Statement_of_Intent_To_Pay_Prevailing_Wages.pdf

PDF 91 KB Posted

Attached to
Whole Block Reconstruction - Elva Drive Gallup NM
Solicitation number
2026-ITB-004
Issued by
Mckinley County, New Mexico

About this file

The document is a Statement of Intent to Pay Prevailing Wages form, issued by the New Mexico Department of Workforce Solutions, Labor Relations Division, for the Whole Block Reconstruction project on Elva Drive in Gallup, New Mexico. The form is designed to ensure that all contractors and subcontractors working on the public works project commit to paying workers at least the prevailing wage rates as determined by the state. The form must be completed and submitted to the contracting agency within three days of the contract award, with detailed information required for the general contractor, subcontractors, and any additional tier subcontractors.

The form requires contractors to provide comprehensive company information, including contact details, contract amounts, project start and completion dates, and a State Wage Decision Number. Contractors must certify that all workers will be paid no less than the prevailing wage rates, with the understanding that violations can result in debarment procedures and potential requirements to pay back wages. The document emphasizes compliance with the Public Works Minimum Wage Act (13-4-11 through 13-4-18, NMSA 1978) and highlights the importance of correct job classification, proper wage payment, and overtime compensation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(Revised 08/22/2013)

STATEMENT OF INTENT TO PAY PREVAILING WAGES

To Be Completed Before Construction Starts

All FIELDS ARE REQUIRED

FORM MUST BE SENT TO THE CONTRACTING AGENCY WITHIN 3 DAY OF THE AWARD

General Contractor Information Company Name:

Address:

City : State: Zip:

Phone: Fax: E-Mail:

Estimated Start Date: State Wage Decision Number:

Project Title:

Project Physical Address:

Total Contract Amount: Estimated Completion Date:

Print Name:

General Contractor Signature:

Sub Contractor Information Sub Contract Amount:

Start date on this project:

Company Name:

Address:

City: State: Zip:

Phone: Fax: E-Mail:

Sub Contractor Signature:

2nd, 3rd, etc. Tier Sub-Contractor Information Contract Amount:

Start date on this project:

Company Name:

Address:

City: State: Zip:

Phone: Fax: E-Mail:

Tier Signature:

I hereby certify that the above information is correct and that all workers I employ on this public works project will be paid no less than the Prevailing Wage Rate(s) as determined by the Department of Workforce Solutions, Labor Relations Division for this project as identified by the State Wage Decision Number. I understand that contractors who violate Prevailing Wage Laws (i.e., incorrect job classification, improper payment of prevailing wages, and/or overtime, etc.), are subject to debarment procedures and shall be required to pay any back wages due to workers. (Ref. Labor Relations Division, Public Works Minimum Wage Act Policy Manual (11.1.2 NMAC) & Public Works Minimum Wage Act (13-4-11 through 13-4-18, NMSA 1978).

Contractor’s Signature Date

(Revised 08/22/2013)

INSTRUCTIONS FOR COMPLETING STATEMENT OF INTENT TO PAY PREVAILING WAGES

GENERAL CONTRACTOR

1. Enter general contractor information and provide signature.

2. Enter State Wage Decision Number as listed in bid documents. (Example: BE-13-0123 B)

3. Enter project title - listed in bid documents.

4. Enter project physical address - exact location of project (job site).

5. Enter estimated start & completion dates of project.

6. Enter general contractor’s contract amount.

7. All Statements must be sent to the Contracting Agency.

SUB CONTRACTOR

1. Enter general contractor information, but general contractor signature is not needed.

2. Enter sub contractor information as indicated and provide signature.

3. Enter sub contractor contract amount.

NOTE: A separate signed form is needed for each contractor.

2ND TIER SUB CONTRACTOR

1. Enter general contractor information, but general contractor signature is not needed.

2. Enter sub contractor information; subcontractor signature not needed.

3. Enter 2nd tier sub information and provide signature.

4. Enter 2nd tier contractors contract amount.

3RD TIER AND HIGHER CONTRACTOR

1. Attach a copy of this completed form & list the 3rd tier contractor information under the 2nd tier

File details come from the government source that posted it. Updated .