Exhibit A SPRBL1-17-R-0030 Page 1 of 16 Issue: 30 May 2017
TECHNICAL REQUIREMENTS
AC Generators Used on 15 kW Tactical Quiet Generators
Exhibit A SPRBL1-17-R-0030 Page 2 of 16
VERSION REVISIONS
Version Added/Deleted Reason 24 Jun 2015 Added: Version Revision table for future use 09 Mar 2016 Add: Contract Security Requirements section APG G-2 Army Security Office policy.
Exhibit A SPRBL1-17-R-0030 Page 3 of 16
TABLE OF CONTENTS
APPLICABLE DOCUMENTS
CONFIGURATION BASELINE
Obsolescence Reporting
Part Revisions
PACKAGING
Wood Packing Material
Military Packaging
SPECIALIZED TESTING ..................................................................................... Error! Bookmark not defined.
CONTRACT SECURITY REQUIREMENTS
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
CDRL List
Individual CDRLs
Exhibit A SPRBL1-17-R-0030 Page 4 of 16
APPLICABLE DOCUMENTS
Military and Federal Standards
MIL-STD-129R MILITARY MARKING FOR SHIPMENT AND STORAGE
MIL-STD-130N IDENTIFICATION MARKING OF U.S. MILITARY PROPERTY
MIL-STD-2073-1E CHANGE 1 STANDARD PRACTICE FOR MILITARY PACKAGING
Military and Federal Specifications
Other Documents
SPECIAL PACKAGING
AG606REVA
5-60 KW GENERATORS
DRAWING 88-21005 GENERATOR, 15 KW 50/60 HZ
DRAWING 88-21006 GENERATOR, 15 KW 400 HZ
Commercial Documents ISPM 15 Regulation of Wood Packaging Material in International Trade
4/1/2009
Security Documents AT-OPSEC Anti-Terrorism / Operational Security
CONFIGURATION BASELINE
The applicable Configuration Baselines (CB), for the listed Configuration Item (CI) and/or Computer Software Configuration Item (CSCI), are as listed in the table below.
NSN Nomenclature Part Numbers/Drawings
6115-01-383-3124 AC GENERATOR, 15 KW 50/60 HZ 88-21005
6115-01-434-1432 AC GENERATOR, 15 KW 400 HZ 88-21006
Exhibit A SPRBL1-17-R-0030 Page 5 of 16
Configuration. Each CI/CSCI, as developed/built and delivered, shall conform to the cited CB and (if applicable) all subsequent CB’s that will be made contractually binding by the Procuring Contracting Officer (PCO). Configuration changes not directly effecting the configuration baseline do not require Government approval prior to incorporation, but must be documented by the contractor and shall be made available to the Government upon request.
Departures from CB. No changes or departures from the CB are acceptable except for changes or departures which are submitted in accordance with DI-MISC-80711A and are approved by the Government Configuration Manager (C Mgr.) or Configuration Management Officer (CMO) and which are made applicable to the contract by the PCO. Configuration Control shall be effected by the Configuration Control Documents (CCDs) as follows:
Engineering Change Proposal (ECP) includes both the engineering change and the supporting documentation by which the change is described and suggested. An ECP describes changes to the CI/CSCI and associated Government documents and data that are affected by the proposed engineering change.
A Notice of Revision (NOR) shows the detailed changes that must be made to technical documentation, except specifications, (one NOR per document) following approval of an ECP. The NOR is submitted as part of the ECP.
A Specification Change Notice (SCN) is used to delineate the exact change(s) in a specification that will be distributed to users when the ECP is approved. The SCN is submitted as part of the ECP. The SCN is not used for a military or federal document, only a Request for Waiver can be used for those documents.
Value Engineering Change Proposal (VECP) is the same as an ECP except there are proposed cost savings for the program. The contractor shall follow the guidance in Section I of this contract for VECPs.
Request for Waiver (RFW) describes a departure from configuration documentation for a specific number of units or period of time.
Contractor shall identify the impact of the RFW on performance, operational readiness and logistics support of the affected CIs. The Government will require compensation for any RFW.
Contractor shall provide all supporting program or cost data with the CCD. The contractor shall uniquely and sequentially identify (including the use of the contract number) each ECP, VECP, NOR, SCN or RFW. The identification number should use less than 16 characters.
New Items. The contractor shall provide IUID, or DoD recognized equivalent, for all items delivered with an acquisition cost of $5000 or more. For long term contracts, any items that have range quantity prices established, that will exceed the $5000 unit price shall have IUID markings from the beginning of the contract. IUID markings shall be IAW MIL-STD-130N.
Exhibit A SPRBL1-17-R-0030 Page 6 of 16
Permanency and Legibility. The IUID marking and identification plates, tags, etching, or labels when used on equipment, parts, assemblies, subassemblies, units, sets, groups, or kits shall be as permanent as the normal life expectancy of the item and be capable of withstanding the environment, test, cleaning, repair, and rebuild procedures specified for the item. Legibility shall be as required and verified for ready readability per MIL-STD-130N.
Deleterious Effect. Marking of items shall be accomplished in a manner that will not adversely affect the life and utility of the item.
Marking materials creating hazardous conditions shall not be used. Placement and choice of the marking shall not create hazardous conditions.
IUID markings and readability requirements shall comply with MIL-STD-130N.
Symbology markings and the order of priority for marking the hardware shall be in accordance with MIL-STD 103N. First priority is the 2D data matrix symbol (machine readable) IUID is the minimum requirement when there are severe space limitations. The second priority is the human readable characters. The third priority is the Linear Bar Code.
Per the Department of Defense, Item Unique Identification of Government Property Guidebook, Reporting Government Property In the Possession of the Contractor (PIPC), Guidance for: Defense Federal Acquisition Regulation (DFARS) 252.211-7007, Item Unique Identification of Government Property, Version 1.0, September 21, 2007
For new contracts issued after September 13, 2007, DoD will include an Interim Rule, DFARS 252.211-7007, Item Unique Identification of Government Property (DFARS Case 2005-D015), which permanently revises requirements for reporting of PIPC.
The interim rule permanently replaces the DD Form 1662 reporting requirements with requirements for DoD contractors to electronically submit, to the IUID registry, the IUID data applicable to PIPC.
It should be understood that in accordance with DFARS 211.274-5, Contract clauses, the clause at DFARS 252.211-7003, Item Identification and Valuation, must be included in any contract that incorporates the clause at DFARS 252.211-7007, Item Unique Identification of Government Property. This is essential to assure there is no ambiguity in the requirements for assigning, registering, reporting and marking PIPC.
The contractor shall maintain an accurate, current list of IUIDs for all manufactured items on this contract. Dates of manufacture, substitutions, shop changes, etc. shall be included on this list. The list shall be available for inspection by the PCO or other Government representative at any time during the life of this contract. The contractor shall provide this list to the government at the end of the contract.
Exhibit A SPRBL1-17-R-0030 Page 7 of 16
Correction of Noncompliant Equipment and Technical Data.
If this contract contains configuration control requirements, the contractor shall initiate the appropriate configuration control document to correct all affected drawings/specifications which conflict with or omit the marking requirements stipulated above.
If configuration control requirements do not apply and the equipment on order is defined by technical data which conflicts with or omits the marking requirements stated above, the contractor shall advise the PCO. Such advice shall list the number of each deficient drawing/specification and a brief description of the deficiency.
If the item on order is defined by existing Government technical documentation and such documentation is in conflict with the requirements of this SOW, production of equipment with revised markings shall not proceed until Government approval is received.
Government Purchase of Product/Technical Data.
Specifications. If the Government is procuring any equipment specification(s) on this contract, such specification(s) shall include a requirement to mark the appropriate items with IUID.
Drawings. If the Government is procuring engineering drawings or drawing revisions on this contract, the contractor shall include IUID marking requirements on each applicable drawing. Location shall be depicted on the pictorial and other details presented in the notes.
Pricing of IUID Requirements. All efforts required by this SOW and contract, including, but not limited to, the preparation of ECPs or notification of marking deficiencies, PIPC reporting, serial number data reporting at end of contract and the actual marking of hardware, will be included in the base contract price.
Requirements for Quality Assurance System. The contractor shall implement and maintain a Quality Assurance System for commercial items that meets or exceeds commercial best practices. These established commercial quality requirements shall be commonly accepted practices employed by industry in both national and international manufacturing environments. The contractor shall comply with the following requirements in addition to their best practice commercial quality assurance system.
Quality System. The contractor shall establish/maintain a system for the final inspection and test of all purchased items to comply with contract or order requirements.
Exhibit A SPRBL1-17-R-0030 Page 8 of 16
Inspection and Testing. The contractor shall perform final Inspection and testing on all deliverables in accordance with the contractor's Inspection and Testing Procedures. The contractor shall assure that all necessary inspections and tests are performed on completed products, and this shall include all inspections and tests, which are normally performed for the equipment on order. The contractor shall as a minimum perform any inspections and tests (including visual/mechanical inspections and functional tests) required to satisfy the form, fit, and function requirements of the contract. The form, fit, and function requirements are defined by the contractor’s drawings and literature (specification sheets, brochures, technical manuals, etc).
Records. The contractor shall maintain adequate records of inspections and tests to demonstrate that the final product satisfies contract requirements. The Government has the right to review these records at any time.
Measuring, Testing, and Inspection Equipment. The contractor shall provide and maintain gages (including production tooling used for inspection purposes) and other measuring and testing equipment to assure that finished products conform to contract requirements.
