Specs_-_Reconstruction_and_Resurfacing_of_Portions_of_Certain_County_Roads,_Contract_2022A.pdf
PDF 1001 KB Posted
- Attached to
- Reconstruction and Resurfacing of Portions of Certain County Roads, Contract 2022A, Various Townships
- Solicitation number
- 00-907-1128
- Issued by
- Ocean County, New Jersey
About this file
This document is a comprehensive bid specification for the Ocean County Department of Transportation in New Jersey for the Reconstruction and Resurfacing of Portions of Certain County Roads, Contract 2022A. The project involves milling and resurfacing approximately 8.4 miles of roads in Jackson and Toms River Townships, with a total contract duration of 180 calendar days. Key work elements include replacing corrugated metal pipes with reinforced concrete or ductile iron pipes, reconstructing concrete curbs, sidewalks, and ADA curb ramps, upgrading beam guide rail and end terminals, and modifying five signalized intersections to meet current MUTCD standards. The project also involves installing pedestrian signal assemblies, countdown heads, and additional traffic signal heads to upgrade existing pedestrian facilities and traffic signal infrastructure.
The contract is wholly state-funded with a competitive bidding process, and bidders must comply with New Jersey's Small Business Enterprise (SBE) and Equal Employment Opportunity requirements. While no specific SBE subcontracting goals are set for this project, contractors must demonstrate good faith efforts in workforce diversity and employment practices. The bid documents specify detailed technical specifications, including materials requirements, construction methods, electrical work, and traffic signal installations. Contractors will be subject to prevailing wage rate requirements, and the project includes provisions for potential price adjustments for fuel and asphalt. The contract will be awarded to the lowest responsible bidder whose proposal conforms to all specifications, with the county reserving the right to reject all bids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1
RECONSTRUCTION AND RESURFACING OF PORTIONS OF CERTAIN COUNTY ROADS,
CONTRACT 2022A, VARIOUS TOWNSHIPS
State of New Jersey Department of Transportation
Special Provisions For
State Aid Projects
FY 2019 Edition Revision 26: October 2023
Sheet 2
SUPPLEMENTARY SPECIFICATIONS
AUTHORIZATION OF CONTRACT
The Contract for this project is authorized by the provisions of local public contracts law, N.J.S.A. 40A:11-1 et seq.
INSTRUCTIONS TO BIDDERS
This Contract shall comply strictly with all the requirements of the New Jersey Department of Transportation Standard Specifications for Road and Bridge Construction for 2019, including all Baseline Document Changes, except as amended, modified or supplemented herein and which Specifications are made part of these Supplementary Specifications. The New Jersey Department of Transportation Standard Construction Details shall govern except insofar as same are modified or changed in detail drawings prepared especially for this particular Project.
Baseline Document Change (BDC) Announcements are notices that a Baseline Document has been modified in part or in whole. A Baseline document is defined as any official document that has gone through an initial approval process and was approved for use as intended. Thus a BDC is an alteration to or rewriting of any officially approved document.
New documents are also announced with a BDC. For additional BDC’s to the 2019 specs that are not covered in this document: http://www.state.nj.us/transportation/eng/documents/BDC/.
MINIMUM WAGE RATES
The minimum wage rates for labor employed on this Contract shall be as specified in the "Prevailing Wage Rate Determination" of the New Jersey Department of Labor and Workforce Development which is in effect on the date the Project is awarded.
The Contractor is put on notice that he must pay workmen the prevailing wage rate promulgated by the New Jersey Department of Labor and Workforce Development for this Project, copies of which are on file in the Ocean County Engineer's Office and which will be updated to the date of award and will be made a part of this Contract, pursuant to N.J.S.A.34:11:-56.25 et seq.
State wage rates may be obtained from the New Jersey Department of Labor & Workforce Development (Telephone: 609-292-2259) or by accessing the Department of Labor & Workforce Development’s website at https://www.nj.gov/labor/wagehour/wagerate/prevailing_wage_determinations.html. The State wage rates in effect at the time of award are part of this Contract, pursuant to Chapter 150, Laws of 1963 (N.J.S.A. 34:11-56.25 et seq.).
In the event it is found that any workman employed by the Contractor, or any Subcontractor covered by the Contract, has been paid a rate of wages less than the prevailing wage required to be paid by the Contract, the County may terminate the Contractor's or Subcontractor's right to proceed with the work, or such part of the work as to which there has been a failure to pay required wages and to prosecute the work to completion or otherwise. The Contractor and his Sureties shall be liable to the County for any excess costs occasioned thereby.
GENERAL
All awards shall be made subject to the approval of the New Jersey Department of Transportation. No construction shall start before approval of said award by the New Jersey Department of Transportation. Prior to the start of construction, the Contractor must submit a Material Questionnaire (SA-11) listing all sources of materials. Any materials used on the project from a non-approved New Jersey Department of Transportation source will be considered non-participating. The Contractor is also notified that the District Office, Division of Local Government Services and Economic Development, must be notified of the construction commencement date at least five (5) calendar days prior to the start of construction.
https://www.nj.gov/labor/wagehour/wagerate/prevailing_wage_determinations.html
Sheet 3
Award of contract and subletting will not be permitted to, materials will not be permitted from, and use of equipment will not be permitted that is owned and/or operated by, firms and individuals included in the report of suspensions, debarments and disqualifications of firms and individuals as maintained by the Department of the Treasury, Division of Purchase & Property, Contract Compliance & Administration, Trenton NJ 08625 (609-292-5400).
