Statement_of_Intent_To_Pay_Prevailing_Wages.pdf

PDF 91 KB Posted

Attached to
G-80 Well POD-10 and POD-11 Drilling and Testing
Solicitation number
ITB-2704
Issued by
San Juan County, New Mexico

About this file

This is a Statement of Intent to Pay Prevailing Wages form issued by the State of New Mexico's Department of Workforce Solutions, Labor Relations Division, applicable to the G-80 Well POD-10 and POD-11 Drilling and Testing project for the City of Gallup. The form must be completed and submitted to the contracting agency within three days of contract award. The project involves drilling, geophysical logging, casing installation, pressure cementing, well screen installation, alignment surveys, well disinfection, development, and testing of two groundwater supply wells located in the SW and SE corners of Section 13, T16N, R19W N.M.P.M. in McKinley County, New Mexico. The form requires general contractor information including company details, contact information, estimated start and completion dates, State Wage Decision Number, project title, physical address, and total contract amount. Additional sections accommodate subcontractor and tiered subcontractor information with corresponding contract amounts and start dates.

All contractors, subcontractors, and tiered subcontractors working on this public works project must certify their intent to pay workers no less than the prevailing wage rates established by the Department of Workforce Solutions, Labor Relations Division, as identified by the State Wage Decision Number referenced in the bid documents. Contractors who violate prevailing wage laws—including incorrect job classification, improper payment of prevailing wages, or overtime violations—are subject to debarment procedures and must pay any back wages owed to workers under the Public Works Minimum Wage Act (13-4-11 through 13-4-18, NMSA 1978). A separate signed form is required for each contractor tier involved in the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(Revised 08/22/2013)

STATEMENT OF INTENT TO PAY PREVAILING WAGES

To Be Completed Before Construction Starts

All FIELDS ARE REQUIRED

FORM MUST BE SENT TO THE CONTRACTING AGENCY WITHIN 3 DAY OF THE AWARD

General Contractor Information Company Name:

Address:

City : State: Zip:

Phone: Fax: E-Mail:

Estimated Start Date: State Wage Decision Number:

Project Title:

Project Physical Address:

Total Contract Amount: Estimated Completion Date:

Print Name:

General Contractor Signature:

Sub Contractor Information Sub Contract Amount:

Start date on this project:

Company Name:

Address:

City: State: Zip:

Phone: Fax: E-Mail:

Sub Contractor Signature:

2nd, 3rd, etc. Tier Sub-Contractor Information Contract Amount:

Start date on this project:

Company Name:

Address:

City: State: Zip:

Phone: Fax: E-Mail:

Tier Signature:

I hereby certify that the above information is correct and that all workers I employ on this public works project will be paid no less than the Prevailing Wage Rate(s) as determined by the Department of Workforce Solutions, Labor Relations Division for this project as identified by the State Wage Decision Number. I understand that contractors who violate Prevailing Wage Laws (i.e., incorrect job classification, improper payment of prevailing wages, and/or overtime, etc.), are subject to debarment procedures and shall be required to pay any back wages due to workers. (Ref. Labor Relations Division, Public Works Minimum Wage Act Policy Manual (11.1.2 NMAC) & Public Works Minimum Wage Act (13-4-11 through 13-4-18, NMSA 1978).

Contractor’s Signature Date

(Revised 08/22/2013)

INSTRUCTIONS FOR COMPLETING STATEMENT OF INTENT TO PAY PREVAILING WAGES

GENERAL CONTRACTOR

1. Enter general contractor information and provide signature.

2. Enter State Wage Decision Number as listed in bid documents. (Example: BE-13-0123 B)

3. Enter project title - listed in bid documents.

4. Enter project physical address - exact location of project (job site).

5. Enter estimated start & completion dates of project.

6. Enter general contractor’s contract amount.

7. All Statements must be sent to the Contracting Agency.

SUB CONTRACTOR

1. Enter general contractor information, but general contractor signature is not needed.

2. Enter sub contractor information as indicated and provide signature.

3. Enter sub contractor contract amount.

NOTE: A separate signed form is needed for each contractor.

2ND TIER SUB CONTRACTOR

1. Enter general contractor information, but general contractor signature is not needed.

2. Enter sub contractor information; subcontractor signature not needed.

3. Enter 2nd tier sub information and provide signature.

4. Enter 2nd tier contractors contract amount.

3RD TIER AND HIGHER CONTRACTOR

1. Attach a copy of this completed form & list the 3rd tier contractor information under the 2nd tier

File details come from the government source that posted it. Updated .