Specs.pdf
PDF 14 MB Posted
- Solicitation number
- 36C24225Q0701
About this file
The document is a detailed specification for a pneumatic tube system expansion project at the Albany Stratton VA Medical Center. The project involves modifying the location of the pneumatic tube receiving station in the 2C Operating Room Suite, including demolition of an existing dumbwaiter shaft, installation of SwissLog/Translogic pneumatic tubing, and system integration. The General Contractor is required to provide all materials, labor, and supplies to complete the system, with the VA providing some existing materials like the receiving station assembly and pneumatic tube sections.
Key project requirements include: performing approximately 75% of work on a designated weekend behind containment barriers, maintaining a 2-hour fire rating, installing new wallboard and finishes, matching existing colors and protection systems, and completing the entire project within 180 days of the Notice to Proceed. The contractor must also use the VISN 2 Autodesk Build Construction management platform, complete required training, and provide three 4-hour training sessions for medical center staff on system operation and maintenance. The project is part of the VA's Non-Recurring Maintenance (NRM) program and involves careful coordination to minimize disruption to the medical center's operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24225Q0701 0001.docx | DOCX document | |
| WD Albany.docx | DOCX document | |
| 36C24225Q0701_1.docx | DOCX document | |
| Pneumatic Tube Systemas built drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VHAALNHoganJ Text Box All items stored in the corridor are will be relocated to PACU Friday night after last patient
Contractor to set up containment and begin after last patient for the evening
***Work will be conducted on an Non anesthesia weekend so as not to affect operations ***
If work isn't 100% complete on Sunday evening on the corridor wall/ tube station, containment will be reduced to a small workable room for clean new work. Contractor to paint and complete finishes in small containment yet still allow beds to pass