SS 2027 PW1 Bid Price Form – Addenda 1
This is a bid price form addendum for a public works services contract managed by the Metropolitan Area Planning Council (MAPC) on behalf of the South Shore Regional Services Consortium, serving twelve participating Massachusetts municipalities. The contract encompasses four primary service categories: Roadway Surface Treatments (microsurfacing, emulsion with latex chip seal, and asphalt rubber surface treatment); Pavement Markings (thermoplastic, water-based, epoxy, and low V.O.C. options); Street Sweeping (spring cleanup and on-call services); and Sidewalk Construction, Reconstruction, and Resurfacing (bituminous and cement concrete work with associated drainage and traffic control services). The bid form itemizes estimated quantities for each service line, ranging from 2,500 square yards for certain microsurfacing applications to 675,100 linear feet for 4-inch yellow single pavement markings, with quantities varying significantly across the four categories. The contract term extends through December 31, 2027, with two optional one-year renewal periods available. Bids were due October 8, 2026, at 4:00 PM via CommBUYS with public opening conducted via Zoom.
Pricing is structured on a unit-price basis, with bidders required to provide costs per square yard for surface treatments and pavement markings, per linear foot for curbing and installations, per ton for asphalt materials and disposal, per day for equipment and materials, per hour for labor and equipment rental, and per each (EA) for discrete items such as signs and symbols. The estimated total first-year contract value is $5.957 million, composed of approximately $4.485 million for roadway surface treatments, $591,081 for pavement markings, $84,000 for street sweeping, and $796,585 for sidewalk work. Bidders must comply with Massachusetts prevailing wage laws and hold MassDOT prequalification in the applicable work class or appear on a MassDOT waiver contractor bid list as of the bid opening date. A bid deposit equal to 5 percent of estimated contract value, performance bonds, and labor and materials payment bonds of at least 50 percent of estimated contract value are required. Low bidders are subject to a 1 percent MAPC contract administration fee on total invoiced amounts. Unit prices remain firm except for permitted adjustments tied to MassDOT fuel and material indices for diesel, gasoline, liquid asphalt, Portland cement concrete, and steel. Individual contracts execute between each participating municipality and the low bidder, with each municipality retaining authority to accept or reject the award.
View the file
Other files
Show 40 more
Latest 50 of 82 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SS 2027 PW1 - Bid Price Form - Addenda 1 Bidder Name: ___________________
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
4. ROAD SURFACE SEALING TREATMENTS
A. Microsurfacing Bid Total = $
1) Surface Course (1 Lift) - [30,000SY and Over] 2,500 x /SY = $
2) Surface Course (1 Lift) - [under 30,000SY] 37,700 x /SY = $
3) Leveling + Surface Course (2 Lifts) - [30,000SY and Over] 10,000 x /SY = $
4) Leveling + Surface Course (2 Lifts) - [under 30,000SY] 45,200 x /SY = $
