Specs 626A4-17-202 Upgrade Elevator Building 5.pdf
PDF 2 MB Posted
- Attached to
- Z1DA--Project 626A4-17-202 - Upgrade Elevator Bldg. 5 Federal contract opportunity
- Solicitation number
- 36C24922B0029
About this file
This federal contract opportunity document solicits bids for Project 626A4-17-202 to upgrade an elevator in Building 5 at the Murfreesboro VA Medical Center. The project includes replacing major elevator components to comply with accessibility standards and safety codes.
Bids are due by February 1, 2022. The work must be completed within 180 days of the notice to proceed. The contractor will furnish all labor, materials, equipment, supervision, and other necessary items to repair and replace the elevator equipment as specified. The project is set aside for service-disabled veteran-owned small businesses. All work must be done in accordance with VA construction requirements and coordinated with the contracting officer's representative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| E-005-ES-400-Riser NC-MAIN SHEET.pdf | ||
| 36C24922B0029 0003.pdf | ||
| 36C24922B0029 0002.pdf | ||
| 36C24922B0029 0001.docx | DOCX document | |
| EMR 36C24922B0029.pdf | ||
| Drawings 626A4-17-202 Final Upgrade Elevator Building 5 .pdf | ||
| WD TN2022187 9-2-2022.pdf | ||
| Header - List of Attachments.txt | TXT text file | |
| 36C24922B0029_1.docx | DOCX document | |
| RFI Form - Upgrade Bldg 5 Elevator.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specscover.doc
Department of Veterans Affairs Alvin C. York VA Medical Center
Murfreesboro, Tennessee
Project Number 626A4-17-202
UPGRADE ELEVATOR BUILDING 5
Final Specifications
(Construction Documents)
September 15, 2017
2629 W. Main Street, Suite 190
Littleton, CO 80120
Ph (720) 550-6307
03-11
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
UPGRADE ELEVATORS BUILDING 5
MURFREESBORO VA MEDICAL CENTER
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10 Table of Contents 04-14
00 01 15 List of Drawing Sheets 04-14
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 01-11
01 35 26 Construction Safety Policy
01 42 19 Reference Standards 09-11
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 06-10
DIVISION 05 – METALS
05 51 00 Metal Stairs 10-15
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-07
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 Flashing & Sheet Metal 10-07
07 84 00 Firestopping 08-08
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-13
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 07-10
09 29 00 Gypsum Board 09-10
09 65 19 Resilient Tile Flooring 12-15
09 91 00 Painting 04-09
DIVISION 14 – CONVEYING EQUIPMENT
14 26 26 Traction Elevator Modernization 01-16
14 27 00 Elevator Cab 09-17
DIVISION 21 – Fire Suppression
21 13 13 Wet Pipe Sprinkler Systems 06-15
03-11
00 01 10-2
DIVISION 22 - PLUMBING
22 05 11 Common Work Results Plumbing 07-16
22 14 29 Sump Pumps 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 11-10
23 05 12 General Motor Requirements for HVAC 02-15
23 05 41 Noise & Vibration Control for HVAC Piping & Equipment 10-15
23 31 00 HVAC Ducts and Casings 04-11
23 36 00 Air Terminal Units 03-10
23 37 00 Air Outlets and Inlets 11-09
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 09-10
26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13
26 05 26 Grounding and Bonding for Electrical Systems 09-10
26 05 33 Raceway and Boxes for Electrical Systems 09-10
26 08 00 Commissioning of Electrical Systems 06-13
26 22 00 Low-voltage Transformers 12-15
26 24 16 Panelboards 05-14
26 27 26 Wiring Devices 04-09
26 29 21 Disconnect Switches 12-12
26 51 00 Interior Lighting Fixtures 04-09
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm 09-05
00 01 15 - 1
EDIT SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
ARCHITECTURAL
A000 COVER SHEET & NOTES
A001 ELEVATOR NOTES
A101 ELEVATOR FLOOR PLANS
A301 ELEVATOR SECTIONS
A401 INTERIOR ELEVATIONS
E101 ELECTRICAL PLAN
M101 HVAC/FIRE PLAN
- - - END - - -
VA Project No. 626A4-17-202 Tennessee Valley Healthcare System
UPGRADE ELEVATOR, BUILDING #5
06-21-17
GENERAL REQUIREMENTS
01 00 00 – I
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 CONTRACTING OFFICER’S REPRESENTATIVE'S FIELD OFFICE
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.18 TEMPORARY USE OF EXISTING ELEVATORS
1.19 TEMPORARY USE OF NEW ELEVATORS
1.20 TEMPORARY TOILETS
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
1.22 NEW TELEPHONE EQUIPMENT
1.23 TESTS
1.24 INSTRUCTIONS
06-21-17
01 00 00 – II
1.25 DEPARTMENT OF VETERANS AFFAIRS-FURNISHED PROPERTY
1.26 RELOCATED EQUIPMENT
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.28 CONSTRUCTION SIGN
1.29 SAFETY SIGN
1.30 PHOTOGRAPHIC DOCUMENTATION
1.31 FINAL ELEVATION Digital Images
1.32 HISTORIC PRESERVATION
1 . 33 FIRE SAFETY……………………………………………………………………………………………………………………………… 25
01 00 00 - 1
SECTION 01 00 00
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing material, and furnish labor and materials and perform work for VAMC- Murfreesboro, as required by drawings and specifications. Since there is one elevator in this building, Contractor to schedule his work so that the elevator is out of service for no more than 30 days.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Contracting Officer Representative (COR).
