This is a Statement of Work (SOW) for Video Teleconferencing (VTC) Maintenance and Operations Support for the 25th Attack Wing (25 ATKW) at Shaw AFB, South Carolina.
The contractor shall provide comprehensive Tier II/III maintenance, operations, and programming support for the 25 ATKW's specialized VTC systems that serve as primary Command and Control and intelligence-sharing conduits for real-time remote combat and intelligence operations. The system architecture utilizes Crestron JITC-approved Audio/Video over IP (AVoIP) NVX core systems with 1G LAN connectivity via POE+ switches, routing latency-free 4K video through an isolated and secure AV core LAN network intentionally separated from primary client data networks. The contractor's scope encompasses all VTC room endpoints (codecs, touch panels, displays, peripherals) and the isolated Crestron NVX network up to the physical patch cable connecting to the base enterprise network in the server room; issues beyond this handoff point are the government's responsibility. Required services include quarterly preventative maintenance inspections with hardware diagnostics and audio/video calibration; maintenance and modification of existing custom Crestron 4-Series control programs; coordination of Cisco Webex Codec replacements under the Air Force GEMMS contract; and corrective emergency repair. Service Level Agreements mandate response within 24 business hours for Priority 1 (Critical) failures rendering VTC rooms completely inoperable, with resolution within 7 business days, and response within 72 business hours for Priority 2 (Routine) partial degradation with resolution within 14 business days. On-site services are performed at two facilities in Shaw AFB: Building 1996 (Rooms 1207, 1209, 1212, 1307, 1308, 1309, 1312, 1343) and Building 2002 (Rooms 105, 110, 114, 119, 125, 128, 129, 206, 207, 224, 227).
Contractor qualifications include active Crestron Certified Programmer (CCP), Biamp Tesira, and Cisco Certified Field Technician (CCT) certifications; demonstrable expertise in configuring and maintaining Crestron NVX AVoIP systems on isolated LANs; and minimum three years supporting secure DoD VTC platforms. All on-site personnel must possess active Top Secret/Sensitive Compartmented Information security clearances. The government retains unlimited rights to existing code and will provide complete uncompiled source code upon award. Deliverables include quarterly PM and system health reports, monthly incident/trouble ticket logs, and compiled and uncompiled code backups. The contract consists of a Base Year (November 1, 2026 to October 31, 2027) with four option years extending through October 31, 2031, subject to availability of funds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25 ATKW VTC SOW - Appendix A DRAFT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25 ATKW Video Teleconferencing System Statement of Work (SOW)
Video Teleconferencing (VTC) Maintenance and Operations Support Customer
25th Attack Wing (25 ATKW), Shaw AFB, SC
Date: 09 July 2026
Table of Contents
1.0 Project Title & Background
2.0 Scope of Work
3.0 Place of Performance & Specific Rooms
4.0 Specific Tasks & Technical Requirements
5.0 Service Level Agreements (SLAs)
6.0 Contractor Qualifications & Security
7.0 Deliverables
8.0 Period of Performance (PoP)
9.0 Appendix A: Covered Equipment Inventory
1.0 Project Title & Background
1.1 The 25th Attack Wing (25 ATKW), located at Shaw AFB, SC, requires continuous, uninterrupted Tier II/III maintenance, operations, and programming support for its specialized Video Teleconferencing (VTC) systems. Because the 25 ATKW conducts real-time, remote combat and intelligence operations globally, these VTC suites serve as primary Command and Control (C2) and intelligence-sharing conduits. Unscheduled downtime directly impacts active military operations and national security mandates.
1.2 The system design relies on a Crestron JITC-approved Audio/Video over IP (AVoIP) NVX core system utilizing 1G LAN connectivity via POE+ LAN switches. This system routes latency-free 4K video through an isolated and secure AV core LAN network that is intentionally separated from the primary client data networks. This architecture requires specialized expertise to maintain without losing system functionality, network isolation, or JITC compliance.
2.0 Scope of Work
2.1 The Contractor shall provide all management, labor, tools, equipment, materials, programming capabilities, and specialized technical expertise necessary to perform preventative maintenance, troubleshooting, corrective repair, and firmware upgrades provided by parent companies or COR for the VTC systems listed in Appendix A.
2.1.1 Contractor Scope (Internal): The Contractor is fully responsible for diagnosing and resolving all system faults originating from the VTC room endpoints (codecs, touch panels, displays, peripherals) through the isolated Crestron NVX network, up to and including the physical patch cable connecting to the base enterprise network in the server room.
2.1.2 Government / Enterprise Scope (External): Any packet loss, routing failures, firewall blocks, or physical infrastructure issues (e.g., dark fiber, base power loss) existing beyond this server room hand-off point are outside the scope of this contract. If the Contractor isolates a fault to the base network, they shall immediately document the findings and hand off the ticket to the COR or the local Communications Squadron for resolution.