5) Crack Sealing [per Square Yard] 10,000 x /SY = $
6) Crack Sealing [per Day] 10 x /DY = $
7) Rut Filling 250 x /TN = $
8) Shimming [per Square Yard] 30,000 x /SY = $
9) Shimming [per Ton] 770 x /TN = $
10) Drainage or Sanitary Structures - Adjusted 81 x /EA = $
11) Drainage or Sanitary Structures - Rebult 66 x /FT = $
12) Traffic Controls/Safety Signing -
Traffic Controls/Safety Signing 100 x /SF = $
Reflectorized Drums with Flashers [Type A] - Drum Day 25 x /DY = $
Reflectorized Drums without Flashers - Drum Day 25 x /DY = $
Traffic Cones 25 x /DY = $
Portable Changeable Message Boards - Unit Day 25 x /DY = $
B.Emulsion with Latex [Chip Seal] Bid Total = $
1) Patch Work 2,075 x /SY = $
2) Double Stone Seal (1/2" & 3/8" Stone) 47,500 x /SY = $
3) Double Stone Seal (3/8" Stone & 1/4" Grit) 47,500 x /SY = $
4) Single Stone Seal (1/2" & 3/8" Stone) 42,500 x /SY = $
5) Traffic Controls/Safety Signing
Traffic Controls/Safety Signing 100 x /SF = $
Reflectorized Drums with Flashers [Type A] - Drum Day 25 x /DY = $
Reflectorized Drums without Flashers - Drum Day 25 x /DY = $
Traffic Cones 25 x /DY = $
Portable Changeable Message Boards - Unit Day 25 x /DY = $
C. Asphalt Rubber Surface Treatment Bid Total = $
1) 10% Asphalt Rubber Surface Treatment 65,000 x /SY = $
2) 20% Asphalt Rubber Surface Treatment 65,000 x /SY = $
3) Traffic Controls/Safety Signing
Traffic Controls/Safety Signing 100 x /SF = $
Reflectorized Drums with Flashers [Type A] - Drum Day 25 x /DY = $
Reflectorized Drums without Flashers - Drum Day 25 x /DY = $
Traffic Cones 25 x /DY = $
Portable Changeable Message Boards - Unit Day 25 x /DY = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
6. PAVEMENT MARKINGS
Pavement Markings [Contractor provides both Labor & Materials] Bid Total (Subtotals A + B + C + D) = $
A Thermoplastic $
B Water-Based $
C Epoxy $
D Low V.O.C. $
A. Thermoplastic Subtotal = $
1) 4" Yellow Double 25,493 x /LF = $
2) 4" Yellow Single 675,100 x /LF = $
3) 4" Yellow - Dashed 50 x /LF = $
4) 4" White Double as needed @ /LF
5) 4" White Single 439,700 x /LF = $
6) 4" White - Dashed 5,050 x /LF = $
7) 6" Yellow - Double as needed @ /LF
8) 6" White - Single as needed @ /LF
9) 12" White Stop & Crosswalk 4,850 x /LF = $
10) 6' White Police Circles 2 x /EA = $
11) 8' White "SCHOOL" Legend 14 x /EA = $
12) 8' White "ONLY" Legend 10 x /EA = $
13) Arrows [federal size] 75 x /EA = $
14) 4" White Parking T's and L's 370 x /EA = $
15) 4" White or Yellow Channelization/Median Islands 100 x /LF = $
16) 10' White "SCHOOL" 2 x /EA = $
17) White "RXR" [federal size] 24 x /EA = $
18) 8' White "STOP" 110 x /EA = $
19) 2' Letters as needed @ /EA
20) 3' Letters as needed @ /EA
21) 4" Parking Lot stalls (est. 50 lf each) 1,300 x /LF = $
22) Bike Lane Symbols - White Directional Arrow 20 x /EA = $
23) Bike Lane Symbols - White Bicycle 20 x /EA = $
24) Bike Lane Symbols - White Bicyclist 20 x /EA = $
25) Bike Lane Letters - White "BIKE", "LANE" 10 x /EA = $
26) Bike Lane Symbols - White Sharrow/Shared Lane as needed @ /EA
27) Bicycle Detector Symbol - White 10 x /EA = $
28) Grind Existing Lines (95% - 100%) 400 x /LF = $
B. Water-Based - Subtotal = $
1) 4" Yellow Double 16,582 x /LF = $
2) 4" Yellow Single 34,082 x /LF = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
3) 4" Yellow - Dashed 4,050 x /LF = $
4) 4" White Double 9,000 x /LF = $
5) 4" White Single 26,082 x /LF = $
6) 4" White - Dashed 50 x /LF = $
7) 6" Yellow - Double as needed @ /LF
8) 6" White - Single as needed @ /LF
9) 12" White Stop & Crosswalk 3,550 x /LF = $
10) 6' White Police Circles 5 x /EA = $
11) 8' White "SCHOOL" Legend 113 x /EA = $
12) 8' White "ONLY" Legend 120 x /EA = $
13) Arrows [federal size] 135 x /EA = $
14) 4" White Parking T's and L's 20 x /EA = $
15) 4" White or Yellow Channelization/Median Islands 610 x /LF = $
16) 10' White "SCHOOL" 511 x /EA = $
17) White "RXR" [federal size] 11 x /EA = $
18) 8' White "STOP" 150 x /EA = $
19) 2' Letters 40 x /EA = $
20) 3' Letters 90 x /EA = $
21) 4" Parking Lot stalls (est. 50 lf each) 85 x /LF = $
22) Bike Lane Symbols - White Directional Arrow 65 x /EA = $
23) Bike Lane Symbols - White Bicycle 15 x /EA = $
24) Bike Lane Symbols - White Bicyclist 15 x /EA = $
25) Bike Lane Letters - White "BIKE", "LANE" 105 x /EA = $
26) Bike Lane Symbols - White Sharrow/Shared Lane 5 x /EA = $
27) Bicycle Detector Symbol - White 5 x /EA = $
28) Grind Existing Lines (95% - 100%) 10,000 x /LF = $
C. Epoxy Subtotal = $
1) 4" Yellow Double 6,582 x /LF = $
2) 4" Yellow Single 31,082 x /LF = $
3) 4" Yellow - Dashed 4,000 x /LF = $
4) 4" White Double 9,000 x /LF = $
5) 4" White Single 6,082 x /LF = $
6) 4" White - Dashed as needed @ /LF
7) 6" Yellow - Double as needed @ /LF
8) 6" White - Single as needed @ /LF
9) 12" White Stop & Crosswalk 1,700 x /LF = $
10) 6' White Police Circles 3 x /EA = $
11) 8' White "SCHOOL" Legend 103 x /EA = $
12) 8' White "ONLY" Legend 110 x /EA = $
13) Arrows [federal size] 110 x /EA = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
14) 4" White Parking T's and L's 20 x /EA = $
15) 4" White or Yellow Channelization/Median Islands 60 x /LF = $
16) 10' White "SCHOOL" 63 x /EA = $
17) White "RXR" [federal size] 53 x /EA = $
18) 8' White "STOP" 40 x /EA = $
19) 2' Letters 20 x /EA = $
20) 3' Letters 20 x /EA = $
21) 4" Parking Lot stalls (est. 50 lf each) 25 x /LF = $
22) Bike Lane Symbols - White Directional Arrow 5 x /EA = $
23) Bike Lane Symbols - White Bicycle 5 x /EA = $
24) Bike Lane Symbols - White Bicyclist 5 x /EA = $
25) Bike Lane Letters - White "BIKE", "LANE" 5 x /EA = $
26) Bike Lane Symbols - White Sharrow/Shared Lane 5 x /EA = $
27) Bicycle Detector Symbol - White 5 x /EA = $
28) Grind Existing Lines (95% - 100%) 10,000 x /LF = $
D. Low V.O.C. Subtotal = $
1) 4" Yellow Double 500 x /LF = $
2) 4" Yellow Single 25,000 x /LF = $
3) 4" Yellow - Dashed as needed @ /LF
4) 4" White Double 5,000 x /LF = $
5) 4" White Single as needed @ /LF
6) 4" White - Dashed as needed @ /LF
7) 6" Yellow - Double as needed @ /LF
8) 6" White - Single as needed @ /LF
9) 12" White Stop & Crosswalk 1,500 x /LF = $
10) 6' White Police Circles 3 x /EA = $
11) 8' White "SCHOOL" Legend 3 x /EA = $
12) 8' White "ONLY" Legend 10 x /EA = $
13) Arrows [federal size] 10 x /EA = $
14) 4" White Parking T's and L's 20 x /EA = $
15) 4" White or Yellow Channelization/Median Islands 10 x /LF = $
16) 10' White "SCHOOL" 3 x /EA = $
17) White "RXR" [federal size] 3 x /EA = $
18) 8' White "STOP" 40 x /EA = $
