This document is a specifications document for the Oregon Department of Transportation (ODOT) Hermiston Maintenance Station Solar project. ODOT is seeking an ESB certified firm to purchase and install a rooftop solar array system and complete an electrical service upgrade at the Hermiston Maintenance Station located at 1840 Hwy 395 in Hermiston, Oregon. The project requires substantial completion by January 2, 2023 and final completion by January 16, 2023. The contractor is responsible for providing all permits, coordinating with suppliers and subcontractors, maintaining a clean worksite, and providing operations and maintenance documentation.
The document provides detailed technical specifications for the electrical work, including requirements for conduit, wiring, grounding, panelboards, and other electrical components. It also outlines submission requirements, closeout procedures, and contractor responsibilities regarding site access, safety, and coordination with ODOT. No pricing or funding details are provided, and the document does not mention any set-asides or incumbent contractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OregonBuys Vendor Solicitation Response~13.pdf | ||
| OB Bid S-44300-00002624 RFA 5383 Amendment 1.pdf | ||
| Plan Sheets.pdf | ||
| RFCQ 35229.docx | DOCX document | |
| Hermiston Maintenance Station Photo.pdf | ||
| RFCQ 35229 Attachments A-D.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
February 28, 2022
Oregon Department of Transportation Hermiston Maintenance Station Solar project
Project Description Oregon Department of Transportation Hermiston Maintenance Station is interested in having an ESB certified firm purchase and install a roof top solar array system along with the electrical service upgrade.
Project Location 1840 Hwy 395 Hermiston, OR 97838
ODOT Contact The ODOT Project Manager for this work is Shelby Stout.
Email: shelby.stout@odot.oregon.gov
Desk phone: (541) 963-1399
Cell phone: (541) 952-1165
Address: 3012 Island Avenue, La Grande, OR 97850
The ODOT Project Manager may designate an additional ODOT contact person or engineer to support with inspections or questions in the field.
Scheduling of Contract
1. Substantial completion of the Work shall be no later than 1/2/23. Final Completion shall be no later than 1/16/23.
2. After award of bid, the Contractor shall contact the ODOT Project Manager to schedule the
Work at least 10 business days prior to the start of Work.
3. The Work shall be accomplished on weekdays between the hours of 7 a.m. to 5 p.m. Work hours shall exclude weekends and state holidays, unless specifically requested by the Contractor and approved by the ODOT Project Manager.
4. The Contractor shall coordinate the efforts of all suppliers and subcontractors, shall maintain orderly progress of the Work, prevent duplication of effort, and ensure proper sequence of operations.
5. The Contractor shall submit to the ODOT Project Manager a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all subcontractors and their key representatives.
Clean-Up/Conditions of Site
1. The Contractor shall be responsible for keeping the ODOT Project Manager informed of all activity throughout the Work.
2. The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the premises. The Contractor shall broom-clean their work area at the end of each work day and neatly stack materials and debris in an approved location. Failure to clean up allows the State to perform the necessary clean-up actions and bill the contractor the direct costs, plus $300.00, to be deducted from final payment.
3. The Contractor shall protect materials subject to damage by temperature or other weather conditions.
4. The location for storage of materials, debris, or dumpster on the Premises shall be approved in advance by the ODOT Project Manager. Disposal facilities, bins, or dumpsters shall not be provided by ODOT.
5. The Contractor shall notify the ODOT Project Manager at least 2 days in advance of any major deliveries.
6. Contractor shall immediately notify the ODOT Project Manager of any damage done by the Contractor to the Premises, grounds, or adjacent State properties.
7. Damage done by the Contractor to the Premises or surrounding area shall be repaired to existing conditions as found prior to the commencement of the Work.
8. ODOT shall not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the Premises.
9. It is the responsibility of the Contractor to ensure the Work is performed in accordance with
Oregon OSHA rules and regulations.
10. Any permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Manager prior to the start of work. The Contractor shall be responsible for posting all permits on site in accordance with local jurisdiction requirements.
11. The Contractor shall immediately bring to the attention of the ODOT Project Manager any conflicts or issues between existing utilities and the Work.
12. Contractor shall be responsible for making arrangements for temporary utility requirements during construction and related costs.
13. Restroom and drinking water shall be provided by the Contractor.
Detailed Specifications See separately attached plans and specifications
Submittals The Contractor shall provide the following submittals at a minimum to the ODOT Project Manager.
Submittals shall be approved by the ODOT Project Manager prior to the start of on-site construction.
1. See separately attached plans and specifications
Close-Out
1. Contractor shall maintain at each Premises one set of the approved drawings for recording as-built conditions. Mark (in red) changes made during the course of construction.
2. Inspection of the work by the ODOT Project Manager for establishment of Substantial
Completion shall be made within 3 business days after receipt of the Contractor’s written request. At this time, the ODOT Project Manager and the Contractor shall develop a punchlist document of any incomplete or deficient work.