These devices shall be calibrated against certified measurement standards, which are traceable back to national/international standards.
Corrective Action. The contractor shall promptly act to correct nonconforming materials and conditions to satisfy contract or order requirements and prevent the recurrence of this problem.
Handling, Storage, Preservation, Packaging, and Shipping shall be in accordance with MIL-STD-2073-1. The Contractor shall establish, maintain, control and be responsible for the handling, storage, preservation, packaging and shipping to protect the quality of the materials and to prevent damage from loss, deterioration, degradation, or substitution of products.
Responsibility. The requirements of this Techical Requirements do not relieve the contractor of the responsibility to perform any additional tests or inspections required to assure product quality and compliance with drawings and specification requirements
Requirements for Warranty. The contractor shall provide a commercial “NO COST” warranty covering workmanship and materials for all items furnished in accordance with this contract or any modification thereof. The warranty shall be for a minimum of one year in duration. The contractor shall insure the item is date stamped and serialized to insure the beginning date of the warranty is known.
The contractor will also include within the packing, a note addressing the warranty and identifying the address of the facility that can provide detailed packing and shipping instructions in the event of a warranty claim. The contractor shall document by serial number each warranty claim in relation to the contractor’s configuration baseline.
Warranty Manual. The contractor shall provide an operational manual and/or an insert to accompany the material, describing the actions to be taken by the user in order to exercise the warranty and obtain repaired/replaced equipment.
Exhibit A SPRBL1-17-R-0030 Page 9 of 16
Warranty Procedures. Upon arrival at the contractors repair facility, both the contractor and Government representative will determine if failed item is covered under the warranty. There shall be no cost for items tested and found to be a "False Pull" or "No Evidence of Failure (NEOF)". The contractor shall meet a 30 day turn-around time for repair. This time shall be from the date of receipt by the contractor, to shipment from the contractor's facility. The Government shall be responsible for shipment from the warranty submitter’s location to the contractor’s facility and the contractor shall be responsible for transportation cost from the contractor’s facility to the CONUS warranty submitter’s location or a CONUS location of the Government’s choosing for OCONUS located warranty submissions.
Warranty Markings. Warranty markings shall be applied to unit, intermediate and shipping containers. The markings shall be in a conspicuous location to give notice that the item(s) are subject to warranty coverage. These markings shall indicate the time period or condition of the warranty (e.g., days/months, hours of operation, etc.).
Exhibit A SPRBL1-17-R-0030 Page 10 of 16
Obsolescence Reporting
N/A
Part Revisions
88-21005, REV L
88-21006, REV L
PACKAGING
Wood Packing Material
Wood packaging material (WPM) includes but is not limited to pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frame and cleats. This requirement excludes materials that have undergone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSB).
All WPM shall meet the requirements of International Standards for Phytosanitary Measures (ISPM) Number 15, “Guidelines for Regulating Wood Packaging Material in International Trade”. DoD shipments inside and outside of the United States shall meet the requirements of ISPM 15 whenever WPM is used to ship DoD cargo.
All WPM shall comply with the official quality control program for heat treatment (HT) or kiln dried heat treatment (KD HT) (IAW) American Lumber Standard Committee (ALSC), Incorporated, Wood Packaging Material Program and WPM Enforcement Regulations (see http://www.alsc.org/).
All WPM shall include certification/quality markings IAW the ALSC standard. Markings shall be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides of the pallet and be contrasting and clearly visible. All containers shall be marked on a side other than the top or bottom, contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ASLC approved DUNNAGE stamp.
Failure to comply with these requirements may result in refusal, destruction, or treatment of materials at the point of entry. The Government reserves the right to recoup from the contractor any remediation costs incurred by the Government.
Wood packing material includes pallets. See DLAD 52.247-9012 Requirements for Treatment of Wood Packaging Material (WPM).
Exhibit A SPRBL1-17-R-0030 Page 11 of 16
Military Packaging
Military Packaging in accordance with (MIL-STD-2073-1, AG00000601, etc.) is applicable.
DS7029 and/or DS7033 Preservation, Packing and Marking Instructions
DS7029 - DS7033 LEGEND
Qty Quantity Prot Req Protection Required PKG-REF Packaging Reference (Military/Federal Specification or Standard) SPI Special Packaging Instruction LPK Level of Packing QUP Quantity per Unit Pack ICQ Intermediate Container Quantity Pkg Reqmt Codes Packaging Requirement Codes when PKG-REF cites MIL-STD-2073 The below codes are for special markings:
PC Project Code WG Warranty/Guarantee SL Shelf Life BC Bar Code FMS Foreign Military Sales
Exhibit A SPRBL1-17-R-0030 Page 12 of 16
DS7029 - DS7033
NSN Prot Req PKG-REF or SPI LPK QUP ICQ Special Markings
Pkg J. J J J J J J J J J Reqmt I. II. III. IV. V. VI. VII. VII.a IX X Codes (MP) (CD) (PM) (WM) (CD) (CT) (UC) (IC) (PK) (SM) 6115-01-383-3124 Military AG00000606 B 001 - ZZ Z ZZ ZZ ZZ Z ZZ ZZ - - 6115-01-434-1432 Military AG00000606 B 001 - ZZ Z ZZ ZZ ZZ Z ZZ ZZ - -
Exhibit A SPRBL1-17-R-0030 Page 13 of 16
CONTRACT SECURITY REQUIREMENTS
AT-OPSEC Form Signed
In the event of a discrepancy between the signed DD 254 Contract Security Classification Specification, included as an attachment to the solicitaition/contract, and the language in this section, the signed DD 254 information shall take precedence.