Payment for a pay item in the proposal includes all the compensation that will be made for the work of that item as described in the contract documents unless the "Measurement and Payment" clause provides that certain work essential to that item will be paid for under another pay item.
Whenever any Section, Subsection, Subpart or Subheading is amended by such terms as changed to, deleted or added, it is construed to mean that it amends that Section, Subsection, Subpart or Subheading of the 2019 Standard Specifications unless otherwise noted.
Whenever reference to page number is made, it is construed to refer to the 2019 Standard Specifications unless otherwise noted.
Henceforth in this supplementary specification whenever reference to the State, Commissioner, Department, Engineer or Inspector is made, it is construed to mean the particular municipality or County executing this contract.
Whenever reference to Title 27 is made, it is construed to mean Title 40.
The following information is located at the end of these Special Provisions:
1. Small Business Enterprise Utilization on Wholly State Funded Projects. (State Funded Project Attachment 1)
2. State of New Jersey Equal Employment Opportunity Special Provisions for Wholly State Funded Projects.
(State Funded Project Attachment 2)
3. Requirements for Affirmative Action to Ensure Equal Employment Opportunity on Wholly State Funded Projects. (State Funded Project Attachment 3)
4. Investigating, Reporting and Resolving Employment Discrimination and Sexual Harassment Complaints on Wholly State Funded Projects. (State Funded Project Attachment 4)
5. Payroll Requirements for Wholly State Funded Projects. (State Funded Project Attachment 5)
6. Americans with Disabilities Act Requirements for Wholly State Funded Contracts. (State Funded Project
Attachment 6)
Materials or assemblies as specified will be accepted on the basis of certificates of compliance stating that such materials or assemblies fully comply with the requirements of the Contract.
Materials or assemblies used on the basis of certificates of compliance may be sampled and tested at any time and if found not to be in conformity with the contract requirements, will be subject to rejection whether in place or not. The Contractor shall require the manufacturer or supplier to furnish three copies of certificates of compliance with each delivery of materials, components and manufactured items that are acceptable by certification. One copy shall be furnished to the Engineer, one copy shall be furnished to the District Office Division of Local Government Services and Economic Development and one copy shall be retained by the Contractor.
Certificates of compliance shall contain the following information:
Project and location to which the material is consigned.
Name of the Contractor to which the material is supplied.
Kind of material supplied.
Quantity of material represented by the certificate.
Means of identifying the consignment, such as label marking, seal number, etc.
http://www.state.nj.us/transportation/eng/specs/SP/doc/EEOSpecialProvisionsState.rtf http://www.state.nj.us/transportation/eng/specs/SP/doc/PayrollRequirements.rtf http://www.state.nj.us/transportation/eng/specs/SP/doc/AmericansWithDisabilities.rtf
Sheet 4
Date and method of shipment.
Statement that the material has been tested and found in conformity with the pertinent contract requirements stated in the certificate.
Signature of a person having legal authority to bind the supplier.
Signature attested to by a notary public or other properly authorized person.
Payments relative to materials supplied to be accepted on the basis of certificates of compliance shall not be made until the Engineer has in his possession an acceptable certificate of compliance.
DIVISION 100 - GENERAL PROVISIONS
SECTION 101 - GENERAL INFORMATION
101.01 Introduction.
The following is added:
Pursuant to N.J.S.A. 27:1B-21.6, the Department intends to enter into a contract for the advancement of the Project.
However, sufficient funds for the Project may not have been appropriated, and only amounts appropriated by law may be expended. Payment under the Contract is restricted to the amounts appropriated for a fiscal year (FY).
Governing bodies have no legal obligation to make such an appropriation. There is no guarantee that additional funds will be appropriated. Failure by governing bodies to appropriate additional funds will not constitute a default under, or a breach of, the Contract. However, if the Department terminates the Contract or suspends work because funds have not been appropriated, the parties to the Contract will retain their rights for suspension and termination as provided in 108.13, 108.14, and 108.15; except as indicated below.
Do not expend or cause to be expended any sum in excess of the amount allocated in the current fiscal year's Capital Program (as specified below). The Department will notify the Contractor when additional funding has been appropriated. Any expenditure by the Contractor which exceeds the amount appropriated is at the Contractor's risk and the Contractor waives its right to recover costs in excess of that appropriated amount.
101.03 Terms.
All references to "Commissioner", "Department" or "State" shall be interpreted to mean "County". All references to "Engineer" or “ME” shall be interpreted to mean "County Engineer".
The following term is added:
Full Traffic Access. All work is complete to allow safe unencumbered use of the final paved portion of roadway throughout the project including but not limited to striping, RPMs, rumble strips, highway lighting, and traffic signals as determined by the RE.
The following is omitted:
Federal Aid Project. Any agreement or modification thereof between NJDOT and any applicant and a person for construction work which is paid for in whole or in part with funds obtained from the Federal government or borrowed on the credit of the Federal government pursuant to any program involving a grant, contract, loan, insurance or guarantee under which the NJDOT itself participates in the construction work.
Federal Aid Project Attachments. Attachments to the Contract Special Provision document, used for Federal Aid Projects.
Sheet 5
Add the following term:
Wholly State Funded Project: Any agreement, contract or modification thereof between local public agencies and a person for construction work which is paid for in whole or in part with funds obtained from the State government or borrowed on the credit of the State government pursuant to any program involving a grant agreement, contract, loan, insurance or guarantee. This term excludes any agreement, contract or modification for construction work which is paid for in whole or in part with funds obtained from the Federal government.
