Statement of Requirements (SOR) Draft - FY26 Project X Fans.docx
DOCX document 45 KB Posted
- Attached to
- FY 26 SOS Operational Fan System
- Solicitation number
- FY26SOSOPFANS
About this file
This is a Statement of Requirements (SOR) for the procurement and installation of an industrial fan system at Squadron Officer School (SOS), Maxwell Air Force Base, Alabama. The project, designated Project X Fans (Building 1446), aims to mitigate heat-related injury risks by installing a centrally controlled airflow system in a 19-bay covered outdoor facility used for Field Leadership training events. The system must include 19 industrial-grade fans with 22-inch propeller diameters, 3/4 HP motors (1-phase, 115/230V, 60 Hz), galvanized aluminum propellers with polypropylene inlet/outlet housings, and spiral-wound steel finger guards. The contractor must provide OEM-compatible column/wall mounting kits for all 19 fans and a single centralized control system with an outdoor-rated enclosure featuring start, stop, emergency stop, and reset pushbuttons for simultaneous fan operation. All equipment must be brand new; refurbished or remanufactured items are not authorized.
The contractor is responsible for full delivery, installation, and commissioning of the system at Building 1446, Lemay Plaza, Maxwell AFB, AL 36112. Installation responsibilities include conducting a site survey, securing all 19 fans to the building structure, completing all electrical work in accordance with the National Electric Code by a licensed electrician, and conducting functional testing with government representatives present. The contractor must provide operator training on the centralized control system and deliver all manufacturer warranty documentation and support procedures prior to project acceptance. Standard OEM commercial warranties apply at no additional cost to the government, with the warranty period beginning upon final project acceptance. Additional contract requirements address contractor access to Air Force installations, security protocols, identification and vehicle pass procedures, traffic regulations, and health and safety standards. The government point of contact is SOS/OD, with Stephen Wade (334-953-5894) or Tamar Selmi (334-953-1522) listed as contacts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought - Project X Fans.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Requirements
PROJECT X FANS B1446
1.0 PURPOSE: The purpose of this project is to enhance student safety and maintain training effectiveness by mitigating the significant risk of heat-related injuries. This will be achieved by installing a centrally controlled airflow system in a 19-bay covered outdoor facility used for physically demanding challenges during extreme summer heat. Building 1446 is a covered, outdoor facility with 19 distinct training bays used for Field Leadership events at Squadron Officer School (SOS). The facility is not climate-controlled, and during summer months, ambient temperatures can pose a significant risk of heat-related injuries to students. The purpose of this project is to procure and install a complete, turnkey industrial fan system to mitigate this risk. This system will enhance student safety, protect the health and welfare of personnel, and ensure an effective training environment by generating consistent airflow throughout the 19 training bays.
2.0 DESCRIPTION OF ITEMS: The contractor shall provide all equipment, materials, and components necessary to create a complete and operational fan system as specified below.
2.1 Requirements:
· Fans (Quantity 19): Salient characteristics must be equivalent to or exceed the following:
· Propeller Diameter: 22 inches
· Motor: ½ HP, 1Ph/115/230V/60 Hz
· Construction: Galvanized aluminum propeller with high-impact polypropylene fan inlet/outlet and spiral wound steel finger guards.
· Rating: Industrial grade, suitable for a covered outdoor environment.
· Mounting (Quantity 19):
· OEM-provided column/wall mount kits fully compatible with the fan system.
· Controls (Quantity 1):
· A single, centralized control system with an outdoor rated enclosure.
· System must feature simultaneous fan operation via start, stop, emergency stop, and reset pushbuttons.
All equipment must be brand new; refurbished or remanufactured items are not authorized.
3.0 DELIVERY REQUIREMENTS:
3.1 Transportation of all products, loading, unloading, storage, and all necessary movement from factory to final on site set up. The delivery and install of the equipment will be to Bldg 1446 Lemay Plaza, Maxwell AFB, AL 36112. POC: SOS/OD - Stephen Wade (334-953-5894) or Tamar Selmi (334-953-1522).
3.2 Delivery Address: Bldg 1446 Lemay Plaza, Maxwell AFB, AL 36112.
4.0 INSTALLATION REQUIREMENTS: The contractor shall provide all supervision, labor, and equipment to install a fully functional system.
· The contractor is responsible for conducting a site survey to verify all measurements, structural mounting points, and electrical power sources.
· Install one fan in each of the 19 training bays, secured to the building’s structure.
