sidewalk, curb and gutter

- Pulverize planing asphalt, excavate and haul.

- Demolition, relocation and/or installation of stormwater drainage pipe and structures.

- Demolition, relocation and/or installation of potable water pipe and fire hydrants.

- Demolition, relocation and/or installation of sanitary sewer pipe.

- Erosion control.

- Vehicular and pedestrian traffic control.

- Layout and installation of pavement markings.

- Layout, demolition, relocation and/or installation of traffic signal light induction loops and underground electrical power.

- Demolition, relocation and/or installation of fences.

- Provision of trees

1.2.7.3 Other related minor construction activities that meet a minimum estimated magnitude of construction of $50,000 and shall include:

- Excavation, grading, compaction, prepping, re-sloping, etc the grounds around a facility.

- Underground utility work not restricted by privatization.

- Fencing, etc.

1.2.7.4 Site Layout: The contractor shall be responsible for determining vertical, horizontal, angle points, distances, surface and subsurface features, construction staking, and layout relevant to each task order, based on government provided simplified sketches. Staking and layout may include calculating and setting elevations and grades to provide positive drainage for pavements, curbs and gutters and drainage structures verifying (e.g. the furnished sketch shows the geometry of a new parking lot and the contractor provides all layout including calculating elevations and grades). The contractor shall survey existing conditions of the work site, including topography, existing buildings and infrastructure, and underground infrastructure whenever possible (e.g. measuring invert elevations and diameters of sewers at manholes) to ensure usably complete end product compliant with all specifications.

1.3 ELECTRONIC SUBMITTALS

1.3.1 Transmittal Form: All submittals shall be submitted electronically unless specified otherwise in the Task Order. The contractor shall use the electronic version of the transmittal form (ENG Form 4025) for submitting both Government-approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.3.2 Submittal Format

1.3.2.1 Drawings: The submission of drawings shall be in an electronic drawing file in AutoCAD format and a second electronic copy in PDF format (to facilitate review by Government personnel who do not have AutoCAD software).

See A/E/C CADD Standard Release 6.0 for detailed standards for the drawings. The reference is located at https://www.wbdg.org/ccb/AECCAD/ERDCITL_TR12-6_r6.pdf

1.3.2.2 Other submittals: For catalog cuts, illustrations, printed specifications, or other data submitted inapplicable portions shall be marked out and applicable items such as model numbers, sizes, and accessories shall be indicated by arrows or highlights. The submittals will be provided in electronic (.pdf) format http://www.wbdg.org/ccb/AECCADD/aeccaddstd.PDF

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Location: The work shall be performed at various locations on Joint Base Lewis - McChord, Washington.

1.4.2 EXHIBIT LINE ITEMS (ELINS)

1.4.2.1 This is a pre-priced line-item contract. Task Orders issued under this contract shall be priced based on the ELINS identified in the ELIN Pricing Schedule (TE 01), and as described in the ELIN Descriptions (TE 02). On rare occasions, some task orders may include work that is not included on the ELIN schedule. In these cases, non-pre-priced (NPP) items may be negotiated, but the total price of all NPP items cannot exceed 10% of the task order value. Furthermore, any proposal with a NPP item exceeding $2500 must include three quotes from competing sub-contractors/suppliers, to aid the government in establishing fair and reasonable pricing for the NPP items.is a pre-priced line item contract.

Task Orders issued under this contract shall be priced based on the ELINS identified in the ELIN Pricing Schedule (Technical Exhibit C), and as described in the ELIN Descriptions (Technical Exhibit D). On rare occasions, some task orders may include work that is not included on the ELIN schedule. In these cases, non-pre-priced (NPP) items may be negotiated, but the total price of all NPP items cannot exceed 10% of the task order value.

Furthermore, any proposal with a NPP item exceeding $2500 must include three quotes from competing sub-contractors/suppliers, to aid the government in establishing fair and reasonable pricing for the NPP items.

1.4.2.2 The ELIN descriptions define the scope of work for each ELIN and reference the applicable technical specification by which the contractor must comply. Each ELIN description includes all labor, materials, equipment, mobilization, demobilization, clean-up, supervision, overhead, and profit required to perform the work. The ELIN Pricing Schedule identifies the unit of measure (and unit pricing upon award) for each ELIN.

1.4.2.3 The ELIN unit pricing will be fixed for the life of the contract, adjusted only with the exercise of each option period, by applying a co-efficient that will be calculated in accordance with the methodology described in the Statement of Work.

1.4.3 COMPUTATION OF COEFFICIENT FOR OPTION PERIODS

1.4.3.1 To ensure ELIN pricing is adjusted to reflect current market prices, a co-efficient will be calculated and applied to each Option Period. The contractor’s ELIN pricing for the base period shall be considered to have a co-efficient of 1.0. With the exercise of each Option, a new co-efficient will be calculated, based on the formula in paragraph 1.4.3.2 below. This co-efficient will then be applied to the sum of each task order’s negotiated ELINS, to result in the final task order pricing.