C. The VA FMS Engineering Office, VA-TN Valley Healthcare System, Murfreesboro VAMC, Bldg. #6, 3400 Lebanon Pike, Murfreesboro, TN 37129-1236, will render certain technical services during construction. Such services shall be considered as advisory to the Project and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
E. The contractor will designate a competent person (CP) to serve as the sole point of contact responsible for safety management on the project site. Competent persons are defined as those capable of identifying existing and predictable hazards in the surroundings and working conditions which are unsanitary, hazardous, or dangerous, and who have the authority to take prompt corrective measures to eliminate them. This CP designation is a formal, required submittal that requires approval by the contracting officer’s representative (COR).
Federal acquisition regulation (FAR) 52.236-13, with alternate 1, requires submittal and approval of a safety plan, specific to the project and to the construction site. The contractor will submit a safety plan that includes detailed safety precautions and
01 00 00 - 2 practices to mitigate identified hazards specific to this project and to this construction site. This plan is a formal, required submittal that requires approval by the Contracting Officer’s Representative (COR).
F. Training:
1. The contractor will submit proof of 10-hour OSHA safety course (i.e., copies of documentation) for all other prime contractor employees as well as any subcontract employees that will work on the site. This proof is a formal, required submittal that requires approval by the Contracting Officer’s Representative
(COR).
Submittals must include the names, qualifications, and training dates for the prime contractor-designated competent person (CP) designated to administer the site-specific safety program, as well as the CP (if different) for high risk activities as required by OSHA regulations, such as ladders, excavations, trenching, etc.
2. Submit training records of all such employees for approval before the start of work.
3. The contractor will submit proof of a 30-hour OSHA safety course (i.e., copies of documentation) for prime contractor-designated competent persons as well as any subcontractor-designated competent persons that will work on the site. This proof is a formal, required submittal that requires approval
G. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
ITEM I, VAMC – MURFREESBORO VA MEDICAL CENTER, UPGRADE ELEVATOR,
BUILDING 5, PROJECT NUMBER: 626A4-17-202
Introduction:
Building 5 at the Murfreesboro VA Medical Center, has one Passenger elevator that requires upgrade & modernization, including replacement of major components. The upgraded and modernized elevator must comply with the most current American Society of Mechanical Engineers (ASME):
A17.1-07 Safety Code for Elevators and Escalators and A17.2-07 Inspectors Manual for Electric Elevators and Escalators requirements, 01 00 00 - 3 along with applicable National Fire Protection Association (NFPA), National Electric Code (NEC) and Uniform Federal Accessibility Standards, Americans with Disabilities Act (ADA).
Statement of Work:
The contractor will provide equipment, material and labor necessary for the Upgrade & Modernization of one passenger elevator in building #5. Project includes repair and replacement of major components as indicated on plans and specification for this project, noting that the specifications provided for Passenger Elevator (P-1) are a performance specification (Section 14 26 26) that provides instructions on which components will be replaced and which components will be reused, but refurbished or cleaned and serviced.
Contractor will replace existing Dover Elevator Control Panel, overhead DC geared traction machine, DC Motor Generator Set, Governor, and secondary sheave with new MCE i-Motion Control Panel or approved equal simplex microprocessor control panel, with VVVF Re-Generative AC Motor Drive Unit, overhead Permanent Magnet AC Gearless Machine, (PM- AC Gearless Hoist Machine)secondary sheaves, hoist cables, governor, governor cable, governor tension sheave, hoistway door panels and hoistway door equipment and new "clad" stainless steel hoistway entrances. Reuse existing machine beams, main and counterweight rails, buffers, counterweights, entrance frames, sills, hanger supports, strut angles, fascia plates, and platform. Provide new "close loop" Car Door Operators, Detector Edge, Car and Hall Push Button Stations, and Elevator Cab Interiors. Provide LED illumination in the elevator machine room, overhead, hoistway, (between each floor) and pit.
Relocate the governor and secondary sheave from the secondary level to the new Elevator Machine Room. Provide a new 2-hour rated Elevator Machine Room enclosure with OSHA approved stairway to Machine Room elevation, landing/platform, LED illumination, Light Switch, GFCI Outlets, Machine Room Door (Swing outside the Machine Room) Shunt Trip Disconnect, Smoke Detector, Fire Suppression (Sprinkler Heads, Heat Sensors, Shut-Off Valve, and Tamper Switch outside the Elevator Machine Room) Provide Heating, Air Conditioning, and Ventilation.
The construction period will be approximately 90 days, from Notice to Proceed, with consideration for any long lead time equipment items required for this project.