· All electrical work, including conduit runs and connections to the fans and control panel, shall be performed by a licensed electrician in accordance with the National Electric Code (NEC).
· The centralized control system shall be installed in a location approved by the government Point of Contact (POC).
· Upon completion, the contractor shall conduct a functional test with a government representative present to demonstrate that all 19 fans operate correctly from the centralized panel.
· The contractor shall remove all tools, equipment, and installation debris from the worksite, leaving the area clean.
5.0 TRAINING REQUIREMENTS: Prior to final acceptance, the contractor shall provide a brief orientation to the government POC on the operation of the centralized control system. All user manuals for the fans and control system shall be provided at this time.
6.0 STANDARD WARRANTY: The contractor shall provide any Original Equipment Manufacturer (OEM) standard commercial warranty applicable to the products being purchased at no additional cost to the Government. Items must be brand new. Refurbished items are not authorized.
6.1 Prior to project acceptance, the contractor shall provide the customer with all manufacturer warranty documents for the fans and the control system. The warranty period shall begin upon final acceptance of the project by the government.
6.2 Prior to project acceptance, the contractor shall provide written procedures, points of contact within company, and required information for all warranty services prior to project acceptance. This information shall include written confirmation of the warranty period, phone numbers and contact information/procedures for support, troubleshooting assistance, and replacement of faulty furniture.
7.0 GENERAL INFORMATION: Items must be brand new. Refurbished items are not authorized.
8.0 SECURITY REQUIREMENTS FOR UNCLASSIFIED SERVICES ONLY
No CAC REQUIRED
Contractor Notification Responsibilities: The contractor shall notify the contracting officer within 30 days before on-base performance of the service. The notification shall include:
a. Name, address, and telephone number of contractor employees working on the contract.
b. The contract number and contracting agency.
c. The location(s) of service performance and future performance, if known.
d. The date service performance begins.
e. Any change to information previously provided under this paragraph.
Installation Access Requirements: As prescribed by the DAFFARS 5352.242-9000, Contractor access to Air Force installations, AFI 31-218, Motor Vehicle Traffic Supervision, and DoDM5200.08v3_AFMAN31-101v3, Installation Perimeter Access Control.
The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished contractor identification badges while visiting or performing work on the installation.
The contractor shall submit a written request on company letterhead to the Contracting Officer (CO) listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign a request for base identification credentials or vehicle passes.
The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, and valid vehicle insurance certificate to obtain a vehicle pass.
During performance of the service, the contractor shall be responsible for obtaining the required identification for newly assigned personnel and for prompt return of credentials for any employee who no longer requires access to the work site.
Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
Failure to comply with these requirements may result in the withholding of final payment.
Vehicle Inspections. All commercial vehicles will be directed to Gate 3 (Kelly St) or Gate 4 (Congressman Dickenson for Gunter) for processing through the Commercial Vehicle Inspection (CVI) Area, when operational. During non-duty hours and holidays, commercial vehicle inspections will be conducted at Gate 1 (Maxwell Blvd) or Gate 4 (Congressman Dickinson Drive) only. Inspection members will conduct thorough inspections of the interior and exterior of the vehicle for items prohibited from the installation such as explosive devices, weapons and ammunition, drugs, and open or closed alcohol containers.
REAL ID Act: All Maxwell Air Force Base and Gunter Annex visitors must present a REAL ID-compliant credential to be issued a pass.
REAL ID-compliant cards have a star marking ⭐️on the upper portion of the card. If the card does not have a star marking, it is not REAL ID-compliant and won’t be accepted as proof of identity to board commercial aircraft or access military installations like Maxwell or Gunter.
Those without a REAL ID-compliant driver’s license may also use a U.S. passport or passport card, a Transportation Worker Identification Card (TWIC), a Veteran Health Identification Card (VHIC), or a combination of the following documents to be issued a pass:
· An original or certified true copy of a birth certificate with a raised seal
· A social security card
· A driver’s license issued by a state, territory, or the District of Columbia that is not REAL ID-compliant.
All three documents must reflect the same name (or a documented former name through legal name change documents such as a court order, marriage certificate, or divorce decree).
More information about accessing Maxwell can be found here: https://www.maxwell.af.mil/About-Us/Fact-Sheets/Display/Article/4024201/base- access-information/.
Controlled/Restricted Areas: If work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with DAFI 31-101, Integrated Defense, and DoDM5200.02_DAFMAN 16-1405, Air Force Personnel Security Program.
If unescorted access is not authorized and the contractor requires access to controlled/restricted areas, they must be escorted by appropriately cleared government personnel at all times.
