- Solicitation number
- SPRBL1-16-R-0033
About this file
Contract Data Requirement List
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 0002 – SPRL1-16-R-0033
DD Form 1423, JUN 90 (REVERSE) (EF)
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoD 5010.12-M for detailed instructions)
FOR GOVERNMENT PERSONNEL FOR THE CONTRACTOR
ITEM A. Self-explanatory.
ITEM B. Self-explanatory.
ITEM C. Mark (X) appropriate category: TDP - Technical Data Package;
TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management", etc.
ITEM D. Enter name of system/item being acquired that data will support.
ITEM E. Self-explanatory (to be filled in after contract award).
ITEM F. Self-explanatory (to be filled in after contract award).
ITEM G. Signature of preparer of CDRL.
ITEM H. Date CDRL was prepared.
ITEM I. Signature of CDRL approving authority.
ITEM 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.
ITEM 2. Enter title as it appears on data acquisition document cited in
Item 4.
ITEM 3. Enter subtitle of data item for further definition of data item
(optional entry).
ITEM 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12- L (AMSDL), or one-time DID number, that defines data content and format requirements.
ITEM 5. Enter reference to tasking in contract that generated requirement for the data item (e.g., Statement of Work paragraph number).
ITEM 6. Enter technical office responsible for ensuring adequacy of the data item.
ITEM 7. Specify requirement for inspection/acceptance of the data item by the Government.
ITEM 8. Specify the requirement for approval of a draft before preparation of the final data item.
ITEM 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DODD 5230.24
ITEM 10. Specify number of times data items are to be delivered.
ITEM 11. Specify as-of date of data item, when applicable.
ITEM 12. Specify when first submittal is required.
ITEM 13. Specify when subsequent submittals are required, when applicable.
ITEM 14. Enter addresses and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
ITEM 15. Enter total number of draft/final copies to be delivered.
ITEM 16. Use for additional/clarifying information for Items 1 through
15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
ITEM 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort by the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data items to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data items to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying this data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
ITEM 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data. These estimated data prices should be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data.
The Government's right to use the data shall be governed by the pertinent provisions of the contract.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP X TM OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
DVE Spares
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
Scientific and Technical Reports Configuration Control
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A SOW Para 3.1.3 RDER-PRI-NR
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION IN
LT
ASREQ SEE ITEM 16
b. COPIES
SECT. B
8. APP CODE
N/A
11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
SEE ITEM 16
Reg
Repro
16. REMARKS:
: Data Item Description DI-MISC-80711A: Delete block 10 instructions entirely and follow instructions in SOW 3.1.5
The contractor shall prepare and submit Configuration Control
Documents in accordance with the SOW section for Configuration
Control (Para 3.1) when a change to or departure from a contractual baseline document is deemed necessary.
Data shall be submitted and exchanged electronically in Microsoft
Office suite of applications (MS Word, Excel, Power Point, Access, and Project). Alternate formats may be allowed subject to
Government review and approval.
If the CDRL Data Deliverable is NSP (Not Separately Priced), then an electronic DD Form 250 will be required via the Wide
Area Workflow website in order for the contractor to receive payment for the data deliverable (see section G of the Contract).
E-mail notification is required with any electronic submission.
RDER-PRI-NR
PCO
ACO
QAR
15. TOTAL 0 4 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Van Nguyen, PRD
Engineer, 443-861-3028
01/28/2016 Michael Heussner
Branch Chief, 443-861-3473
01/28/2016
DD Form 1423-1, 1 Jun 90
Original Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Advise Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork
Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block
E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER MISC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
DVE Spares Contract
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
Scientific and Technical Reports IUID Marking
Diagram/Instructions
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MISC-80711A
(SEE BLOCK 16)
SOW PARA. 3.3.2.3 RDER-PRI-NR
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
IN
ASREQ see item 16
SECT. B
8. APP CODE
N/A
11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
N/A see item 16
Item 4: Delete Block 10.2 of Data Item Description (DID) and prepare in accordance with this CDRL & the Statement of Work.
Item 12: Delivery of draft shall be 120 DAC award. Government has 30 days to review/comment.
Item 13: Delivery of final shall be 30 days after receipt of
Government comments. Government has 60 days to determine acceptance. Contractor to submit DD250 upon acceptance of IUID
Marking Diagram/Instructions.
Item 14:
All digital files will be provided both by electronic submission, e.g., e-mail, FTP, etc., as arranged with the requiring office, and also by
CD ROM, readable by computers running Microsoft Windows.
RDER-PRI-NR 1
15. TOTAL 1 1 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Van Nguyen, PRD
Engineer, 443-861-3028
01/28/2016 Michael Heussner
Branch Chief, 443-861-3473
Based upon DD Form 1423-1, 1 Jun 90
Original Form Approved
Based upon DD Form 1423-1, 1 Jun 90
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Advise Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork
Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block
E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER SESS
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
DVE Spares
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
Source Data for Forecasting
Diminishing Manufacturing Sources and Material Shortages (DMSMS)
DMSMS Data
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-81656
SOW PARA. 3.5 RDER-PRI-NR
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
IN
ASREQ see item 16
SECT. B
8. APP CODE
N/A
11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE see item 16 see item 16
Item 12: Delivery of DMSMS data shall be as required.
Government has 60 days to review and determine acceptance.
See DI-SESS-81656 for DMSMS Data format and content requirements. Contractor to submit DD250 upon acceptance of
DMSMS Data.
RDER-PRI-NR
CECOM LRC
PCO
Data shall be submitted and exchanged electronically in Microsoft
Office applications (MS Word, Excel, Power Point, Access, and
Project). Alternate formats may be allowed subject to Government review and approval.
15. TOTAL 2 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Van Nguyen, PRD
Engineer, 443-861-2844
01/28/2016 Michael Heussner
Branch Chief, 443-861-3473
File details come from the government source that posted it. Updated .