3. Prior to Final Completion, Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems.
4. Prior to Final Completion, Contractor shall provide one hard copy and a digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Manager.
5. Prior to Final Completion, Contractor shall complete all items on the punchlist.
6. At the time of Final Completion, Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Manager.
7. Inspection of the work by the ODOT Project Manager for establishment of Final Completion shall be made within 5 business days after receipt of the Contractor’s written request.
Bid Items
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT UNIT PRICE TOTAL PRICE
TABLE OF CONTENTS
DIVISION 26 - ELECTRICAL
26 00 00 ELECTRICAL BASIC REQUIREMENTS
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS AND EQUIPMENT
26 05 33 RACEWAYS
26 05 34 BOXES
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 73 ELECTRICAL DISTRIBUTION SYSTEM STUDIES
26 24 16 PANELBOARDS
26 27 13 ELECTRICAL METERING
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 31 00 PHOTOVOLTAIC SYSTEMS
26 43 00 SURGE PROTECTIVE DEVICES
ODOT Hermiston MS ELECTRICAL BASIC REQUIREMENTS
100% Construction Documents 26 00 00 - 1
SECTION 26 00 00 - ELECTRICAL BASIC REQUIREMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Work included in 26 00 00, Electrical Basic Requirements applies to Division 26, Electrical work to provide materials, labor, tools, permits, incidentals, and other services to provide and make ready for Owner's use of electrical systems for proposed project.
B. Contract Documents include, but are not limited to, Specifications including Division 00, Procurement and Contracting Requirements and Division 01, General Requirements, Drawings, Addenda, Owner/Engineer Agreement, and Owner/Contractor Agreement. Confirm requirements before commencement of work.
C. Definitions:
1. Provide: To furnish and install, complete and ready for intended use.
2. Furnish: Supply and deliver to project site, ready for unpacking, assembly and installation.
3. Install: Includes unloading, unpacking, assembling, erecting, installation, applying, finishing, protecting, cleaning and similar operations at project site as required to complete items of work furnished.
4. Approved or Approved Equivalent: To possess the same performance qualities and characteristics and fulfill the utilitarian function without any decrease in quality, durability or longevity. For equipment/products defined by the Contractor as "equivalent", substitution requests must be submitted to Engineer for consideration, in accordance with Division 01, General Requirements, and approved by the Engineer prior to submitting bids for substituted items.
5. Authority Having Jurisdiction (AHJ): Indicates reviewing authorities, including local fire marshal, Owner's insurance underwriter, Owner's Authorized Representative, and other reviewing entity whose approval is required to obtain systems acceptance.
1.02 RELATED SECTIONS
A. Contents of Section applies to Division 26, Electrical Contract Documents.
B. Related Work:
1. Additional conditions apply to this Division including, but not limited to:
a. Specifications including Division 00, Procurement and Contracting Requirements and
Division 01, General Requirements.
b. Drawings
c. Addenda
d. Owner/Engineer Agreement
e. Owner/Contractor Agreement
f. Codes, Standards, Public Ordinances and Permits
1.03 REFERENCES AND STANDARDS
A. References and Standards per Division 00, Procurement and Contracting Requirements and
Division 01, General Requirements, individual Division 26, Electrical Sections and those listed in this Section.
B. Codes to include latest adopted editions, including current amendments, supplements and local jurisdiction requirements in effect as of the date of the Contract Documents, of/from:
1. State of Oregon:
a. OAR - Oregon Administrative Rules
b. OESC - Oregon Electrical Specialty Code
c. OSSC - Oregon Structural Specialty Code
C. Reference standards and guidelines include but are not limited to the latest adopted editions from:
1. ABA - Architectural Barriers Act
2. ADA - Americans with Disabilities Act
3. ANSI - American National Standards Institute
100% Construction Documents 26 00 00 - 2
4. APWA - American Public Works Association
5. ASCE - American Society of Civil Engineers
6. ASTM - ASTM International
7. CFR - Code of Federal Regulations
8. EPA - Environmental Protection Agency
9. ETL - Electrical Testing Laboratories
10. FCC - Federal Communications Commission
11. IBC - International Building Code
12. IEC - International Electrotechnical Commission
13. IEEE - Institute of Electrical and Electronics Engineers
14. ISO - International Organization for Standardization
15. MSS - Manufacturers Standardization Society
16. NEC - National Electric Code
17. NECA - National Electrical Contractors Association
18. NEMA - National Electrical Manufacturers Association
19. NETA - National Electrical Testing Association
20. NFPA - National Fire Protection Association
21. OSHA - Occupational Safety and Health Administration
22. UL - Underwriters Laboratories Inc.
D. See Division 26, Electrical individual Sections for additional references.
1.04 SUBMITTALS
A. See Division 01, General Requirements for Submittal Procedures as well as individual Division 26, Electrical Sections.
