Specs.pdf

PDF 14 MB Posted

Attached to
Z1DA--NRM-CONST 528A8-22-860 PNEUMATIC TUBE COMPLETION
Solicitation number
36C24225Q0701
Issued by

About this file

The document is a detailed specification for a pneumatic tube system expansion project at the Albany Stratton VA Medical Center. The project involves modifying the location of the pneumatic tube receiving station in the 2C Operating Room Suite, including demolition of an existing dumbwaiter shaft, installation of SwissLog/Translogic pneumatic tubing, and system integration. The General Contractor is required to provide all materials, labor, and supplies to complete the system, with the VA providing some existing materials like the receiving station assembly and pneumatic tube sections.

Key project requirements include: performing approximately 75% of work on a designated weekend behind containment barriers, maintaining a 2-hour fire rating, installing new wallboard and finishes, matching existing colors and protection systems, and completing the entire project within 180 days of the Notice to Proceed. The contractor must also use the VISN 2 Autodesk Build Construction management platform, complete required training, and provide three 4-hour training sessions for medical center staff on system operation and maintenance. The project is part of the VA's Non-Recurring Maintenance (NRM) program and involves careful coordination to minimize disruption to the medical center's operations.

View the file

Other files

File Type Posted
36C24225Q0701 0001.docx DOCX document
WD Albany.docx DOCX document
36C24225Q0701_1.docx DOCX document
Pneumatic Tube Systemas built drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHAALNHoganJ Text Box All items stored in the corridor are will be relocated to PACU Friday night after last patient

Contractor to set up containment and begin after last patient for the evening

***Work will be conducted on an Non anesthesia weekend so as not to affect operations ***

If work isn't 100% complete on Sunday evening on the corridor wall/ tube station, containment will be reduced to a small workable room for clean new work. Contractor to paint and complete finishes in small containment yet still allow beds to pass