If work is required in a classified environment, the area must be sanitized, and the contractor will be escorted at all times by appropriately cleared government personnel.
Reporting Requirements: The contractor shall comply with DAFI 71-101, Volume-1, Criminal Investigations, and AFI 71-101, Volume-2, Protective Service Matters, requirements. Contractor personnel shall report to 42d Air Base Wing Information Protection Office, any information or circumstances of which they are aware may pose a threat to the security of DoD personnel, contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.
Traffic Laws: The contractor and their employees shall comply with base traffic regulations set forth in AFI 31-218, Motor Vehicle Traffic Supervision and DoDM5200.08v3_AFMAN31-101v3, Installation Perimeter Access Control. Personnel in violation may be issued a Central Violations Bureau Form 1805 traffic ticket.
Random Installation Entry/Exit Checks: Entry/exit vehicle checks are conducted by order of the 42 ABW Commander. These checks are conducted for the purpose of safeguarding the base and protecting government property by discovering and seizing stolen property, classified information, and contraband. Refusal to submit to an installation (entry/exit) vehicle check may result in the loss of base driving privileges, revocation of base registration, or debarment action.
Cellular Phone Operation Policy: The use of cellular phones while operating a motorized vehicle is prohibited on Maxwell-Gunter. Although discouraged, drivers are authorized to use devices, i.e. ear bud or ear boom, which allows their cellular phone to be operated hands-free. The device must not cover both ears. This policy applies to everyone driving on Maxwell AFB and Gunter Annex. Personnel in violation may be issued a Central Violations Bureau Form 1805 traffic ticket.
Wireless Electronic Devices: The contractor will not establish their own Information Technology (IT) systems or networks (Local Area Networks [LAN], Wide Area Network [WAN], Cellular phone/USB Modem as WAN, Wi-Fi as WAN, etc.), or camera system without the direct permission of the Program Manager and governing communications and responsible information systems office (42 CS).
Firearms and Ammunition: Transporting weapons or ammunition, concealed or otherwise, IS NOT permitted by any non-law enforcement personnel on Maxwell AFB/Gunter Annex at any time regardless of state issued concealed weapons/LEOSA permits. Violations may result in criminal prosecution under applicable federal laws.
Illegal Weapons. The weapons below are considered illegal, unless specifically authorized by competent authority and are prohibited on Maxwell AFB/Gunter Annex. Violations may result in criminal prosecution under applicable federal laws.
f. Switchblade knives or knives with any type of automatic blade release.
g. An incendiary/explosive weapon (e.g., grenades, flash bangs).
h. Fireworks
i. Homemade mortars, aka "tennis ball launchers" or similar devices.
9. ADDITIONAL CONTRACT TERMS AND CONDITIONS:
CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS
(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver's license, current vehicle registration, valid vehicle insurance certificate, and all appliable base regulations to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with all appliable base regulations citing the appropriate paragraphs as applicable.
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) The contractor shall provide an after-hours contact number or after-hours email in the Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in DAFMAN 10-206 for emergency operational reporting. Foreign Nationals may participate and may remove themselves from the Emergency Mass Notification System at any time. To update information, personnel can access the globe icon on their system desktop screens and choose the "Access Self-Service" option.
(g) Failure to comply with these requirements may result in withholding of final payment.
(END OF CLAUSE)
OMBUDSMAN
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, the interested party may contact the ombudsman, Primary: Lt Col Barbara Divine, Director of Staff, AFICC/KT, Telephone Numbers: (210) 652-7822 (DSN: 487-7822); or Alternate: Mr. Todd S. Joyner, Chief, Clearance & Program Support Division, Telephone Number: (210) 652-7075 (DSN: 487-7075). Address: 2035 First Street West, JBSA Randolph TX 78150-4304. E-mail Addresses: barbara.divine@us.af.mil and todd.joyner@us.af.mil. Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU/SMC ombudsman level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-2395, facsimile number (571)256-2431.
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the contracting officer.
(END OF CLAUSE)
HEALTH AND SAFETY ON GOVERNMENT INSTALLATIONS
(a) In performing work under this contract on a Government installation, the contractor shall:
(1) Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(2) Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes.
(b) The contracting officer may, by written order, direct Air Force Occupational Safety and Health (AFOSH) Standards and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.
(c) Any violation of these health and safety rules and requirements, unless promptly corrected as directed by the contracting officer, shall be grounds for termination of this contract in accordance with the Default clause of this contract.
(END OF CLAUSE)