Text version
Statement of Objectives
Incirlik AB, Turkey
TSW – CDSINCIRLI DODAAC – FP8161
STATEMENT OF OBJECTIVES, 9 Dec 19
Scope: The Defense Logistics Agency (DLA) Aerospace Energy Business Unit, as the Department of Defense (DoD) Integrated Materiel Manager (IMM) for Aerospace Energy products and related services, requires delivery of Aviator’s Breathing Oxygen to Incirlik AB, Turkey into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to Incirlik AB.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
Tank Hot Fill: Occasionally, the Contractor may be required to perform a “Hot Fill” in order to cool-down and refill any tank that has gone empty and is warm.
Security Requirements: Contractor personnel shall provide a valid passport, driver’s license, insurance, vehicle paperwork, and shall be escorted at all times at each destination. All delivery vehicles are subject to search by security personnel prior to accessing delivery location and while on each facility.
Rota Naval Station, Spain
TSW – CDSROTANAV DODAAC – FP8170
STATEMENT OF OBJECTIVES, 24 Feb 20 products and related services, requires delivery of Aviator’s Breathing Oxygen and Liquid Nitrogen to Naval Station Rota, Spain into Government-owned and Contractor-provided tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to Naval Station Rota.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
Liquid Nitrogen (LN2), Type II, Grade B, NSN 6830-01-644-2557, shall meet the requirements of the most current version of Commercial Item Description A-A-59503.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Expedited/Emergency Delivery:
Emergency deliveries shall be within three (3) calendar days of request unless otherwise determined with the DLA Contracting Officer. After emergency delivery order is placed, Contractor shall coordinate delivery time and acceptance of emergency deliveries with customer.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during
Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
Contractor-Provided Tank Installation:
Contractor shall install their Contractor provided tanks and equipment on existing cement pads, within the existing system footprints, no later than 30 calendar days from start of contract performance. The Contractor shall also perform all inspections and maintenance of Contractor provided tanks/equipment to assure systems provide safe and uninterrupted support. Contractor provided tanks may be chilled through initial deliveries, but initial deliveries into Contractor provided tanks shall not qualify as a “Hot Fill” service. The Contractor will coordinate with the current supplier to effect removal of current equipment and installation of new equipment, or to retain the current equipment.
The Contractor may be required to provide a temporary system during change out of existing system or tanks to eliminate any delay in supply of product.
Contractor-Provided Equipment Removal:
Contractor provided tanks/equipment shall be removed by the Contractor within 30 calendar days after contract termination. The Contractor will coordinate with the follow-on supplier to effect removal of current equipment and installation of new equipment.
Ramstein AB, Germany
TSW – CDSRAMSTEN DODAAC – FP8039
STATEMENT OF OBJECTIVES, 8 Jan 20 products and related services, requires delivery of Aviator’s Breathing Oxygen and Liquid Nitrogen to Ramstein AB, Germany into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b.
destination to Ramstein AB.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
Liquid Nitrogen (LN2), Type II, Grade B, NSN 6830-01-644-2557, shall meet the requirements of the most current version of Commercial Item Description A-A-59503.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
Security Requirements: Contractor personnel shall provide a valid passport, driver’s license, insurance, vehicle paperwork, and shall be escorted at all times at each
Spangdahlem AB, Germany
TSW – CDSSPANGDA DODAAC – FP8063
STATEMENT OF OBJECTIVES, 16 Jan 20 products and related services, requires delivery of Aviator’s Breathing Oxygen and Liquid Nitrogen to Spangdahlem AB, Germany into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b.