Revise the following term:
actual cost: The computed cost using calculations of direct labor, labor fringe benefits, indirect labor costs, insurance, materials, extraordinary expenses, equipment, profit, overhead, and subcontractors.
101.04 Inquiries Regarding the Project.
Inquiries prior to bids in accordance with this Subsection shall be addressed to: Gary Leemann, Ocean County Engineering Department, 129 Hooper Ave., PO Box 2191, Toms River, NJ 08754, Telephone: 732-929-2130.
Inquiries after award of contract shall be addressed to: Local Aid District 3 Office, Deval Desai, Senior Executive Service , 1035 Parkway Avenue, PO Box 600, Trenton, NJ 08625, Telephone: 609-963-2020.
SECTION 102 - BIDDING REQUIREMENTS AND CONDITIONS
102.01 Qualification to Bid.
The requirements of this Subsection of the Standard Specifications are hereby deleted.
102.02 Bidder Registration and Downloading of the Proposal Documents.
The requirements of this Subsection of the Standard Specifications are hereby deleted.
102.03 Revisions Before Submitting a Bid.
The requirements of this Subsection of the Standard Specifications are hereby deleted and the following substituted therefor:
In accordance with N.J.S.A. 40A:11-23(c)(2), the County will only issue written or graphic information to clarify, correct or change the Proposal documents, contract or bidding notices as addenda. The Bidder shall acknowledge all addenda before the opening of bids. The County will not accept the bid if the Bidder has not acknowledged all addenda.
Certain addenda contain amendments. Amendments require revisions to the schedule of items to be bid, in which case the County will include with the addenda a revised schedule of quantities. This revised schedule sheet MUST be used in the bid. The County has the right to reject any bid not using this revised schedule of quantities.
102.04 Examination of Contract and Project Limits.
The following is added to this Subsection of the Standard Specifications:
(1) Evaluation of Subsurface and Surface Conditions.
There are no boring logs or pavement cores for this project.
Sheet 6
102.07 Preparation of the Bid.
The bid is the completed Proposal documents that are submitted electronically by the Bidder to the County at the time for the opening of bids, as stipulated in the Notice to Bidders. The Bidder must submit a bid electronically through the County’s OpenGov Electronic Bid Portal. Please do not submit a paper bid submission. Paper bid submissions and/or multiple submissions will be cause for rejection. The Bidder shall include all addenda in the bid. The Bidder shall specify a price in numerals for each Item. The Bidder shall insert the price in the box provided for the lump sum Item under the column designated as “Unit Cost.” For unit price Items, the Bidder shall insert the per unit price under the column designated “Unit Cost” in the appropriate box at the location provided therefore. When the Bidder intends to bid zero ($0.00) for an Item, the Bidder shall insert a “0” in the “Unit Cost” column for unit price Items.
When the Proposal contains alternate Items, the Bidder shall insert only the unit price and amount for the lowest priced alternate Item. When alternate Items in the Proposal have a lump sum pay quantity, the Bidder shall insert only the amount for the lowest priced alternate Item. The Bidder shall construct the alternate Item for which a price has been provided. When the Proposal contains groups of alternate Items, the Bidder shall insert only the unit price and amount for each Item within the lowest priced alternate group. The Bidder shall construct the alternate group of Items for which a price has been provided.
The only entries permitted in the bid are the unit or lump sum prices for Items to be bid. The software will perform all extensions of the unit or lump sum prices and calculate the total bid amounts.
The last two paragraphs of this section are omitted.
102.09 Proposal Bond.
The second paragraph of this Subsection of the Standard Specifications is hereby deleted and replaced by the following:
The proposal when submitted shall be accompanied by a guarantee in the amount of not less than ten percent (10%) of the total sum bid, provided such guarantee shall be for no more than twenty thousand ($20,000.00) dollars. The guarantee may be in one of the following three forms: cashier’s check, certified check or Proposal Bond. The guarantee shall be payable to the County of Ocean. In the event that a cashier’s check or certified check is used, evidence of ability to furnish a Performance Bond and a Payment Bond in accordance with Subsection 151.03.01 must also accompany each bid.
102.10 Submission of Bids.
The first paragraph of this Subsection of the Standard Specifications is hereby deleted.
The seventh paragraph of this Subsection of the Standard Specifications is hereby deleted.
102.13.01 Bidder Pre-Award Requirements.
A. Federal Aid Projects
This Section intentionally left blank.
SECTION 103 - AWARD AND EXECUTION OF CONTRACT
103.01 Award of Contract.
The first paragraph of this Subsection of the Standard Specifications is changed to read as follows:
Sheet 7
The Award of Contract, if it be awarded, will be to the lowest responsible bidder whose Proposal conforms in all respects to the requirements set forth in the Contract Documents. The County will award the Contract or reject all bids within 60 days after the bids are received. When the County cannot make an unconditional award, this time limit may be extended by mutual agreement for one 30-day interval.
103.05.A Escrow Bid Documents.
Revise Section 103.05.A to the following:
A. Purpose. The bid documents are the supporting information, calculations, quotes, and other information used to prepare the bid. The Department may use the Contractor’s bid documents to negotiate changes and claims if they are escrowed and a signed custody agreement is provided. The information contained in the bid documents does not modify the terms and conditions of the Contract. If the Contractor fails to escrow bid documents within the time specified in 103.04, the Department will not make payment for a disproportionate allocation of costs for work for which no Item is provided in the Contract, as specified in 102.08, in the renegotiation of costs of Items when there is a major decrease in quantity.
