Statement of Need - RA Cooling Infrastructure Repair PDF.pdf
PDF 170 KB Posted
- Attached to
- FA2543BuckleyCoolingInfrastructureRepair
- Solicitation number
- FA2543BuckleyCoolingInfrastructureRepair
About this file
This is a Statement of Need from 460 Civil Engineer Squadron (460 CES) for restricted area cooling water repair materials required for the Mission Delta 4 (MD4) Restricted Area at Buckley Space Force Base.
The procurement requires three distinct product packages: (1) an Elbow Repair Package containing 30 carbon steel pipe repair clamps in sizes ranging from 3" to 10" diameter (with straight, 90-degree, and 45-degree configurations), capable of withstanding 60 PSI water pressure and featuring 3-Layer Polyethylene internal coating with either epoxy or neoprene protection; (2) a Pipe Freezing Kit utilizing liquid carbon dioxide to create in-line ice plugs for temporary pipe isolation on pipes 3/8" to 10" in diameter, capable of achieving minimum -109°F temperatures, and including jackets, high-pressure hoses (minimum 16' length), CO2 cylinder valve adapters, and timing boards; and (3) a Carbon Fiber Cloth Roll, Epoxy and High-Modulus Filler Package consisting of a field-saturated carbon fiber system with two-part epoxy capable of sealing steel pipe leaks in both hoop and axial directions, operating effectively at temperatures up to 200°F with minimum ply thickness of 0.0105". All three product categories must comply with ASME PCC-2, ISO 24817, and ASME B13 standards for high-pressure leak sealing. Delivery to Buckley Space Force Base is required within 3 days of order receipt, with government acceptance and inspection upon delivery. No response date, award date, or pricing information is specified in this statement of need document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought - RA Cooling Infrastructure PDF.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF NEED
460 CES
Restricted Area Cooling Water Repair Materials Current as of 17 March 2026
1. SCOPE:
460 CES requires a large-scale material purchase to repair and fortify the cooling water within the Mission Delta 4 (MD4) Restricted Area (RA). Necessary materials include carbon steel pipe repair clamps for leak repair, a pipe freezing kit for temporary isolation for pipes up to an 10” diameter, and carbon fiber cloth for leak hardening.
2. REQUIREMENT:
Product
Quantity
Elbow Repair Package 1
Pipe Freezing Kit 1
Carbon Fiber Cloth Roll, Epoxy and High-Modulus Filler Package
3. SPECIFICATIONS:
Elbow Repair Package
- Shall include two (2) 10” pipe repair clamps.
- Shall include two (2) 8” pipe repair clamps.
- Shall include two (2) 6” pipe repair clamps.
- Shall include two (2) 4” pipe repair clamps.
- Shall include two (2) 3” pipe repair clamps.
- Shall include two (2) 10” 90-degree elbow clamps.
- Shall include two (2) 8” 90-degree elbow clamps.
- Shall include two (2) 6” 90-degree elbow clamps.
- Shall include two (2) 4” 90-degree elbow clamps.
- Shall include two (2) 3” 90-degree elbow clamps.
- Shall include two (2) 10” 45-degree elbow clamps.
- Shall include two (2) 8” 45-degree elbow clamps.
- Shall include two (2) 6” 45-degree elbow clamps.
- Shall include two (2) 4” 45-degree elbow clamps.
- Shall include two (2) 3” 45-degree elbow clamps.
- Clamps shall be capable of withstanding up to 60 PSI water pressure.
- Clamps shall be internally 3-Layer Polyethylene (3LPE) coated.
- Clamps shall be carbon steel material.
- All clamps must have either an internal epoxy coating as called out or come with a neoprene sheet.
- Material shall be compliant with ASME PCC-2, ISO 24817, and ASME B13 for sealing high pressure leaks.
Pipe Freezing Kit
- Shall utilize liquid carbon dioxide (CO2) to freeze stationary water.
- Shall create in-line ice plug within piping system for pipe section isolation.
- Shall form dry ice at a temperature of at minimum -109ºF.
- Shall include all necessary jackets to support freezing pipes 3/8” to 10” in diameter.
- Shall include high pressure hoses no less than 16’ in length.
- Shall include all necessary CO2 cylinder valve adapters.
- Shall include all necessary timing boards and pads.
- Material shall be compliant with ASME PCC-2, ISO 24817, and ASME B13
Carbon Fiber Cloth Roll, Epoxy and High-Modulus Filler Package
- Shall be field-saturated system made of carbon fiber cloth.
- Shall come with and be applied with two-part epoxy.
- Shall be a high-modulus filler material, comparable to industry standard for sealing high-pressure leaks.
- Shall seal steel pipe leaks in both hoop and axial directions.
- Shall operate effectively at temperatures up to 200oF.
- Shall be effective on cooling water lines.
- Shall have ply thickness of at least 0.0105”.
- Material shall be compliant with ASME PCC-2, ISO 24817, and ASME B13
4. DELIVERY:
Must be delivered to Buckley Space Force Base. The contractor shall deliver the above requirements no later than 3 days after receipt of order.
Items, when delivered, will be accepted and inspected by the government officials responsible for receiving the products and performing any required inspections.
File details come from the government source that posted it. Updated .