1.4.3.2 The computation of the coefficient for option years will be in accordance with the following formula:

pl = p x f Definitions:

pl = New Coefficient p = Coefficient Factor for Previous Contract Period (Note: Base Period Coefficient = 1.0) f = Index Factor

a. The Index Factor f, shall be computed according to the following equation:

f = CCI-C

CCI-B

b. Where: CCI-C is the Construction Cost Index (CCI) for the month in which the option period is exercised, as published by the ENR (formerly called the Engineering News Record).

c. The CCI-B is the CCI for the month in which the contract’s base period was awarded.

d. In computing f, the CCI-C may be located on the “Market Trends” page of the ENR issue current at the time that the option year is exercised.

1.4.3.3 If the CCI ceases to be published, the parties will agree on substitute indices to be used and the contract modified accordingly. Coefficients will not be adjusted for any other changes or circumstances encountered during the life of the contract. When it is determined that a task order requires modification the Contractor shall calculate his proposal using the same coefficient that was used in calculating the basic task order, regardless of the date of the modification.

1.4.4 ORDERING PROCEDURE

1.4.4.1 A Request for Proposal (RFP) with a project specific Statement of Work (SOW), that may include government provided concept sketch, and submittal register will be issued to the contractor. The Contractor will not be reimbursed for any pre-task order costs, including, site visits, proposal preparation, or attendance during negotiations.

1.4.4.2 A site walk(s) and scoping meeting(s) will be conducted with the government and contractor prior to submission of the proposal. The scope of work, sketches, recommended improvements, and means and methods of construction will be discussed.

1.4.4.3 The contractor will submit a proposal using the Exhibit Line Items (ELIN) pricing schedule that includes the appropriate ELINS and associated quantity take- offs applicable to the Task Order. The total price of the proposal will be established by multiplying the pre-priced unit price of each ELIN times the contractor’s proposed quantities for each ELIN. These ELINS will then be totaled, and the sum will be multiplied by the appropriate co-efficient (1.0 for the base period or the appropriate Option Period co-efficient, as calculated by the formula in Paragraph 1.4.3 above). The contractor will also include with its proposal a preliminary construction schedule, any recommended improvements to the SOW or sketches, and when applicable, a preliminary traffic control plan.

a. The description of each ELIN is included in Technical Exhibit D.

b. Non pre-priced (NPP) items are not to exceed 10% of the overall task order value. NPP items over $2,500 require three competitive quotes.

c. For individual ELINS, if a fraction of an ELIN unit is proposed, the total price of that

ELIN shall be submitted by rounding to the nearest penny.

1.4.4.4 A meeting may be conducted between the government and contractor to discuss applicable ELINS, quantities, non-pre-priced items (NPP), construction duration, and any changes to scope or sketches (recommended improvements).

1.4.4.5 ELINS agreed upon during discussions for each Task Order (to include the means and methods of construction) shall be considered to be included in the scope of work for that Task Order. Specific quantities agreed upon however shall only be used for the pricing of the Task Order and will not be binding on either party unless otherwise specified in the Task Order SOW. Tasks orders shall be awarded as firm fixed-prize awards based on tasks and specifications contained in award SOW and referenced Technical Exhibits.

1.4.4.6 A bilateral, firm fixed price task order will be awarded by the contracting officer to complete the work as negotiated, to include the final SOW and sketches. The contractor cannot begin work until the Contracting Officer has approved the applicable performance and payment bonds and a notice to proceed (NTP) is issued.

1.5 CONTRACT DRAWINGS

Contractor shall provide “as-built” drawings as required for each Task Order

1.6 CONTRACTOR PERSONNEL AND SUB-CONTRACTOR QUALIFICATIONS

1.6.1 The Prime Contractor shall provide a Project Manager. The Project Manager shall be responsible for the overall management of the task order and is subject to removal by the Contracting Officer for non-compliance with the requirements specified in each task order.

The individual shall be employed by the Prime Contractor. The roles of the Project Manager are the administration of construction from start to finish including Safety, Quality, Cost and Schedule. Oversees the performance of all trade contractors and reviews architectural and engineering drawings to make sure that all specifications and regulations are being followed. Supervises Superintendent(s), reviews their reports, checks on any reported difficulties, and corrects any safety violations or other reported deficiencies.

Tracks and controls construction schedule and associated costs to achieve completion of project per task order. The Project Manager shall possess either of the following combinations of experience and education:

i. Baccalaureate Degree in engineering, architecture, construction management, or construction technology and five years’ experience working as a Project Manager (or in a position with equivalent responsibilities) simultaneously managing multiple construction projects.

ii. Ten years’ experience working as a Project Manager (or in a position with equivalent responsibilities) managing construction projects.