destination to Spangdahlem AB.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
Liquid Nitrogen (LN2), Type II, Grade B, NSN 6830-01-644-2557, shall meet the requirements of the most current version of Commercial Item Description A-A-59503.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior
Security Requirements: Contractor personnel shall provide a valid passport, driver’s license, insurance, vehicle paperwork, and shall be escorted at all times at each
Naval Air Station (NAS) Souda Bay - Air Force, Greece
TSW – CDSNSASDBY DODAAC – FP8071
STATEMENT OF OBJECTIVES, 11 Feb 20
Scope: The Defense Logistics Agency (DLA) Aerospace Energy Business Unit, as the Department of Defense (DoD) Integrated Materiel Manager (IMM) for Aerospace Energy products and related services, requires delivery of Aviator’s Breathing Oxygen to NSA Souda Bay, Greece into a Contractor-leased tank. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to NSA Souda Bay- Air Force.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Expedited/Emergency Delivery:
Emergency deliveries shall be within three (3) calendar days of request unless otherwise determined with the DLA Contracting Officer. After emergency delivery order is placed, Contractor shall coordinate delivery time and acceptance of emergency deliveries with customer.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Contractor-Provided Tank Installation:
Contractor shall install their Contractor provided tanks and equipment on existing cement pads, within the existing system footprints, no later than 30 calendar days from start of contract performance. The Contractor shall also perform all inspections and maintenance of Contractor provided tanks/equipment to assure systems provide safe and uninterrupted support. Contractor provided tanks may be chilled through initial deliveries, but initial deliveries into Contractor provided tanks shall not qualify as a “Hot Fill” service. The Contractor will coordinate with the current supplier to effect removal of current equipment and installation of new equipment, or to retain the current equipment.
The Contractor may be required to provide a temporary system during change out of existing system or tanks to eliminate any delay in supply of product.
Contractor-Provided Equipment Removal:
Contractor provided tanks/equipment shall be removed by the Contractor within 30 calendar days after contract termination. The Contractor will coordinate with the follow-on supplier to effect removal of current equipment and installation of new equipment.
Security Requirements: Contractor personnel shall provide a valid passport, driver’s license, insurance, vehicle paperwork, and shall be escorted at all times at each
NAS Souda Bay - Navy, Greece
TSW – CDSNSASDBY DODAAC – N66691
STATEMENT OF OBJECTIVES, 9 Mar 20
Scope: The Defense Logistics Agency (DLA) Aerospace Energy Business Unit, as the Department of Defense (DoD) Integrated Materiel Manager (IMM) for Aerospace Energy products and related services, requires delivery of Aviator’s Breathing Oxygen to NSA Souda Bay, Greece into Contractor-provided tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to NSA Souda Bay - Navy.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Expedited/Emergency Delivery:
Emergency deliveries shall be within three (3) calendar days of request unless otherwise determined with the DLA Contracting Officer. After emergency delivery order is placed, Contractor shall coordinate delivery time and acceptance of emergency deliveries with customer.
Contractor-Provided Tank Installation:
Contractor shall install their Contractor provided tanks and equipment on existing cement pads, within the existing system footprints, no later than 30 calendar days from start of contract performance. The Contractor shall also perform all inspections and maintenance of Contractor provided tanks/equipment to assure systems provide safe and uninterrupted support. Contractor provided tanks may be chilled through initial deliveries, but initial deliveries into Contractor provided tanks shall not qualify as a “Hot Fill” service. The Contractor will coordinate with the current supplier to effect removal of current equipment and installation of new equipment, or to retain the current equipment.
The Contractor may be required to provide a temporary system during change out of existing system or tanks to eliminate any delay in supply of product.
Contractor-Provided Equipment Removal:
Contractor provided tanks/equipment shall be removed by the Contractor within 30 calendar days after contract termination. The Contractor will coordinate with the follow-on supplier to effect removal of current equipment and installation of new equipment.