SECTION 104 - SCOPE OF WORK
104.01 Intent.
The following is added to this Subsection of the Standard Specifications:
The work to be performed under this Contract consists of the milling and resurfacing of 8.4 miles of roads in the Townships of Jackson and Toms River. Included in this Contract is the replacement of Corrugated Metal Pipe using Reinforced Concrete Pipe or Ductile Iron Pipe; the reconstruction of concrete curb, concrete sidewalk, and ADA curb ramps; upgrading Beam Guide Rail and End Terminals; and the installation of detectable warning surfaces, curb pieces, bicycle safe grates, and traffic stripes and markings. Five (5) signalized intersections will also be modified as part of this Contract. This work includes upgrading the existing pedestrian facilities to current ADA standards and modifying the existing traffic signals to meet current MUTCD standards. The various locations involve the installation of pedestrian signal assemblies, countdown heads, and additional traffic signal heads.
104.03.03 Types of Changes.
3. Changes in the Character of Work.
The following is added to this Subsection of the Standard Specifications:
The provisions set forth in N.J.S.A. 40A:11-16.7 shall be deemed a part of this Contract.
104.03.09 Delay Damages.
This entire Subsection of the Standard Specifications is hereby deleted.
SECTION 105 - CONTROL OF WORK
105.01 Authority of the Department.
105.01.01 RE.
Revise the second paragraph to:
Sheet 8
Unless otherwise specified, send correspondence with the Department to the RE. Where correspondence is specified to be directed to persons other than the RE, send a copy to the RE. Ensure that correspondence complies with the following:
1. Assign every correspondence sent to the Department a unique correspondence serial number in the subject line, numbered sequentially beginning with Contractor Correspondence No. 1.
2. If the correspondence includes a request for information or asks for an interpretation of the Contract, also assign a unique RFI serial number in the subject line numbered sequentially beginning with RFI-1.
3. If the correspondence constitutes a notice of change, assign a unique change notice serial number in the subject line numbered sequentially beginning with Change Notice No. 1. For subsequent correspondence referring to a change notice or to the events that are the subject of a previous change notice, refer in the subject line to the original change notice number.
105.01.02 Inspection.
The first sentence of this Subsection of the Standard Specifications is changed to read as follows:
Inspectors employed by the County are authorized by the Engineer to inspect all work done and materials furnished.
The following is added to this Subsection of the Standard Specifications:
Inspection services will be provided by the County Engineer.
105.02 Responsibilities of the Contractor.
105.02.05 Civil Rights Requirements.
Revise Section 105.02.05.1 to the following :
1. Federal Aid projects. This Section intentionally left blank.
Revise the first line of Section 105.02.05.2 to the following:
2. Wholly State Funded Contracts. When applicable for wholly State Funded contracts under the jurisdiction of New Jersey Statutes N.J.S.A. 10:5-31 et seq., State EEO regulations and goals apply as specified in State Funded Project Attachments 1 to 6 of the Special Provisions.
105.03 Conformity with the Contract.
Revise the first sentence of the first paragraph to:
In the event the Contractor discovers a discrepancy, error, omission, or ambiguity in the Contract, or if the Contractor has any doubt or question as to the intent or meaning of the Contract, the Contractor must immediately notify the RE.
Revise the fourth sentence of the sixth paragraph to:
If the Department loses funding for the nonconforming work, on the basis of permitting nonconforming work to remain, the Department will not pay for the work permitted to remain in place.
105.04 Plans and Specifications.
Sheet 9
Copies of the Standard Specifications and Baseline Document Changes may be obtained from the New Jersey Department of Transportation.
105.05 Working Drawings.
The third sentence of the third paragraph of this Subsection of the Standard Specifications is hereby deleted and the following substituted therefor:
The Contractor shall submit to the County Engineer two (2) sets of complete and fully detailed shop or working drawings required for carrying out the Project in accordance with procedures prescribed in this Subsection of the Standard Specifications. One set will be returned to the Contractor and one set will be kept as a record copy in the office of the County Engineer.
The following is added to this Subsection of the Standard Specifications:
The ninth paragraph is changed to:
Submit working drawings for certification or approval as specified in Table 105.05-1. This list is not all inclusive.
Ensure that the working drawings submitted for approval are signed and include an embossed seal by a Professional Engineer. The working drawings submitted for certification are not required to be signed and sealed by a Professional Engineer unless they alter the original Contract.
105.07 Cooperation with Utilities.
The following is added to this Subsection of the Standard Specifications following 105.07.01A. Initial Notice:
The corporations, companies, agencies or municipalities owning or controlling the utilities are listed below:
GAS MAINS:
New Jersey Natural Gas Co.
Attn: Marc Panaccione, Managing Engineer Distribution Engineering 1415 Wyckoff Road, P.O. Box 1464 Wall, NJ 07719 Telephone: (732) 919-8140
UTILITY POLES AND/OR UNDERGROUND CABLES:
Jersey Central Power & Light Co.