19) 2' Letters 20 x /EA = $
20) 3' Letters 20 x /EA = $
21) 4" Parking Lot stalls (est. 50 lf each) 25 x /LF = $
22) Bike Lane Symbols - White Directional Arrow 5 x /EA = $
23) Bike Lane Symbols - White Bicycle 5 x /EA = $
24) Bike Lane Symbols - White Bicyclist 5 x /EA = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
25) Bike Lane Letters - White "BIKE", "LANE" 5 x /EA = $
26) Bike Lane Symbols - White Sharrow/Shared Lane 5 x /EA = $
27) Bicycle Detector Symbol - White 5 x /EA = $
28) Grind Existing Lines (95% - 100%) 10,000 x /LF = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
8. STREET SWEEPING
A. Spring Clean-Up (Streets) Bid Total = $
1) Disposal by Town 150 x /C. Mi. = $
2) Disposal by Contractor 200 x /TN = $
B. On-Call (Regular & Emergency) Bid Total =
1) Disposal by Town 150 x /HR
2) Disposal by Contractor 200 x /TN = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
14. SIDEWALK CONSTRUCTION, RECONSTRUCTION, AND REPAIR
Sidewalk Construction, Reconsuction, and Resurfacing Bid Total = $
1) Cape Cod Berm 400 x /LF = $
2) Granite Curb - Straight [Supply and Set] 5,700 x /LF = $
Granite Curb - Straight [Set Only] 20 x /LF = $
Granite Curb - Radius [Supply and Set] 150 x /LF = $
Granite Curb - Radius [Set Only] 20 x /LF = $
3) Pre-Cast Concrete Curb - Straight [Set Only] 200 x /LF = $
Pre-Cast Concrete Curb - Radius [Set Only] 5 x /LF = $
4) Adjust/Reset Curbing 150 x /LF = $
5) Bituminous Concrete Sidewalk - New Construction 475 x /SY = $
[Site Prep by Town] 10 x /SY = $
6) Bituminous Concrete Sidewalk - Reconstruction 2,275 x /SY = $
[Site Prep by Town] 10 x /SY = $
Gravel 650 x /CY = $
7) Bituminous Concrete Sidewalk and Driveway Apron - Resurfacing 125 x /SY = $
[Site Prep by Town] 15 x /SY = $
8) Cement Concrete Sidewalk - New Construction 50 x /SY = $
Cement Concrete Sidewalk - Reconstruction 50 x /SY = $
9) Cement Concrete Wheelchair Ramps - New Construction 100 x /SY = $
Cement Concrete Wheelchair Ramps - Reconstruction 100 x /SY = $
10) Sawcutting 5,500 x /LF = $
11) Handicap Ramp Tactile Strips 55 x /EA = $
12) Loam & Hydro-Seed [4" Depth] 400 x /SY = $
13) Adjust Service Box 190 x /EA = $
14) Replace Service Box 20 x /EA = $
15) Adjust Manhole Catch Basin Frames 225 x /EA = $
16) Rebuild Manhole and Catch Basin Frames 70 x /EA = $
17) Reset or Replace Brick or Stone Walkway 75 x /SY = $
18) Catch Basin Installed 25 x /EA = $
19) Gutter Inlet Installed 20 x /EA = $
20) Ductile Iron Drainpipe 450 x /LF = $
21) 4 inch PVC Pipe for Drainage 350 x /LF = $
22) Unclassified Excavation 660 x /CY = $
23) Hot Mix Asphalt for Patching 450 x /TN = $
24) Traffic Controls/Safety Signing -
Traffic Controls/Safety Signing 250 x /SF = $
Reflectorized Drums with Flashers [Type A] - Drum Day 30 x /DY = $
Reflectorized Drums without Flashers - Drum Day 80 x /DY = $
Traffic Cones 80 x /DY = $
Bidder Initials: ___________
Bid Item
Estimated
Quantity x Bid Price / Unit = Total
Changes to the document marked in RED.
25) Pre-Paving Sweeping -
Disposal by Town 75 x /HR = $
Disposal by Contractor 50 x /TN = $
26) Equipment Rental -
Gradall 120 x /HR = $
Grader 2 x /HR = $
Tandom 10-Ton Roller 30 x /HR = $
10-Ton Vibrator Roller 30 x /HR = $
10 Wheel Dump Truck 80 x /HR = $
Trailer 16 x /HR = $