Work will include:
01 00 00 - 4
Repair, Upgrade and Modernize one (1) existing Overhead Traction Passenger elevator, complete as specified. In order to maintain equipment similarity and replacement parts standardization at the Murfreesboro VA Medical Center, Murfreesboro, TN, the elevator equipment design/manufacturer for Building #5 shall be consistency with VA Standards for “Open Architecture” and non-proprietary elevator equipment manufacturers. Some Demolition and repair may be required to remove and replace specified elevator equipment and Contractor must engage/coordinate with the Fire Protection central control system (annunciator) contractor to reprogram the new elevator controls (fire panel) into the Murfreesboro VAMC fire protection system.
ITEM II BID BREAKOUT*
Provide a breakout of the bid amount in the following manner:
1. Passenger Elevator P-1 $_________
Bid total $_________
Codes:
All work shall be provided in accordance with the most current edition of the following criteria:
a. Drawings.
b. Specifications.
c. VA Design and Construction Procedures.
d. ASME A17.1 Elevator Code & Handbook
e. Most current version of International Plumbing Code (IPC).
f. Occupational Safety and Health Administration (OSHA) standards.
End of Statement of Work
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
Documents will be provided in digital PDF format at no additional cost to the Contractor. Contractor may reproduce these documents as required.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
01 00 00 - 5
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Work is assumed to be performed during normal work hours, which are
Monday thru Friday 8 a.m. to 4:30 p.m. For work outside of “regular hours” as defined in the contract, the General Contractor shall give one week’s notice to the Contracting Officer so that security and / or escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Photography of the work (elevator mechanical room, elevator and shaft; however, no photography that shows or contains the image of a patient is allowed.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officers Representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
01 00 00 - 6
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours
01 00 00 - 7 before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Department of Veterans Affairs premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Department of Veterans Affairs, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Department of
Veterans Affairs. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workmen are subject to rules of Medical Center applicable to their conduct.
01 00 00 - 8
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Department of
Veterans Affairs and not the Contractor.
I. Phasing:
01 00 00 - 9
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to the elevator in building 5.
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR, and Contractor, as indicated on the phasing drawings.
K. All other areas of Building 5 and all other buildings on campus will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to
Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc., to facilitate patient and staff access. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
L. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the contractor laydown area as indicated on the
01 00 00 - 10 drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
M. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of at least 50 degrees F at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
N. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for additional requirements.
01 00 00 - 11
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Department of
Veterans Affairs and not the Contractor.
O. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
P. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
01 00 00 - 12
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
Q. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of buildings and areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting
Officer. This report shall list by rooms (elevator mechanical room) and spaces (elevator cab and shaft:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Department of
Veterans Affairs. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-
2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
01 00 00 - 13
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Department of
Veterans Affairs are identified by attached tags and / or noted on drawings or in specifications as items to be stored. Items that remain property of the Department of Veterans Affairs shall be removed or dislodged from present locations in such a manner as to
01 00 00 - 14 prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed promptly by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Department of Veterans Affairs. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Department of Veterans Affairs in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
01 00 00 - 15
C. Refer to Articles, "Alterations", "Restoration", and "Operations and
Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Department of Veterans Affairs shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
01 00 00 - 16
B. Subsurface conditions have been developed by core borings and test pits.
C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical
Center.
D. The Department of Veterans Affairs does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to
Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES (NA)
1.13 LAYOUT OF WORK (NA)
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or
01 00 00 - 17 similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.16 CONTRACTING OFFICER’S REPRESENTATIVE’S FIELD OFFICE (NA)
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
01 00 00 - 18
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Department of
Veterans Affairs.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Department of Veterans Affairs.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.18 TEMPORARY USE OF EXISTING ELEVATORS (N/A) The Bldg. #5 Elevator is under the control of the contractor until final inspection and acceptance
1.19 TEMPORARY USE OF NEW ELEVATORS (N/A)
1.20 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Department of Veterans Affairs shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by
01 00 00 - 19 the Contractor for chargeable electrical services shall be the prevailing rates charged to the Department of Veterans Affairs. The
Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Department of Veterans Affairs, the
Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each
01 00 00 - 20 connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.22 NEW TELEPHONE EQUIPMENT (N/A)
1.23 TESTS
A. As per Specifications Section 14 26 26, Elevator Modernization
Specification, the contractor shall provide a written testing and acceptance plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation. Final acceptance shall include inspection by a certified elevator inspector.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc.
01 00 00 - 21
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.24 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at
01 00 00 - 22 the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.25 DEPARTMENT OF VETERANS AFFAIRS-FURNISHED PROPERTY (N/A)
1.26 REPLACED EQUIPMENT
A. Contractor shall disconnect, dismantle as necessary, remove and dispose of existing elevator equipment and components that are to be replaced.
B. Perform removal of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of replaced equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing
01 00 00 - 23 equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT (N/A)
1.28 CONSTRUCTION SIGN
A. Provide a Construction Sign where and if directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint.
Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .