This is a Statement of Objectives (SOO) for a federal contract opportunity issued by the Arnold Engineering Development Complex (AEDC) at Arnold Air Force Base in Tennessee. The SOO number is 16873-26-001, dated August 5, 2026, with identification IRA-26-1407.

The primary objective is to provide an independent air supply system to a test cell at Arnold AFB through installation of compressors, dryers, heaters, and expansion turbines that will deliver a secondary, dedicated conditioned air supply. The project encompasses all required utilities, power, equipment, and controls to support the new process air equipment. The contractor must develop a complete Statement of Work satisfying performance requirements outlined in Attachment 1 – Performance Parameters. Minimum required milestones include Project Kickoff Meeting, Contractor Readiness Review, Preliminary Design Review, Power Study Approval, Equipment Specification Approval, Intermediate Design Review, Critical Design Review, Final Design Review, Completion of Fabrication and Installation, Verification Readiness Review, System Readiness Review, and On-Site System Orientation/Training. Data deliverables include comprehensive technical documentation such as operational drawings, fabrication and installation drawings, analysis reports, equipment specifications, hazard tracking logs, risk assessments, permits, demolition and manufacturing plans, failure modes and effects analysis, system test plans, testing results, training materials, and user manuals. The Government shall receive Unlimited Data Rights to all contractor-provided technical data, analysis, drawings, software, and code. The contractor must develop and maintain a Quality Control Plan and provide monthly status reports with cost, schedule, and technical issue updates to maintain clear government visibility throughout contract performance.

View the file

Other files

File Type Posted
RWP_Independent Air Supply.pdf PDF
SOO_Appendix C_AEDC Standards.pdf PDF
SOO_Appendix B_Design Review Expectations.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STINFO

SOO # 16873-26-001

5 Aug 2026

Statement of Objectives (SOO) AEDC-Arnold AFB: Independent Air Supply

Distribution A: Approved for public release: distribution unlimited.

IRA-26-1407

1. Program Objectives The objective of this effort is to provide an independent air supply to a test cell at Arnold AFB, TN. This will be achieved through the installation of compressors, dryers, heaters, and expansion turbines that will provide a secondary, dedicated conditioned air supply to the existing test cell. The project also includes all utilities, power, equipment, and controls required to support the new process air equipment. The minimum success criteria for the system is described in Attachment 1 – Performance Parameters.

2. Contract Objectives At a minimum, the contract shall define the following:

2.1. Work to-be Performed:

Provide specific, performance-based, quantitative terms of the work to-be-done, in the form of a complete Statement of Work (SOW), to satisfy the performance requirements established in Attachment 1 – Performance Parameters. The SOW shall clearly identify and describe, in detail, all design, procurement, fabrication, installation, inspection, testing, and checkout activities required to provide a fully functional independent air supply system.

2.2. Milestones:

Planned, significant events shall be identified in the SOW, including a schedule identifying when each will occur. Milestones shall include, at a minimum:

Project Kickoff Meeting Contractor Readiness Review * Preliminary Design Review * Power Study Approval Equipment Specification Approval Intermediate Design Review * Critical Design Review * Final Design Review * Completion of Fabrication and Installation Verification Readiness Review * System Readiness Review * On-Site System Orientation / Training

* See Appendix B in Attachment 1 – Performance Parameters for specific expectations regarding these design reviews.

2.3. Data Deliverables.

Tangible or intangible data items produced as a result of the work performed shall be identified in the SOW, as well as their anticipated delivery date, method of delivery, format, and quantity.

Data Deliverables for this effort shall include, at a minimum, all documentation identified in Appendix B in Attachment 1 – Performance Parameters, including the following:

Statement of Work Power Study Report Site Plan Operational Drawings (P&IDs, Schematics, Line Diagrams, or Wiring Diagrams) Fabrication and Installation Drawings Analysis Reports Equipment Specification for Major Equipment Hazard Tracking Log Project Risk Assessment Permits Demolition Plan Manufacturing Plan Installation Plan Concept of Operations Failure Modes and Effects Analysis (FMEA) Verification, Validation, and Acceptance Plan System Test Plan Non-Destructive Examination Results Pressure Test Results Performance Testing Results Training Materials and Documentation Programming Documentation and Source Code User Manuals or Vendor-Supplied Maintenance Documentation

2.4. Data Rights:

The Government shall receive Unlimited Data Rights to all Contractor-provided technical data, analysis, drawings, software, code, and programming produced in performance of this effort.

2.5. Training:

The Government shall receive on-site orientation and training for all new equipment or systems. Training will be recorded by the Government for future use.

3. Quality Control Plan (QCP):

The contract shall define the development and maintenance of a quality control plan to ensure the requirements established within this Statement of Objectives, including all attachments, are met in accordance with the SOW. This shall include the development and implementation of procedures to meet milestones and to ensure appropriate corrective action is taken when milestones are not met.

4. Program Management Objective:

Allow offerors the maximum flexibility to innovatively manage schedule, performance, risks, warranties, subcontracts, and data so that it satisfies the user’s performance requirements (see Attachment 1 – Performance Parameters).

Clear government visibility into the schedule, performance, and risks shall be maintained. The Contractor shall maintain clear and continuous communication with the Government, including monthly Status Reports that include, at a minimum, updated cost and schedule information as well as any current technical issues.

Attachments and Appendices:

1. Attachment 1 – Performance Parameters (Distribution D)

a. Appendix A – Reference Drawings (Distribution D)

b. Appendix B – Design Review Expectations (Distribution A)

c. Appendix C – AEDC Standards (Not Sensitive)

d. Appendix D – Road Load Limits (Distribution D)