This document outlines submittal requirements and deadlines for a renovation project solicitation issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6. Key submittals include a security plan, qualification proposal, construction schedules, preconstruction plans, waste management plans, survey reports, contractor licensing and qualifications, and inspection requests. Submittal due dates range from 10 days after notice to proceed to 45 days prior to final inspection.
The related federal contract opportunity is a solicitation to renovate halls and walls under solicitation number 36C24622B0017. The solicitation requires adherence to the Statement of Work and submittal of bid guarantees, bonds, and licensing documentation according to specified schedules.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals
| Section | Submittal/Deliverable | Description | Due Date | |
| 01 33 23 | THIS SECTION APPLIES TO ALL SUBMITTALS IN THE PROJECT SPECIFICATION | |||
| DIVISION 01 | ||||
| 01 00 00 | 1 | Security Plan | 10 Days After NTP | |
| Duplicate Keys and lock combinations | ||||
| Electronic security memorandum | ||||
| Phasing plan | ||||
| As-built drawings | ||||
| 01 32 16.15 | 1 | Qualification proposal to COR within 10 days of bid acceptance | 10 Days after Bid Acceptance | |
| Provide all computer-produced time/cost estimates monthly | ||||
| Submit 3 blue line copies of interim schedule within 20 days of notice to proceed | 20 Days after NTP | |||
| Submit updated schedule after each monthly schedule meeting | Monthly | |||
| Within 30 days of VA approval of updated project schedule, submit revised electronic file of activity/event changes | ||||
| Submit any requests for change of completion date to contracting officer and show all CPM logic revisions, durations changes, and cost changes | ||||
| 01 33 23 | 1 | Preconstruction Submittals | Monthly | |
| Updated Submittal Register | ||||
| 01 35 26 | 1 | Submit the APP to the COR for review 15 days prior to the date of preconstruction conference for acceptance. | 15 Days Prior to Pre Construction Meeting | |
| 1.14 | Fire Safety Plan | |||
| 4(F)(2) | Confined Space Entry Plan | |||
| 1.5.13 | Emergency Action Plan | |||
| 1.4 | Accident Prevention Plan | |||
| 01 45 00 | 1 | Interim CQC Plan | ||
| 2 | CQC Plan | |||
| 01 57 19 | 1 | Environmental Protection Plan | ||
| 01 74 19 | 1 | Debris Management Plan | ||
| Waste Management Plan | ||||
| Monthly summary of construction and demolition debris diversion and disposal | Monthly | |||
| 02 41 00 | 1 | Survey Report | 15 Days after Bid Acceptance | |
| 02 82 13.19 | 1 | Proof Contracting License | ||
| List of workers/ training / experience | ||||
| List of CPR qualified workers | ||||
| Fit tests | ||||
| Copy of AHA plan | ||||
| Waste handling procedures | ||||
| Emergency Action Plan and Contingency Plan | ||||
| Submit Design and Layout | ||||
| Submit Materials and equipment specifications data | ||||
| Submit Name Locations and Phone Number of Approved Landfill | ||||
| Landfills requirements of ACM waste | ||||
| Contact information of subcontractor used | ||||
| Type of vehicle used for transportation | ||||
| Proof of asbestos training for transportation personnel | ||||
| Contact information of lab | ||||
| Submit qualifications of asbestos abatement company, list of projects, list asbestos regulatory citations | ||||
| Submit information on personnel | ||||
| Submit copies of state license | ||||
| Submit manufacturers technical data for all types of encapsulants | ||||
| Certification from the manufacturer indicating compliance with performance requirements for encapsulants when applied according to manufacturer recommendations. | ||||
| Contractor Qualifications | ||||
| Written approval confirming product compatibility with subfloor material manufacturer and flooring manufacturer | Due to the COR before removal and/or installation of flooring | |||
| Payment Protection | SF 1442 | Bid Gaurantee | Shall be Prestnt with Bid | |
| Payment Bond | Hard Copy Delivered to ACO three (3) days prior to Pre Construction Kick Off Meeting | |||
| Performance Bond | ||||
| Permits, Liscencing, Notification and Request | 00 10 00 | 1.5 (J2) | Suspension of Utilities (Minor) | 7 Days Prior to Interuption |
| 00 10 00 | 1.5 (J3) | Suspension of Utilities (Major) | 14 Days Prior to Interuption | |
| Page 307 | Lift Permit | 14 Days Prior to Lift Operations | ||
| TB Screening Records | 01 35 26 -24 | 1.13 | Personnel | 5 Days prior to Employee's arrival to the medical center |
| Inspection | 01 00 00 -28 | 1.34 | Punch-Out Inspection | 45 Days Prior |
| 01 45 00 - 10 | 1.8 B | Pre-Final Inspection | 30 Days Prior to Final Inspection Request | |
| 01 45 00 - 9 | 1.8 | Final Acceptance Inspection | 14 Days Prior |