This document is a Statement of Work (SOW) for Cargo Fuel Tank repair on an R-11 Refueler Model 7400 SBA 6X4 with serial number AF10L00047. The services will be performed at the contractor's facility, with the government coordinating delivery and pickup of the vehicle. Specific repair requirements include removing the tank lid, die grinding and welding two 8" cracks, cutting and repairing two supporting baffle wall sections with dent removal, and conducting a pressure test to tank specifications of 5.5 PSIG in accordance with DOT 406 standards. The contractor must complete all repairs and pressure testing within 90 days after contract award, with an estimated performance period from September 30, 2025 to December 29, 2025. The current inventory of the vehicle is 0 gallons, and the repairs involve detailed technical work including welding, buffing, and reinstallation of tank components.

View the file

Other files

File Type Posted
Wage Determination 2015-5689 rev 26.pdf PDF
Solicitation - W50SLF25QA012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

STATEMENT OF WORK

1.1 GENERAL:

Provide Cargo Fuel Tank repair and pressure test for R-11 Refueler Model 7400 SBA 6X4 serial number AF10L00047. Current Inventory 0 Gallons. Services shall be performed at the contractor’s facility and the Government POC will coordinate delivery and pick up of R-11 Refueler upon contract award.

1.2 DESCRIPTION OF SERVICES:

The contractor shall provide all supervision, personnel, equipment, transportation, materials and other items and services necessary to perform the following:

- Remove tank lid;

- Die grind x2 8" cracks and buff with pad prep for weld;

- Weld x2 12" welds to cover cracks;

- Clean up weld debris;

- Remove lid;

- Cut out x2 supporting baffle wall sections to push out dent about 2'x2' each section;

- Prep and buff to reinstall after dent pressed out;

- Push out dent to tank specs; 5.5 PSIG IAW DOT 406

- Weld in 2 baffle wall sections;

- Pressure test to tank specs; 5.5 PSIG IAW DOT 406

- Clean up weld debris; and

- Reinstall lid.

1.3 PERIOD OF PERFORMANCE

The contractor shall complete all repairs and one pressure test no more than 90 days after award, estimated September 30, 2025 to December 29, 2025.