2.2 The scope includes maintaining operational availability IAW 5.0 Service Level Agreements (SLAs) for the designated systems and ensuring that no software updates or hardware replacements degrade the current operational capabilities.
3.0 Place of Performance & Specific Rooms
3.1 All on-site services shall be performed at Shaw AFB, SC in the following designated secure locations:
Building Covered Rooms / Suites
Building 1996 Rooms 1207, 1209, 1212, 1307, 1308, 1309, 1312, and 1343
Building 2002 Rooms 105, 110, 114, 119, 125, 128, 129, 206, 207, 224, and 227
4.0 Specific Tasks & Technical Requirements
Requirement Area Technical Execution Details
4.1 Preventative
Maintenance (PM)
Perform quarterly PM inspections on all Appendix A systems. Testing must include hardware diagnostics, audio/video calibration, cable integrity checks, and Cisco codec loopback tests. Document findings, firmware levels, and preemptive actions in a Quarterly Report.
4.2 Custom
Software & Programming
Maintain, troubleshoot, and modify existing custom Crestron 4-Series control programs and touch panels. Critical: Firmware updates or patches must cause zero loss to existing system macro functions, routing configurations, or layouts.
4.3 AF GEMMS
Warranty Integration
All Cisco Webex Codecs are covered under the Air Force GEMMS contract. The Contractor shall not price or procure Cisco hardware warranties. The Contractor shall diagnose failures, coordinate replacements via GEMMS/COR, install Government-provided units, and restore programming.
4.4 Corrective
Emergency Repair
Dispatch qualified technicians to troubleshoot and repair failed components. If hardware is replaced, the Contractor must source non-GEMMS parts, install them, and compile existing GFI code to ensure seamless integration.
5.0 Service Level Agreements (SLAs)
5.1 Due to the combat-support mission of the 25 ATKW, response times are strictly enforced:
Priority Level
Technical Description Required Response Required Resolution
Priority 1 (Critical)
Any failure rendering a VTC room completely inoperable for scheduled or active mission-critical briefings.
Within 24 Business Hours (Remote/On-site)
Within 7 Business Days
Priority 2 (Routine)
Partial degradation of a system where VTC capabilities remain operational (e.g., failed secondary display).
Within 72 Business Hours
Within 14 Business Days
5.2 If parts are unavailable due to back order or unavailability due to real-world logistics, the contractor will provide weekly updates to the COR via email until resolved.
6.0 Contractor Qualifications & Security
6.1 To successfully execute this contract without degrading 25 ATKW capabilities, bidding contractors must meet the following mandatory thresholds:
Qualification Area
Mandatory Contractor Requirement
Manufacturer Certifications
Personnel must hold active Crestron Certified Programmer (CCP), Biamp Tesira, and Cisco Certified Field Technician (CCT) certifications, or equivalent.
AVoIP & NVX Expertise
Demonstrable expertise in configuring, troubleshooting, and maintaining Crestron NVX AVoIP systems on isolated LANs.
Code Ownership Transfer
The Government holds unlimited rights to the existing code and will provide the complete, uncompiled source code as GFI upon award.
DoD Experience & Security
Minimum three (3) years supporting secure DoD VTC platforms. All on-site personnel must possess an active Top Secret/Sensitive Compartmented Information security clearance and coordinate with the 25 ATKW Security Manager.
7.0 Deliverables
7.1 The Contractor shall provide the following deliverables to the Contracting Officer’s Representative (COR) and the designated 25 ATKW Technical Lead to ensure full accountability, SLA compliance, and Government ownership of all system configurations.
Deliverable Reference Title Submission Frequency Recipient
DEL-01 Quarterly PM & System Health Report
Within 5 business days post-
PM
COR / 25 ATKW
Tech Lead
DEL-02 Monthly Incident/Trouble Ticket Log
Monthly (by the 5th business day) COR
DEL-03
Compiled & Uncompiled Code Backup
Within 5 days of any programming change
COR (via Secure Media)
8.0 Period of Performance (PoP)
8.1 The contract will consist of a Base Year with four (4) Option Years, subject to the availability of funds (FAR 52.232-18).
Contract Phase Estimated Start Date Estimated End Date
Base Year 01 November 2026 31 October 2027
Option Year 1 01 November 2027 31 October 2028
Option Year 2 01 November 2028 31 October 2029
Option Year 3 01 November 2029 31 October 2030
Option Year 4 01 November 2030 31 October 2031
9.0 Appendix A: Covered Equipment Inventory
9.1 Appendix A provides the consolidated baseline inventory of mission-critical VTC, Audio/Visual, networking equipment and system layout to be maintained and supported under this contract, inclusive of all associated auxiliary hardware, raceways, and cabling.