1.6.2 The Prime Contractor shall provide a Superintendent. The project superintendent shall be responsible for the supervision of all on site construction activities and is subject to removal by the Contracting Officer for non-compliance with the requirements specified in each task order.

The individual shall be employed by the Prime Contractor. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer. The Superintendent shall possess the following experience:

i. Five years’ experience working as a Construction Superintendent (or in a position with equivalent responsibilities) managing construction projects.

The Superintendent can fulfill the role of SSHO but cannot perform the function of Quality Control Manager.

1.6.3 The Prime Contractor shall provide a Site Safety and Health Officer (SSHO) as required in the EM385-1-1 and in accordance with the Specification Section entitled “Governmental Safety Requirements”. The Contractor SSHO may be assigned other duties in addition to the duties required as SSHO.

1.6.3.1 The responsibilities associated with the Site Safety and Health Officer positions are required for each task order. The Contracting Officer reserves the right to require the replacement of the individual performing these combined duties if not performing satisfactorily. If responsibilities are combined and performed by one individual, the contractor shall define who is performing each responsibility with the task order proposal.

1.6.4 The Prime Contractor shall provide a Construction Quality Control (CQC) System Manager as required in the specification section titled QUALITY CONTROL. The individual shall be employed by the Prime Contractor. The Contracting Officer reserves the right to require the replacement of the individual performing these combined duties if not performing satisfactorily. If responsibilities are combined and performed by one individual, the contractor shall define who is performing each responsibility with the task order proposal. The Quality Control Manager can fulfill the role of SSHO but cannot perform the function of Superintendent.

1.6.5 The Prime Contractor shall provide:

1.6.5.1. Qualified Person to conduct inspections under Part 4 of the 2024 (or later) Construction General Permit (CGP).

(a) Qualified Person shall have a minimum of 5 years related experience working on projects of similar nature, scope and dollar value. Qualified person shall not be assigned any other duties.

(b) Qualified Person shall have EPA Construction Inspection Training certification and Washington State Certified Erosion and Sediment Control Lead certification.

(c) Provide an alternate Qualified Person.

1.6.5.2. Construction work to meet Parts 2.2 (BMPs w/ maintenance timelines/steps), 2.2.14.a. (stabilization deadlines), & 9.10.3 of the EPA Construction General Permit and Part S.4. (discharge monitoring) of the WA State Construction Stormwater General Permit.

WA State CESCL training (at cost) -https://ecology.wa.gov/regulations-permits/permits-certifications/certified-erosion-sediment-control

EPA Stormwater Inspection Cert (Free/online) https://www.epa.gov/npdes/construction-inspection-training-course

1.7 OCCUPANCY OF PREMISESs

Before work is started, the Contractor shall arrange with the Contracting Officer Representative a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, and corridors.

1.8 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fecology.wa.gov%2Fregulations-permits%2Fpermits-certifications%2Fcertified-erosion-sediment-control&data=05%7C02%7Chenry.c.egbuka.civ%40army.mil%7Cd3cddd542f6c4afe55b108dc7b805bf8%7Cfae6d70f954b481192b60530d6f84c43%7C0%7C0%7C638521038425543121%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=Vms2dcgCYVfvksgP2MLzV9jNdNfGPx3feq4jyuks8Lg%3D&reserved=0 https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fecology.wa.gov%2Fregulations-permits%2Fpermits-certifications%2Fcertified-erosion-sediment-control&data=05%7C02%7Chenry.c.egbuka.civ%40army.mil%7Cd3cddd542f6c4afe55b108dc7b805bf8%7Cfae6d70f954b481192b60530d6f84c43%7C0%7C0%7C638521038425543121%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=Vms2dcgCYVfvksgP2MLzV9jNdNfGPx3feq4jyuks8Lg%3D&reserved=0 https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fwww.epa.gov%2Fnpdes%2Fconstruction-inspection-training-course&data=05%7C02%7Chenry.c.egbuka.civ%40army.mil%7Cd3cddd542f6c4afe55b108dc7b805bf8%7Cfae6d70f954b481192b60530d6f84c43%7C0%7C0%7C638521038425548854%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=8l9beayWo%2FSa0%2BSYXosUURRn%2Fvj45B4QQLq0akD%2Fyeg%3D&reserved=0

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.9 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged shall remain the property of the Government. The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area.

Contractor shall maintain property control records for material or equipment designated as salvage.

Contractor's system of property control may be used if approved by the Contracting Officer.

Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.

