SSA Waterbury CT post award REVISED schedule.docx

DOCX document 20 KB Posted

Attached to
Lease of Office Space within Region 1. Request for Lease Proposals (RLP) #24-REG01 - Office Space
Solicitation number
9CT2076
Issued by

About this file

This document includes a federal solicitation for lease of office space and related post-award schedule. The General Services Administration Public Buildings Service Region 1 seeks to lease approximately 7,323 to 7,689 square feet of office space in Waterbury, Connecticut through the Automated Advanced Acquisition Program. The lease term is 15 years firm with an 8-year amortization period for tenant improvements and building specific amortized capital. The solicitation specifies location and configuration requirements for the space. The post-award schedule outlines a 345 calendar day timeline from lease award to government occupancy, including various design, review, approval, construction, and acceptance stages. The federal agency tenant improvement allowance is $62.50 per ABOA SF and building specific amortized capital is $25.00 per ABOA SF. Offers must be submitted through the AAAP system during open periods in January through July, with award being made to the lowest priced technically acceptable offer.

View the file

Other files

File Type Posted
SSA- Waterbury DA Map.pdf PDF
Waterbury CT DA (1).pdf PDF
Delineated Area Map Revised.pdf PDF
SSA Agency Special Requirements - Master Doc V.11-25-2020 (2).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Note: This document should be completed and attached to the AAAP Project Specific Advertisement ONLY when the generic schedule attached to the RLP needs to be replaced with a project specific post-award schedule. Reference the generic schedule when consulting with your regional project management teams to determine the appropriate number of working days for each activity. Ensure the total number of working days accurately reflects the sum of all activities prior to posting to the System for Award Management website (SAM.gov). Confirm that the working days are entered into the appropriate paragraphs in 4.01 of the lease prior to transmitting for signature.

Activity
Working Days
Agency-Provided Design Intent Drawings
30

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents
80
Government Review of Construction Drawings
30
Lessor Preparation and Submission of the TI and BSAC Price Proposal
20
Government Reviews and Approves Pricing
15
Government Issues Notice to Proceed with Construction
10
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
160
Government Inspects and Accepts Finished Space
10
Total Work Days from Lease Award to Government Acceptance
345
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1PSA VERSION - REV (10/22)