Attn: Harvey Lockley 101 Crawford's Corner Road, Bldg. #1, Suite 1-511 Holmdel, NJ 07733 Telephone: 732-212-4262
Verizon Engineering Attn: Arturo Cabrera 999 West Main Street Freehold, NJ 07728 Telephone: 732-683-5124
Sheet 10
Verizon Business Group (MCI) Attn: John Alessandrini 630 Clark Ave King of Prussia, PA 19406 Telephone: 610-517-8456
Verizon Business Group (MCI) Attn: Nahed Shahata 355 First Ave Staten Island, NY 10301 Telephone: 646-529-0572
A.T. & T.
Attn: Louis Marello Cable Protection Center Engineering Inquiries 400 Hamilton Avenue, Mail Room White Plains, NY 10601 Telephone: 914-467-1097
AT&T
Cable Protection Carlo Verdi, Local Engineer Engineering Inquiries 2315 Salem Road Wall Street - Building #3 Conyers, GA 30013 Telephone: (732) 610-9598
Sprint Nextel Attn: Mike Brown 484 Williamsport Pike, Box 113 Martinsburg, WV 25404 Telephone: 304-267-2384
CATV:
Comcast Cable Attn: Ralph Giampaolo Construction Coordinator, Ocean County 901 West Leeds Avenue Pleasantville, NJ 08232 Telephone: (856) 229-6115
Comcast Cable Attn: Bob Mayeux Construction Coordinator, Ocean County 901 West Leeds Avenue Pleasantville, NJ 08232 Telephone: 609-680-1069
Sheet 11
Altice Tech Services USA - Cablevision Attn: John McCallum 40 Pine Street Tinton Falls, NJ 07753 Telephone: (732) 496-0340
WATER AND/OR SEWER MAINS:
Ocean County Utilities Authority Attn: Robert McGlaughlin 501 Hickory Lane - P.O. Box P Bayville, NJ 08721 Telephone: 732-269-4500
BASF Corporation Attn: Mr. Fred Goelz 227 Oak Ridge Parkway Toms River, NJ 08755 Telephone: 732-245-5267
Veolia North America Attn.: Ivonne Wojtowicz 1451 Route 37 West, Suite 2 Toms River, NJ 08753 Telephone: (732) 557-7788
Jackson Township M.U.A.
Attn: Mr. Earl Quijano 135 Manhattan Street Jackson, NJ 08527 Telephone: 732-928-2222
Toms River Township M.U.A.
Attn: Nicholas Otten, PE 340 W. Water Street Toms River, NJ 08753 Telephone: 732-240-3500
Bidders are advised to verify the above information as its accuracy and completeness is not guaranteed by the County.
Water lines, gas lines, wire lines, service connections, water and gas meter boxes, water and gas valve boxes, utility manholes, light standards, cableways, signals, railroad lines and all other utility appurtenances within the limits of the project which are to be relocated or adjusted are to be moved by the owners at their expense, except as otherwise provided for in the Supplemental Specifications or as noted on the Plans.
105.07.01 Working in the Vicinity of Utilities.
B. Locating Existing Facilities.
2. Fiber Optic Markout Form is available at:
http://www.state.nj.us/transportation/eng/elec/ITS/requests.shtm.
http://www.state.nj.us/transportation/eng/elec/ITS/requests.shtm
Sheet 12
Bureau of Traffic Operations, South Region (TOCS) 1 Executive Campus-Route 70 West Cherry Hill, NJ 08002-4106 Telephone: 856-486-6650
For Weigh-in-Motion and Traffic Volume systems contact:
Transportation Data and Safety Unit PO Box 600 Trenton, NJ 08625 609-963-1891
For Roadway Weather Information Systems contact:
Permits, Electrical Maintenance & Claims Unit PO Box 600
609-963-1829
3. NJDOT
Central Region Electrical 1035 Parkway Avenue 4th Floor E&O Bldg.
CN 600
Telephone: 609-963-1491
105.07.02 Work Performed by Utilities.
Whenever utility services are encountered in which the private property owner also directly owns the utility service, said utility service shall be relocated by the Contractor. Separate payment will not be made for this relocation but all such costs shall be included in the unit prices bid for the various items of the Contract as listed in the Proposal.
Whenever the temporary relocation or temporary support of public or private facilities is necessitated in order to complete the Project, all such temporary relocation or temporary support costs shall be borne by the Contractor.
When water, sewer and gas house connections, boxes, cleanouts and valves must be relocated or replaced to carry out this Project, the cost of such work shall be included in the prices bid for the various pay items.
The Contractor will be required to coordinate with the utility companies during all stages of the project. Specifically, but not limited to, at the beginning of the project for the relocation of the poles, during construction for the resetting and/or reconstruction of manholes, water valves and fire hydrants. The Contractor is responsible for all damage done to the utilities due to his work or any subconsultant’s work.
General Notes
1. The Contractor shall provide the utility companies with the notices called for in the schedules.
2. The Contractor shall provide the utility companies with survey control and prior to the installation of company facilities, the Contractor and companies shall jointly verify the location.
Sheet 13
3. Schedules contained herein are estimated time frames only and are to be verified by the Contractor.
4. Schedules are estimated and may change in accordance with field conditions.
5. Revisions to staging of construction may alter these schedules.
6. Where joint facilities are proposed, the Contractor shall coordinate work with the affected companies.
7. Utilities sharing joint poles shall commence work as soon as the poles are available for each of the individual company disciplines.
8. Utilities can perform their work only after the Contractor has completed its clearing and grading of site as necessary.