2. SPECIFICATIONS AND CODES

2.1 Codes

2.1.1 The Contractor shall comply with the most recent edition, at time of solicitation, of all pertinent Local, State, and Federal building and life/health/safety codes, including but not limited to the following:

2.1.1.1 Applicable Unified Facilities Criteria (UFC)

2.1.1.2 UFC 1-200-01: General Building Requirements http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01

2.1.1.3 UFC 3-420-01: Plumbing Systems and International Plumbing Code

2.1.1.4 UFC 3-201-01: Civil Engineering

2.1.1.5 [UFC 1-200-02: High Performance and Sustainable Building Requirements] https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02

2.1.1.6 ASA IE&E SDD policy https://www.wbdg.org/ffc/army-coe/policies-and-guidance-army-design-and-construction/army-sdd-policy-update

2.1.1.7 [UFC 1-201-01 Non-Permanent DOD Facilities in Support of Military Operations]

2.1.1.8 EM 385-1-1

(http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx)

2.1.1.9 National Electrical Code, NFPA 70

2.1.1.10 National Fire Protection Association (NFPA) Codes

2.1.1.11 Telecommunication Industry Association/Electrical Industry Association Wiring

Standards (Building Telecommunication Wiring Standards)

2.1.1.12 Army Installation Information Infrastructure Architecture Policy (I3A)

2.1.1.13 JBLM Design Standard specifications (https://www.jblmdesignstandards.army.mil)

2.1.1.14 JBLM Master Plan, which includes Architectural Appearance Standards

2.1.1.15 PWE-707, Standard Operating Procedure for Construction and Demolition (C&D) Waste

Planning and Reporting (available through government Project Manager [PM])

2.1.1.16 National Pollutant Discharge Elimination System (NPDES) small Municipal Separate

Storm Sewer Systems (MS4) Permit No. WAS-026638. Use guidance documents found at https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/stormwater

2.1.1.17 PWE-020 Ozone Depleting Chemical (ODC) and Non-Exempt Substitute Management Plan

2.1.1.18 Washington Administrative Code (WAC) 173-340 Model Toxics Control Act-Cleanup

2.1.1.19 National Electric Safety Code IEEE C2

2.1.1.20 NFPA 101 Life Safety Code

2.1.1.21 SDDCTEA Pamphlet 55-17 Better Military Traffic Engineering

2.1.1.22 2016 Manual of Uniform Traffic Control Devices for Streets and Highways

2.1.1.23 Technical Criteria for the Installation Information Infrastructure Architecture (I3A, 2017).

http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01 http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02 https://www.wbdg.org/ffc/army-coe/policies-and-guidance-army-design-and-construction/army-sdd-policy-update https://www.wbdg.org/ffc/army-coe/policies-and-guidance-army-design-and-construction/army-sdd-policy-update http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx https://www.jblmdesignstandards.army.mil/ https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/stormwater https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/stormwater https://app.leg.wa.gov/wac/default.aspx?cite=173-340

2.1.1.24 JBLM Design Standards, specification section 33 82 00.

2.1.1.25 DOD, MIL-HDBK-419A, Grounding, Bonding, and Shielding for Electronic Equipment and Facilities.

2.1.1.26 DOD, MIL-STD-188-124B, Grounding, Bonding and Shielding for Common Long

Haul/Tactical Communication Systems Including Ground Based Communications- Electronics Facilities and Equipment.

2.1.1.27 BICSI Outside Plant (OSP) Design Reference Manual.

2.1.1.28 BICSI Standards.

2.1.1.29 ANSI/IEEE-C2; National Electric Safety Code (NESC).

2.1.1.30 ANSI/TIA-606; Administration Standard for Telecommunications Infrastructure criteria.

2.1.1.31 ANSI/TIA-607; Generic Telecommunications Bonding and Grounding (Earthing) for

Customer Premises.

2.1.1.32 ANSI/TIA-758; Customer-Owned Outside Plant Telecommunications Infrastructure

Standard.

5.2. Specifications

5.2.1. The Contractor shall comply with all relevant specification sections as set forth in the

Base Contract.

5.2.2. All work shall comply with relevant standards and specifications of the following:

a. Manual on Uniform Traffic Control Devices 2009 (UTCD)

b. WSDOT Standard Specifications for Road, Bridge, and Municipal Construction 2021

M 41-10

c. WSDOT Standard Plans M21-01 September 2020

d. Stormwater Management Manual for Western Washington 2024

e. If standards, specifications, and/or best management practices conflict with contractual requirements or government designs, it is the responsibility of the contractor to submit an RFI to the government PM/COR/KO to determine the appropriate course of action.

3 SUBMITTALS

3.1 Project Submittal Requirements

3.1.1 All submittals shall be submitted in accordance with the specification section titled SUBMITTAL PROCEDURES. Required submittals are identified in their applicable specification sections.

3.1.2 In addition to the requirements as outlined in the specification section titled SUBMITTAL PROCEDURES, an electronic copy of each submittal shall be provided to the Government.

Delivery method shall be decided during the CQC coordination meeting.

3.2 Close-out Submittal Requirements

5.2.1.1 The Contractor shall provide project Final Record drawings meeting the CAD/GIS requirements in the current version (FY21) of JBLM DPW Geospatial Requirements

b. All exterior work under this project shall be geospatially referenced using one of the following methods.

(1) Shown on Final Record drawings with Washington State Plane South coordinates referenced.

(2) Shown on Final Record drawings with reference dimension from existing known reference points within 1000 feet of the project site.

(3) Or provided in georeferenced GIS format (i.e. ESRI File Geodatabase, Shapefiles)

c. Each Final Record drawing set shall have a cover page with the following project information:

• Project Title

• All Project IJO number(s)

• Project Package number = Projects Drawing File number

• Contract number and associated Task Order number.

• Labeled “FINAL RECORD” with project’s completion date (BOD)

• Table of Contents listing all drawing sheets associated with this project.

3.2.1 The Contractor shall provide a Letter of non-retention for all contract documents, plans, drawings, and specifications after the destruction of all copies that are not required to satisfy legal requirements.

4 ENVIRONMENTAL AND CULTURAL RESOURCES

4.1 Asbestos Containing Material

4.1.1 Existing suspect materials involved with all disturbance work are assumed to be Asbestos- Containing Material (ACM). It is the Contractor’s responsibility to either test for, or to assume the suspect material is ACM, and that it is abated /encapsulated in accordance with AHERA, Federal, and Local regulations. No Asbestos Hazard Emergency Response Act (AHERA) inspection is required when the suspect materials are assumed to be ACM. The Government reserves the right to accept assumptions of ACM-positive, or to require such AHERA surveys to be performed.

4.1.2 When performed, inspections shall be accomplished in accordance with the Asbestos Hazard Emergency Response Act (AHERA), Federal and Local regulations. A Certified AHERA Asbestos Building Inspector shall perform all inspections. The inspection documentation shall comply with AHERA, Federal and Local regulations and shall include assessment of each Asbestos-Containing Material (ACM), its location, quantity, type, friability and percentage of asbestos.

4.1.3 If the tested material is positive for asbestos or assumed to be ACM and must be disturbed during project execution, Contractor shall have a certified Asbestos Contractor perform all asbestos disturbance work necessary to complete the project in accordance with 29 CFR 1926.1101, WAC 296-62-077, 296-65, and PSCAA Regulation 3.4. A certified abatement plan and all other applicable requirements of ‘UFGS 02 82 00 Asbestos Remediation’ are also required to be submitted and accepted before work is started. If this effort is believed to constitute differing site condition(s), the Contractor shall submit an RFI identifying the situation.

4.2 Lead-Containing Paint

4.2.1 Existing suspect painted surface materials involved in disturbance work will be considered to contain detectable lead paint. It is the Contractor’s responsibility to either test for, or to assume the suspect material is either Lead Based Paint (LBP) or Lead Containing Paint (LCP), and that it is abated/encapsulated in accordance with OSHA, HUD, Federal and Local regulations. The Government reserves the right to accept assumptions of LCP/LBP-positive, or to require such LCP/LBP surveys to be performed.

4.2.2 When performed, testing shall be accomplished in accordance with OSHA and/or HUD guidelines. A Certified Lead Paint Inspector shall perform lead paint inspections. The inspection documentation shall comply with Federal and Local regulations and shall include identification of all lead paint, its location, quantity, percentage by weight, and TCLP characteristics IAW ASTM E1908-16, “Standard Guide for Sample Selection of Debris Waste from a Building Renovation or Lead Abatement Project for Toxicity Characteristic Leaching Procedure (TCLP) Testing for Leachable Lead (Pb)”

4.2.3 If suspect material tests positive for lead, or assumed to be lead containing, any disturbance of the material shall be in accordance with:

4.2.3.1.1 Federal level: 29 CFR 1926.62:

https://www.govregs.com/regulations/expand/title29_chapterXVII-i3_part1926_subpartD_section1926.62

4.2.3.1.2 Washington WISHA-DOSH: WAC 296-62-07521:

http://app.leg.wa.gov/WAC/default.aspx?cite=296-62-07521

A Contractor work plan is required to be submitted and accepted before work is started, in accordance with applicable sections of ‘UFGS 02 83 00 Lead in Remediation’. If this effort is believed to constitute differing site condition(s), the Contractor shall submit and RFI identifying the situation.

4.3 Environmental Coordination

If illicit discharges from construction sites impact outfall water quality, the primary contractor for the construction site will be responsible for all fines and violations associated with illicit discharge. The primary contractor will also be responsible for all maintenance, cleanup, or reporting associated with illicit discharge. The primary contractor must also self-report al illicit discharges to the EPA. The primary contractor also needs to include the stormwater program manager in the self-reporting process and CC’ed in all communication with the EPA regarding the illicit discharge. Failure to do so may cause DPW to issue a stop work order until the project is back in compliance with MS4 and other permits.

Additional training for stormwater compliance may be required depending on the severity of the illicit discharge.