c012741 Sticky Note Delete, there is no DD254
Exhibit A SPRBL1-17-R-0030 Page 14 of 16
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
CDRL List
CDRL
Data Line No. DID Identification Title A001 DI-MISC- 80711A Configuration Control B001 DI-MISC- 80711A IUID Marking Diagram/Instructions
Exhibit A SPRBL1-17-R-0030 Page 15 of 16
Individual CDRLs
CDRL A001
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
1003 A TDP X TM OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
AC Generators Used on 15 kW TQGs
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001 Scientific and Technical Reports Configuration Control
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A Technical Requirements Configuration Baseline
RDER-PRP-G INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
LT ASREQ SEE ITEM 16 b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
SEE ITEM 16
Reg
Repro
16. REMARKS:
Data Item Description DI-MISC-80711A: Delete Block 10 instructions entirely and follow instructions in SOW found in Technical Requirements Configuration Baseline.
The contractor shall prepare and submit Configuration Control Documents in accordance with the Technical Requirements section for Configuration Baseline when a change to or departure from a contractual baseline document is deemed necessary.
All deliveries shall be in digital format. All digital files shall be provided both by electronic submission, e.g., e-mail, FTP, etc., as arranged with the requiring office, and also by CD ROM readable by computers running Microsoft Office 2000 and Office XP suite of applications (MS Word, MS Excel, MS PowerPoint, and MS Project, etc.).
Alternative delivery media may be discussed with the Contracting Officer prior to delivery.
RDER-PRP-G
PCO
ACO
QAR
AMSEL-LC-LEO-E-ET
AMSEL-LC-LEO-E-AV*
* 1 COPY VECP ONLY.
15. TOTAL 0 6 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
PAUL PERIA
RDER-PRP-G
Mechanical Engineer
04 / 05 / 17 MARK L. CARINGI
RDER-PRP-G
Chief, Generator Branch
03 / 24 / 17
DD Form 1423-1, 1 Jun 90
Exhibit A SPRBL1-17-R-0030 Page 16 of 16
CDRL B001
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
1003 A TDP TM OTHER MISC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
AC Generators Used on 15 kW TQGs
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
B001 Scientific and Technical Reports IUID Marking Diagram/Instructions
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A Technical Requirements RDER-PRP-G INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
LT ASREQ SEE ITEM 16 b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
N/A SEE ITEM 16
Reg
Repro
16. REMARKS:
Item 4: Delete Block 10.2 of Data Item Description (DID) and prepare in accordance with this CDRL & the Technical Requirements.
Item 12: Delivery of draft shall be 120 DAC. Government has 30 days to review/comment.
Item 13 Delivery of final shall be 30 days after receipt of Government comments. Government has 60 days to determine acceptance.
Contractor to submit DD250 upon acceptance of UID Marking Diagram/Instructions.
Item 14: All digital files will be provided both by electronic submission, e.g., e-mail, FTP, etc., as arranged with the requiring office, and also by CD ROM, readable by computers running Microsoft Windows.
RDER-PRP-G
PCO
ACO
QAR
AMSEL-LC-LEO-E-ET
AMSEL-LC-LEO-E-AV
15. TOTAL 0 5 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
PAUL PERIA
RDER-PRP-G
Mechanical Engineer
04 / 05 / 17 MARK L. CARINGI
RDER-PRP-G
Chief, Generator Branch
03 / 24 / 17
DD Form 1423-1, 1 Jun 90
| APPLICABLE DOCUMENTS |
| CONFIGURATION BASELINE |
| Configuration. Each CI/CSCI, as developed/built and delivered, shall conform to the cited CB and (if applicable) all subsequent CB’s that will be made contractually binding by the Procuring Contracting Officer (PCO). Configuration changes not direct... |
| Obsolescence Reporting |
| Part Revisions |
| PACKAGING |
| Wood Packing Material |
| Military Packaging |
| CONTRACT SECURITY REQUIREMENTS |
| CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1 |
| CDRL List |
| Individual CDRLs |
| CDRL B001 |