9. All distances, stations, offsets and lengths are approximate (plus or minus).
10. Existing facilities can be removed only after relocated facilities have been installed and are in operation.
11. Work performed by the Contractor noted herein is part of the County’s overall operation and is included in the County project plans and specifications.
12. The Contractor shall provide field layout for horizontal and vertical location of proposed curb or edge of pavement and limits of disturbance.
13. The Contractor shall coordinate field meetings with all utilities to verify the field layout and to verify the limits of clearing to be provided for all utility relocation. Any remobilization required to correct clearing for utility relocation will be done at the Contractor’s sole expense. Clearing site includes clearing for installation of poles, anchors, cables and appurtenances and providing necessary access for utility relocation including guide rail opening and grading as required to place new or relocated facilities.
14. The Contractor shall coordinate with the utilities to establish the location of all test pits necessary to determine conflicts. The Contractor shall perform all test pits to the satisfaction of the utility companies and the County Engineer. Traffic control for test pits is to be provided by the Contractor.
15. The Contractor shall provide the aerial utility companies with thirty (30) days notice and allow in his schedule a minimum of ninety (90) days to complete aerial relocation for each stage of construction.
16. The Contractor may not start construction within the travel way until all aerial utility relocations have been completed in a particular stage.
17. The Contractor shall provide buried utility companies with thirty (30) days notice and shall thereafter coordinate his operation with the utility schedules. The Contractor shall provide traffic control/lane closures coordination that accommodates the various utility relocations, resets and adjustments.
18. No separate measurement or payment will be made for any and all coordination and traffic control with the various utility companies.
19. The Contractor’s schedule shall anticipate the minimum lead times estimated herein above or the stated time frames provided by the respective utility companies, whichever is greater.
The Contractor shall lay out all the work to be done by the utility companies using the baselines he has established.
This shall include, but not be limited to: offset stakes or hubs to establish proposed utility pole locations and cut sheets for resetting or relocation of existing utility structures. The Contractor shall also include the following when collecting test pit information: station and offset to the baseline, elevation at the top of the utility (when multiple conduits are encountered, the bottom elevation shall be included), and material, type and size of the utility encountered.
The Contractor shall be responsible for verifying which utility poles need to be relocated. If utility poles need to be reset due to Contractor error, he shall be responsible for any charges assessed by the utility companies.
105.08 Environmental Protection.
The requirements of this Subsection shall also apply to lands regulated by the New Jersey Pinelands Commission.
No separate payment will be made for this work.
Sheet 14
TEMPORARY PROJECT WATER POLLUTION CONTROL (SOIL EROSION)
PRECONSTRUCTION CONFERENCE.
At the Preconstruction Conference or prior to the start of the applicable construction, the Contractor shall submit for acceptance his schedules for accomplishment of temporary and permanent erosion control work, as are applicable for clearing and grubbing; grading; bridges and other structures at watercourses; construction; and paving. He shall also submit for acceptance his proposed method of erosion control on haul roads and borrow pits and his plan for disposal of waste materials. No work shall be started until the erosion schedules and methods of operations have been accepted by the Engineer.
105.11 Construction Layout.
The following is added to this Subsection of the Standard Specifications:
The Contractor is responsible for laying out Horizontal and Vertical control and checking survey benchmarks before the start of construction. Any discrepancies in survey benchmarks, layout control, or plan grades shall be brought to the attention of the Engineer seventy-two (72) hours prior to construction.
The Contractor shall establish and maintain additional Horizontal and Vertical control to replace any control points lost during construction. The Contractor shall establish the new benchmarks and shall acquire approval by the Ocean County Engineer prior to the start of construction and layout.
The Contractor shall be responsible for furnishing As-built grades at each proposed grade on the contract drawings. The As-built grades shall be hand written or electronically placed adjacent to the grades on the Construction, Drainage, Grading, or Electrical Plans. Acceptable As-builts shall consist of, but not limited to, grades, dimensions, station and offsets, inverts, pipe size, pipe material, traffic signal foundations, etc. The As-built plans shall be signed and sealed by a New Jersey Professional Land Surveyor and shall be submitted within thirty (30) days of acceptance of the substantial completion letter for the project (single work location) or each location on multiple work site projects. Two (2) paper copies and one (1) electronic copy shall be included with the submission.
105.11.04 Measurement and Payment.
This Subsection of the Standard Specifications is hereby deleted and the following substituted therefor:
No separate payment will be made for the As-built survey. All associated costs of the As-built survey shall be included in the price bid for “Construction Layout”. Final payment for Construction Layout shall not be made until required As-builts have been submitted to and approved by the Engineer.
The County will measure and make payment for items as follows:
Pay Item Pay Unit
Construction Layout Dollar
SECTION 106 - CONTROL OF MATERIAL AND EQUIPMENT
106.02 Department Furnished Material.
Sheet 15
There shall be no materials furnished by Ocean County.
106.03 Foreign Materials and Equipment.
The following is added to this Subsection of the Standard Specifications:
The attention of the Contractor is particularly directed to N.J.S.A. 40A:11-18 which requires on any contracts for County or Municipal work that only manufactured and farm products of the United States, wherever available, be used in such work. Determination of availability shall be the sole responsibility of the Engineer. Findings by the Engineer of non-availability will be set out in the contract documents.
The attention of the Contractor is directed to all existing federal and state statutes and regulations which prohibit on any public work the use by the Contractor or subcontractor of materials produced or manufactured outside the United States of America. Exceptions to this prohibition, upon the findings of the Engineer, are allowed only where its enforcement would be inconsistent with the public interest or where the material is not produced or manufactured in the United States in commercial quantities and of a sufficient quality.