4.3.1 The Contractor shall comply with all Joint Base Lewis-McChord (JBLM) environmental requirements, including the most current installation regulation 200-1 (Environmental Protection and Enhancement) and Design Standards specification section 01 57 19 Temporary Environmental Controls and 01 57 19.01 20 Supplemental Temporary Environmental Controls. This includes the submission of an Environmental Protection Plan (EPP) prior to commencement, as detailed in section 01 57 19. The JBLM Environmental Division will review the submittals EPP and provide comments to the Contracting Officer or their representative. Regulation 200-1 and specification sections 01 57 19 and 01 57

19.01 20 are available at the JBLM Design Standards website https://www.jblmdesignstandards.army.mil.) The Stormwater office can be contacted at:

usarmy.jblm.id-readiness.list.dpw-stormwater@army.mil

4.3.2 The EPP shall include, but not be limited to, a site map identifying ground disturbing activities, drainage paths to existing stormwater conveyance infrastructure, proposed source control Best Management Practices (BMPs), and all other proposed temporary and permanent stormwater BMPs. For projects disturbing 5,000 sq. ft. or more, the Contractor shall submit a Stormwater Pollution Prevention Plan (SWPPP) in addition to the EPP. The SWPPP shall be prepared in accordance with PWE-633 Construction Site Stormwater Runoff Control Program and the 2024 SWMMWW and shall detail sediment and erosion control best management practices (BMPs). See section 8.9.4. for required permits.

4.3.3 In accordance with JBLM Reg. 200-3, no construction process water or wastewater shall be discharged to the ground or stormwater conveyance system. Construction discharge must meet requirements of the NPDES Construction General Permit (CGP) for Discharges from Construction Activities and guidance documents under the MS4 Permit. In accordance with JBLM Reg. 200-2, any wastewater generated must be collected, processed, characterized, and disposed of into the JBLM sanitary sewer system or other authorized disposal method.

Prior to disposal, wastewater characterization must at a minimum include pH, Oil and Grease, BOD, and TSS analysis by a NELAC accredited laboratory. Additional analyses https://www.govregs.com/regulations/expand/title29_chapterXVII-i3_part1926_subpartD_section1926.62 https://www.govregs.com/regulations/expand/title29_chapterXVII-i3_part1926_subpartD_section1926.62 http://app.leg.wa.gov/WAC/default.aspx?cite=296-62-07521 https://www.jblmdesignstandards.army.mil/ mailto:usarmy.jblm.id-readiness.list.dpw-stormwater@army.mil may be required if non-conventional wastes or hazardous materials are potential contaminants. Results shall be submitted for review and approval by Public Works. On site characterization by JBLM Pretreatment staff may waive analytical requirements at the discretion of the Pretreatment program manager. JBLM sanitary sewer discharge requires a Sanitary Sewer Discharge Permit issued by DPW Wastewater Treatment Plant. The Environmental Protection Plan for the project must identify any potential wastewater generation and the process of proper disposal.

4.3.4 Temporary BMPs are required for all areas that have exposed soil as required by 2024 SWMMWW. Between October 1 and April 30, contractors will have 2 days to establish temporary BMP coverage for all exposed soil areas, and between May 1 and September 30, contractors will have 7 days to establish temporary BMP coverage. Temporary BMPs are important to keep the site from having turbid water from leaving the site, erosion issues with stabilizing areas, and prevent rework of areas that are affected.

4.3.5 Land disturbing activity - Any activity that results in a change in the existing soil cover (both vegetative and nonvegetative) and/or the existing soil topography. Land disturbing activities include, but are not limited to clearing, grading, filling, and excavation.

Compaction that is associated with the stabilization of structures and road construction shall also be considered a land-disturbing activity. Vegetation maintenance practices, including landscape maintenance and gardening, are not considered land-disturbing activities.

Stormwater facility maintenance is not considered land-disturbing activity if conducted according to established standards and procedures.

4.4 Sustainable Acquisition In order to comply with federally mandated sustainable acquisition requirements and Department of Defense (DOD) and Department of the Army (DA) Green Procurement Program (GPP) policies, Joint Base Lewis-McChord (JBLM) requires the purchase, supply, and use of environmentally preferable products and services. Program elements include recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, non-ozone depleting substances, and environmentally preferable products. For a listing of designated items, associated requirements and managing program websites, see https://sftool.gov/greenprocurement.

4.4.1 Additionally, the JBLM Guide to Sustainable Acquisition for Construction is available in section 01 57 20.00 10 of the JBLM Design Standards webpage (https://www.jblmdesignstandards.army.mil/01-57-2000-10/).

4.4.2 The Contractor shall comply with all applicable Federal, DOD, Army, and JBLM sustainable acquisition laws and policies. If compliant products are unavailable or determined to be impracticable based on cost or performance, the Contractor shall contact the Contracting Officer or their representative for further guidance. Claims of exception must meet applicable legal criteria and be justified in writing through the submission of a completed HJB Form 225 (Sustainable Acquisition Exception). The form is available at https://www.jblmdesignstandards.army.mil/01-57-19/. Additional information is available from the JBLM Sustainable Acquisition Program at (253) 966-6449 or usarmy.jblm.id-readiness.list.dpw-green-procurement@army.mil

4.5 Environmental Management System

4.5.1 Environmental Management System (EMS). The JBLM EMS conforms to the criteria defined in the international standard, ISO 14001:2004 Environmental management systems

– Requirements with guidance for use.

4.5.2 In accordance with EMS procedures, the Contractor shall be familiar with the JBLM https://sftool.gov/ https://www.jblmdesignstandards.army.mil/01-57-2000-10/ https://www.jblmdesignstandards.army.mil/01-57-19/ mailto:usarmy.jblm.id-readiness.list.dpw-green-procurement@army.mil mailto:usarmy.jblm.id-readiness.list.dpw-green-procurement@army.mil environmental policy and shall ensure that this information is considered and incorporated into this project. Additional information regarding the JBLM EMS is available from the installation EMS Coordinator (253-966-4865).

4.5.3 Both the JBLM environmental policy and an environmental awareness training resource are available at the JBLM EMS webpage: https://home.army.mil/lewis-mcchord/my-Joint- Base-Lewis-Mcchord/all-services/public_works-environmental_division/environmental-services#qt0:4

4.6 Hazardous Materials

4.6.1 For any hazardous materials, the Contractor shall submit an initial list of hazardous materials to be used (including unit of measure and Safety Data Sheet for each product). A copy of these documents must be submitted to the Joint Base Lewis-McChord (JBLM) Pollution Prevention Program (usarmy.jblm.id-readiness.list.dpw-aul1@army.mil) prior to commencement. These items must be reviewed by Pollution Prevention and authorized for use by addition to the Contractor’s Authorized Use List (AUL) issued by Pollution Prevention. The Contractor shall not use any hazardous materials not listed on their current AUL issued by Pollution Prevention.

4.6.2 For any in-use hazardous materials, the Contractor shall submit a hazardous material inventory on HJB Form 953 noting the hazardous materials used, the units of measure, quantities used, storage locations, and other information indicated on the form. This inventory shall be submitted at the end of the project. If the project goes into a new calendar year, the Contractor shall also submit a copy of this inventory (accounting for all hazardous materials) by 15 January. For any hazardous materials stored on JBLM, this inventory shall be submitted by the 15th day following the calendar year quarter in which the hazardous materials were used or stored. All HJB 953 inventories shall be submitted electronically and addressed email to the Contracting Officer or their representative, with usarmy.jblm.id-readiness.list.dpw-hm-inventory@army.mil included in the carbon copy (“cc”) line of the email. Questions regarding the form may be directed to the JBLM Pollution Prevention Program (966-6469). The current HJB Form 953, and form instructions are available at Section 01 57 19 of the JBLM Design Standards https://www.jblmdesignstandards.army.mil/01-57-19/.

4.7 Archaeological Requirements

4.7.1 Joint Base Lewis-McChord contains many unmarked archaeological sites that may be eligible for listing in the National Register of Historic Places.

4.7.2 If human remains, artifacts, or features of archaeological interest are inadvertently discovered, the Contractor shall do the following:

4.7.3 Immediately cease activity in the vicinity of the discovery.

4.7.4 Stabilize and protect such discoveries from further disturbance or public disclosure.

4.7.5 Provide immediate notice (no longer than 24 hours following discovery) by telephone and email to the Installation Cultural Resource Manager and Contracting Officer's Representative.

4.7.6 Work may not proceed in the vicinity of the discovery until authorized to proceed by the

Installation Cultural Resource Manager and the Contracting Officer's Representative

(COR).

4.7.7 Any post-award changes that have the potential to impact historic buildings, structures, https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fhome.army.mil%2Flewis-mcchord%2Fmy-Joint-Base-Lewis-Mcchord%2Fall-services%2Fpublic_works-environmental_division%2Fenvironmental-services%23qt0%3A4&data=05%7C01%7Cmichael.s.fowler12.ctr%40army.mil%7Cf20e0b56252047b5244708dbab06abdf%7Cfae6d70f954b481192b60530d6f84c43%7C0%7C0%7C638291817373484789%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=KmCKRNF%2BnDxgoY6JR58vCdI0WalUSv7jO8tsnirbxvg%3D&reserved=0 https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fhome.army.mil%2Flewis-mcchord%2Fmy-Joint-Base-Lewis-Mcchord%2Fall-services%2Fpublic_works-environmental_division%2Fenvironmental-services%23qt0%3A4&data=05%7C01%7Cmichael.s.fowler12.ctr%40army.mil%7Cf20e0b56252047b5244708dbab06abdf%7Cfae6d70f954b481192b60530d6f84c43%7C0%7C0%7C638291817373484789%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=KmCKRNF%2BnDxgoY6JR58vCdI0WalUSv7jO8tsnirbxvg%3D&reserved=0 https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fhome.army.mil%2Flewis-mcchord%2Fmy-Joint-Base-Lewis-Mcchord%2Fall-services%2Fpublic_works-environmental_division%2Fenvironmental-services%23qt0%3A4&data=05%7C01%7Cmichael.s.fowler12.ctr%40army.mil%7Cf20e0b56252047b5244708dbab06abdf%7Cfae6d70f954b481192b60530d6f84c43%7C0%7C0%7C638291817373484789%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=KmCKRNF%2BnDxgoY6JR58vCdI0WalUSv7jO8tsnirbxvg%3D&reserved=0 mailto:usarmy.jblm.id-readiness.list.dpw-aul1@army.mil mailto:usarmy.jblm.id-readiness.list.dpw-hm-inventory@army.mil mailto:usarmy.jblm.id-readiness.list.dpw-hm-inventory@army.mil https://www.jblmdesignstandards.army.mil/01-57-19/ objects, and districts shall be reviewed and approved by the COR in consultation with the JBLM Cultural Resources Program prior to execution.

4.7.8 When work under this contract affects an historic property, in order to comply with AR200-

1 and Section 106 of the National Historic Preservation Act of 1966, all work shall comply with: "The Secretary of the Interior's Standards for the Treatment of Historic Properties with Guidelines for Preserving, Rehabilitating, Restoring and Reconstructing Historic Buildings" (available at https://www.nps.gov/tps/standards.htm).

the "Maintenance and Repair Manual for Historic Structures”.

the "Landscape Development Plan - Volume II"; and the "Installation Design Guide" (documents available at http://www.lewis.army.mil/publicworks/ - click on "Design Standards," "Go to Design Standards," and "Reference Manuals").

4.8 Construction and Demolition (C&D) Waste Planning and Reporting

4.8.1 The DOD Integrated (Non-Hazardous) Solid Waste Management Policy requires all facilities to meet a non-hazardous solid waste diversion goal of 64% in 2022 and 66% in 2023 Construction and Demolition Diversion. Create a waste management plan in accordance with section 01 74 19 of the JBLM Design Standards to meet or exceed the C&D waste diversion target.

4.8.2 Complete and submit quarterly C&D Diversion and Disposal Reporting Form (HJB Form

229) in accordance with form instructions and paragraph "Reports" in Section 01 74 19 of the JBLM Design Standards. The form and instructions can be accessed via the links at Division 01 Section 01 57 19 of the JBLM Design Standards website (http://www.lewis-mcchord.army.mil/designstandards/index1.htm). Section 01 74 19 can also be accessed via the Design Standards website.

4.8.3 Stockpiling on site for new material and broken concrete shall include the following best management practices (BMPs) in EPP’s sediment and control section.

- BMP 123 Plastic Covering (Pages 340-341 of 2024 SWMMWW)

- BMP 151 Concrete Handling (Pages 359-360 of 2024 SWMMWW)

The following are other common BMPs that shall often be used in the course of execution of task orders under this umbrella contract :

BMP C103: High-Visibility Fence BMP C120: Temporary and Permanent Seeding – anticipate watering until 75% grass coverage is established for permanent BMP C122: Nets and Blankets (prefer 100% biodegradable when feasible) BMP C235 Wattles BMP C232 – Gravel Filter Berm

Additional BMPs for contractor consideration:

BMP C101: Persevering Natural Vegetation BMP C102: Buffer Zones BMP C150 – Materials on Hand (e.g., Sandbags, Straw, Straw Bales, Rocks/Rock Bags) BMP C240 – Sediment Trap BMP C123: Plastic Covering

4.9 Excess Soils and Clearing and Grubbing Debris

4.9.1 Excess soils and waste asphalt is expected for this project. In Situ soil testing for contaminates is required.

In-Situ testing is the preferred methodology for soils testing. In Situ soil bore frequencies https://www.nps.gov/tps/standards.htm http://www.lewis.army.mil/publicworks/ will be based on the following guidelines. The in-situ sample frequency for this project is:

Site/Construction Description Bore Frequency

Sample s per Bore 0- 2 feet3

Composit e Sample Depths from Existing Ground Surface

Road Work with a footprint greater than 40-foot diameter circle. One bore on the west side of the road along the edge of existing pavement (with or without stormwater treatment facilities).

1 per 100 feet 2

Samples at 0- 0.5 feet and 0.5-1.5 feet

Linear installation other than a road such as a sidewalk, fence, or electrical trench that does not fit in a 40-foot diameter circle

1 per 50 feet along the alignment of proposed improveme nt 1

Sample at 0-1.5 feet

Notes:

1) Bores/samples are only required when soil will be removed from the site. Bores/samples are only required for the areas associated with the soils to be removed from the site.

2) Soils that exceed the Model Toxic Control Act limits, can be kept onsite directly adjacent to the excavation (aside) if covered with 6-inches of topsoil and…