Questions and Answers

1. What is the length (term) of this assignment?

A. Duration of the SDUs 8, 9, 10, 11 and 12.

2. Is there an estimate of the number of man-hours/year that will be required?

A. 3 issues per unit. 50 hrs to 100 hrs each.

3. Does the scope of work include materials analysis and testing (non-destructive and destructive)?

A. The material being used has been vetted trough a battery of tests e.g. compressive strength, shrinkage, transport properties, Immersion, sulfate expansion, etc. Additional materials analysis and testing is unlikely.

4. Who will the selected firm contract with? DOE or a third-party contractor?

A. Savannah River Remediation, LLC.

5. Will this be a full-time position on site during the construction of the SDU’s?

A. Not a full-time position. SME services will be required on a case by case basis.

6. You have placed a high priority of individuals with credentials that include fellowships in certain professional organizations. Is that an absolute requirement, or will decades of professional engineering experience with mix design and structural design/analysis be deemed equal?

A. SRR has professional engineering experience with mix design and structural design/analysis. Credentials and fellowships are priority because of the potential need for in-depth codes and standards interpretations to enable solutions and related support documentation.

7. Are there incumbents SME’s?

A. Not currently.