If the Engineer finds that in the performance of the contract there has been a failure to comply with the provisions relative to foreign materials, he shall make public his findings and no other contract for the construction of any public work by this contracting agent shall be awarded to such Contractor, or to any partnership, association or corporation with which such Contractor is associated or affiliated, within a period of three years after such finding is made public.
Where the use of foreign material is allowed, such material shall be furnished in accordance with the following requirements:
1. Materials manufactured or produced outside the United States shall be delivered to a location approved by the Engineer where they shall be retained until examination can be completed.
2. The Contractor shall arrange, at his expense, any testing which the Engineer feels necessary to ascertain the acceptability of the material.
3. Each lot of foreign material shall be accompanied by a certificate of compliance. In addition, certified mill test reports shall be attached to the certificate of compliance for those materials for which mill test reports are required and shall clearly identify the lot to which they apply. Certificates of compliance shall contain the following information:
a. Project to which the material is consigned.
b. Name of the Contractor to which the material is supplied.
c. Kind of material supplied.
d. Quantity of material represented by the certificate.
e. Means of identifying the consignment, such as label marking, seal number, etc.
f. Date and method of shipment.
g. Statement that the material has been tested and found in conformity with the pertinent contract requirements stated in the certificate.
h. Signature of a person having legal authority to bind the supplier.
i. Signature attested to by a notary public or other properly authorized person.
106.10 Use of United States Flag Vessels.
The entire text is changed to:
This Section intentionally left blank.
Sheet 16
SECTION 107 - LEGAL RELATIONS
107.01.01 Applicable Law.
The following is added to this Subsection of the Standard Specifications:
Attention of the Contractor is called to the following State laws and regulations:
N.J.S.A. 45:5A-1, et seq, which provides that the installation, erection, repair or alteration of electrical equipment for the generation, transmission or utilization of electrical energy, must be performed by an electrical contractor duly approved and licensed by the New Jersey Board of Examiners of Electrical Contractors.
It is the obligation of the Contractor to advise the applicable gas utility three business days (Saturdays, Sundays, and holidays excluded) before initiating any excavation in the vicinity of gas facilities.
The Contractor shall make available to the Contractor’s employees, subcontractors, the Engineer and the public, all information pursuant to OSHA 29 CFR Part 1926.59 of the Hazard Communication Standard 29 CFR 1910.1200 and shall also maintain a file on each job site containing all material safety data sheets (MSDS) for products in use at the project. These material safety data sheets shall be made available to the Engineer upon request.
107.01.02 Permits, Licenses and Approvals.
The following is added to this Subsection of the Standard Specifications:
The Contractor shall pay all reinspection fees and violation charges for non-compliance with the various permit requirements.
No work may begin until all permits have been received.
The Contractor is put on notice that all permits necessary and required under the State specifications, DEP, Pinelands Commission, Soil Conservation District, EPA, OSHA Regulations, NIOSH recommendations, State of New Jersey regulations and any other applicable federal, state and local government regulations must be obtained prior to commencement of work.
In the event that dewatering is necessary on this project, the Contractor shall be required to obtain the necessary permits from the State of New Jersey, Department of Environmental Protection for dewatering through this contract.
107.02 Discrimination in Employment on Public Works.
This Subsection of the Standard Specifications is deleted in its entirety and replaced with the following:
10:2-1 Antidiscrimination provisions.
10:2-1. Antidiscrimination provisions. Every contract for or on behalf of the State or any county or municipality or other political subdivision of the State, or any agency of or authority created by any of the foregoing; for the construction; alteration or repair of any public building or public work or for the acquisition of materials, equipment, supplies or services shall contain provisions by which the contractor agrees that:
a. In the hiring of persons for the performance of work under this contract or any subcontract hereunder, or for the procurement, manufacture, assembling or furnishing of any such materials, equipment, supplies or services to be acquired under this contract, no contractor, nor any person acting on behalf of such contractor or subcontractor, shall, by reason of race, creed, color, national origin, Sheet 17 ancestry, marital status, gender identity or expression, affectional or sexual orientation or sex, discriminate against any person who is qualified and available to perform the work to which the employment relates;
b. No contractor, subcontractor, nor any person on his behalf shall, in any manner, discriminate against or intimidate any employee engaged in the performance of work under this contract or any subcontract hereunder, or engaged in the procurement, manufacture, assembling or furnishing of any such materials, equipment, supplies or services to be acquired under such contract, on account of race, creed, color, national origin, ancestry, marital status, gender identity or expression, affectional or sexual orientation or sex;
c. There may be deducted from the amount payable to the contractor by the contracting public agency, under this contract, a penalty of $50.00 for each person for each calendar day during which such person is discriminated against or intimidated in violation of the provisions of the contract; and
d. This contract may be canceled or terminated by the contracting public agency, and all money due or to become due hereunder may be forfeited, for any violation of this section of the contract occurring after notice to the contractor from the contracting public agency of any prior violation of this section of the contract.
No provision in this section shall be construed to prevent a board of education from designating that a contract, subcontract or other means of procurement of goods, services, equipment or construction shall be awarded to a small business enterprise, minority business enterprise or a women's business enterprise pursuant to P.L.1985, c.490 (C.18A:18A-51 et seq.).