Aviano AB, Italy
TSW – CDSAVIANOA DODAAC – FP8112
STATEMENT OF OBJECTIVES, 26 Nov 19
Scope: The Defense Logistics Agency (DLA) Aerospace Energy Business Unit, as the Department of Defense (DoD) Integrated Materiel Manager (IMM) for Aerospace Energy products and related services, requires delivery of Aviator’s Breathing Oxygen and Liquid Nitrogen to Aviano AB, Italy into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to Aviano
AB.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
Liquid Nitrogen (LN2), Type II, Grade B, NSN 6830-01-644-2557, shall meet the requirements of the most current version of Commercial Item Description A-A-59503.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior
Security Requirements: Contractor personnel shall provide a valid passport, driver’s license, insurance, vehicle paperwork, and shall be escorted at all times at each
NAS Sigonella, Italy
TSW – CDSNASSIGO DODAAC – N00061
STATEMENT OF OBJECTIVES, 2 Mar 20
Scope: The Defense Logistics Agency (DLA) Aerospace Energy Business Unit, as the Department of Defense (DoD) Integrated Materiel Manager (IMM) for Aerospace Energy products and related services, requires delivery of Aviator’s Breathing Oxygen to NAS Sigonella, Italy into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to NAS Sigonella.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
Lajes Field AB, Portugal
TSW – CDSLAJESAB DODAAC – FP4486
STATEMENT OF OBJECTIVES, 14 Jan 20 products and related services, requires delivery of Aviator’s Breathing Oxygen to Lajes Field AB, Portugal into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to Lajes Field AB.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
Royal Air Force (RAF) Fairford, United Kingdom
TSW – CDSFAIRFOR DODAAC – FP8000
STATEMENT OF OBJECTIVES, 27 Dec 19
Scope: The Defense Logistics Agency (DLA) Aerospace Energy Business Unit, as the Department of Defense (DoD) Integrated Materiel Manager (IMM) for Aerospace Energy products and related services, requires delivery of Aviator’s Breathing Oxygen to RAF Fairford, UK into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to RAF Fairford.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
RAF Lakenheath, TSW – CDSLAKENHE DODAAC – FP8040
STATEMENT OF OBJECTIVES, 16 Jan 20 products and related services, requires delivery of Aviator’s Breathing Oxygen to RAF Lakenheath, UK into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to RAF Lakenheath.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).
RAF Mildenhall, TSW – CDSMILDENH DODAAC – FP8071
STATEMENT OF OBJECTIVES, 8 Jan 20 products and related services, requires delivery of Aviator’s Breathing Oxygen to RAF Mildenhall, UK into Government-owned tanks. The Contractor shall provide all product, materials, supplies, management, tools, equipment, transportation and labor necessary for the delivery of requested product f.o.b. destination to RAF Mildenhall.
Product: Aviator’s Breathing Oxygen (ABO), Type II, NSN 6830-01-644-2463, shall meet the requirements of the most current version of MIL-PRF-27210.
One copy of the Certificate of Analysis (COA) for each sample required by the specification shall be submitted by the Contractor as an attachment to Wide Area Workflow (WAWF). In addition, the Contractor shall include a copy of COA to accompany each delivery to be provided to acceptor at delivery destination.
Product Delivery: Product shall be delivered within 7 calendar days after receipt of an order from the appointed Delivery Scheduler.
Method of Measurement: Method of measurement shall be by truck mounted calibrated flow meter.
Inspection and Acceptance: Inspection for quality shall be performed at origin.
Quantity determination and acceptance shall be at destination. Contractor shall obtain customer signature for delivery at each location for acceptance of quantity. A copy of the signed quantity acceptance document must be attached to the WAWF invoice submittal for payment.
Tank Over-Pressure Protection: If it is determined during supplier site visits or upon review of Customer tank technical information, that additional tank over-pressure protection is required to comply with CGA P-59, Prevention of Over-Pressure during Filling of Cryogenic Vessels, the Contractor shall identify the deficiency to the designated Customer representative(s) for implementation of corrective action. The Contractor may be requested to provide and install the additional tank protection, which may encompass any of the methods identified in the P-59. NOTE: Over-pressure protection devices shall not be installed on Customer-owned storage tanks without prior coordination with DLA Energy Contracting Officer and the activity that physically possesses the tank(s).