Amended 1945, c.l71; 1962, c.213; 1970, c.80, s.7; 1985, c.490, s.9; 1988, c.37, s.8; 1991, c.519, s.lO; 2006, c. l 00, s. l .
107.03 Affirmative Action, Disadvantaged Business Enterprises, or Emerging Small Business Enterprise, and Small Business Enterprises.
It is the public policy of the State and of the United States that no individual, group, firm, or corporation working on or seeking to work on a Public Works Project should be discriminated against on the basis of race, creed, color, national origin, age, ancestry, nationality, marital or domestic partnership status, gender, disability, liability for military service, affectional or sexual orientation, atypical cellular or blood trait, or genetic information (including the refusal to submit to genetic testing). The Department has developed Affirmative Action, Disadvantaged Business Enterprise, or Emerging Small Business Enterprise Programs to implement this policy, and the regulations and requirements applicable to the Contract are contained in the Special Provisions. The Department will resolve conflicts between these regulations and requirements and the other provisions of the Contract to further the above stated public policy.
(REVISED 4/10)
EXHIBIT B
MANDATORY EQUAL EMPLOYMENT OPPORTUNITY LANGUAGE
N.J.S.A. 10:5-31 et seq. (P.L. 1975, C. 127) N.J.A.C. 17:27
CONSTRUCTION CONTRACTS
During the performance of this contract, the contractor agrees as follows:
The contractor or subcontractor, where applicable, will not discriminate against any employee or applicant for employment because of age, race, creed, color, national origin, ancestry, marital status, affectional or sexual orientation, gender identity or expression, disability, nationality or sex. Except with respect to affectional or sexual orientation and gender identity or expression, the contractor will ensure that equal employment opportunity is afforded to such applicants in recruitment and employment, and that employees are treated during employment, without regard
Sheet 18 to their age, race, creed, color, national origin, ancestry, marital status, affectional or sexual orientation, gender identity or expression, disability, nationality or sex. Such equal employment opportunity shall include, but not be limited to the following: employment, up-grading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.
The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the Public Agency Compliance Officer setting forth provisions of this nondiscrimination clause.
The contractor or subcontractor, where applicable will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to age, race, creed, color, national origin, ancestry, marital status, affectional or sexual orientation, gender identity or expression, disability, nationality or sex.
The contractor or subcontractor will send to each labor union, with which it has a collective bargaining agreement, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under this act and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
The contractor or subcontractor, where applicable, agrees to comply with any regulations promulgated by the Treasurer, pursuant to N.J.S.A. 10:5-31 et seq., as amended and supplemented from time to time and the Americans with Disabilities Act. When hiring or scheduling workers in each construction trade, the contractor or subcontractor agrees to make good faith efforts to employ minority and women workers in each construction trade consistent with the targeted employment goal prescribed by N.J.A.C. l7:27-7.2; provided, however, that the Dept. of LWD, Construction EEO Monitoring Program may, in its discretion, exempt a contractor or subcontractor from compliance with the good faith procedures prescribed by the following provisions, A, B and C, as long as the Dept. of LWD, Construction EEO Monitoring Program is satisfied that the contractor or subcontractor is employing workers provided by a union which provides evidence, in accordance with standards prescribed by the Dept. of LWD, Construction EEO Monitoring Program, that its percentage of active "card carrying" members who are minority and women workers is equal to or greater than the targeted employment goal established in accordance with N.J.A.C. l7:27-7.2. The contractor or subcontractor agrees that a good faith effort shall include compliance with the following procedures:
(A) If the contractor or subcontractor has a referral agreement or arrangement with a union for a construction trade, the contractor or subcontractor shall, within three business days of the contract award, seek assurances from the union that it will cooperate with the contractor or subcontractor as it fulfills its affirmative action obligations under this contract and in accordance with the rules promulgated by the Treasurer pursuant to N.J.S.A. 10:5-31
et. seq., as supplemented and amended from time to time and the Americans with Disabilities Act. If the contractor or subcontractor is unable to obtain said assurances from the construction trade union at least five business days prior to the commencement of construction work, the contractor or subcontractor agrees to afford equal employment opportunities minority and women workers directly, consistent with this chapter. If the contractor's or subcontractor's prior experience with a construction trade union, regardless of whether the union has provided said assurances, indicates a significant possibility that the trade union will not refer sufficient minority and women workers consistent with affording equal employment opportunities as specified in this chapter, the contractor or subcontractor agrees to be prepared to provide such opportunities to minority and women workers directly, consistent with this chapter, by complying with the hiring or scheduling procedures prescribed under (B) below;
and the contractor or subcontractor further agrees to take said action immediately if it determines that the union is not referring minority and women workers consistent with the equal employment opportunity goals set forth in this chapter.
(B) If good faith efforts to meet targeted employment goals have not or cannot be met for each construction trade by adhering to the procedures of (A) above, or if the contractor does not have a referral agreement or arrangement with a union for a construction trade, the contractor or subcontractor agrees to take the following actions:
Sheet 19
(l) To notify the public agency compliance officer, the Dept. of LWD, Construction EEO Monitoring Program, and minority and women referral organizations listed by the Division pursuant to N.J.A.C. 17:27-5.3, of its workforce needs, and request referral of minority and women workers;
(2) To notify any minority and women workers who have been listed with it as awaiting available vacancies;
(3) Prior to commencement of work, to request that the local construction trade union refer minority and women workers to fill job openings, provided the contractor or subcontractor…
This is the start of the file's text. The full file is on GovTribe.