B. Provide drawings in format and software release equal to the design documents. Drawings to be the same sheet size and scale as the Contract Documents.
C. In addition:
1. "No Exception Taken" constitutes that review is for general conformance with the design concept expressed in the Contract Documents for the limited purpose of checking for conformance with information given. Any action is subject to the requirements of the Contract Documents. Contractor is responsible for the dimensions and quantity and will confirm and correlate at the job site, fabrication processes and techniques of construction, coordination of the work with that of all other trades, and the satisfactory performance of the work.
2. Provide product submittals and shop drawings in electronic format only. Electronic format must be submitted via zip file via e-mail or posted to ftp site. For electronic format, provide one file per division containing one bookmarked PDF file with each bookmark corresponding to each Specification Section. Arrange bookmarks in ascending order of Specification Section number. Individual submittals sent piecemeal in a per Specification Section method will be returned without review or comment. All transmissions/submissions to be submitted to Architect. Deviations will be returned without review.
a. Provide separate submittals for power system study (per Specification Section 26 05
73) and electrical equipment (for example, switchboards and panelboards).
3. Product Data: Provide manufacturer's descriptive literature for products specified in
Division 26, Electrical Sections.
4. Identify/mark each submittal in detail. Note what differences, if any, exist between the submitted item and the specified item. Failure to identify the differences will be considered cause for disapproval. If differences are not identified and/or not discovered during the submittal review process, Contractor remains responsible for providing equipment and materials that meet the specifications and drawings.
a. Label submittal to match numbering/references as shown in Contract Documents.
Highlight and label applicable information to individual equipment or cross out/remove extraneous data not applicable to submitted model. Clearly note options and
100% Construction Documents 26 00 00 - 3 accessories to be provided, including field installed items. Highlight connections by/to other trades.
b. Include technical data, installation instructions and dimensioned drawings for products, fixtures, equipment and devices installed, furnished or provided. Reference individual Division 26, Electrical specification Sections for specific items required in product data submittal outside of these requirements.
c. See Division 26, Electrical individual Sections for additional submittal requirements outside of these requirements.
5. Maximum of two reviews of complete submittal package. Arrange for additional reviews and/or early review of long-lead items; Bear costs of these additional reviews at Engineer's hourly rates. Incomplete submittal packages/submittals will be returned to contractor without review.
6. Resubmission Requirements: Make corrections or changes in submittals as required, and in consideration of Engineer’s comments. Identify Engineer’s comments and provide an individual response to each of the Engineer’s comments. Cloud changes in the submittals and further identify changes which are in response to Engineer’s comments.
7. Structural/Seismic: Provide weights, dimensions, mounting requirements and like information required for mounting, seismic bracing, and support. Indicate manufacturer's installation and support requirements to meet ASCE 7-10 requirements for non-structural components. Provide engineered seismic drawings and equipment seismic certification.
Equipment Importance Factor as specified in Division 01.
8. Trade Coordination: Include physical characteristics, electrical characteristics, device layout plans, wiring diagrams, and connections as required per Division 26, Electrical Coordination Documents. Be responsible for any modifications to electrical equipment or installations as a result of equipment incompatibility discovered after shop drawing review.
9. Make provisions for openings in building for admittance of equipment prior to start of construction or ordering of equipment.
10. Substitutions and Variation from Basis of Design:
a. The Basis of Design designated product establishes the qualities and characteristics for the evaluation of any comparable products by other listed acceptable manufacturers if included in this Specification or included in an approved Substitution Request as judged by the Design Professional.
b. If substitutions and/or equivalent equipment/products are being proposed, it is the responsibility of parties concerned, involved in, and furnishing the substitute and/or equivalent equipment to verify and compare the characteristics and requirements of that furnished to that specified and/or shown. If greater capacity and/or more materials and/or more labor is required for the rough-in, circuitry or connections than for the item specified and provided for, then provide compensation for additional charges required for the proper rough-in, circuitry and connections for the equipment being furnished. No additional charges above the Base Bid, including resulting charges for work performed under other Divisions, will be allowed for such revisions.
Coordinate with the requirements of "Submittals". For any product marked "or approved equivalent", a substitution request must be submitted to Engineer for approval prior to purchase, delivery or installation.
11. Shop Drawings: Provide coordinated shop drawings which include physical characteristics of all systems, device layout plans, and control wiring diagrams. Reference individual Division 26, Electrical specification Sections for additional requirements for shop drawings outside of these requirements.
12. Resubmission Requirements:
a. Make any corrections or change in submittals when required. Provide submittals as specified. The engineer will not be required to edit and/or interpret the Contractor's submittals. Indicate changes for the resubmittal in a cover letter with reference to page(s) changed and reference response to comment. Cloud changes in the submittals.
b. Resubmit for review until review indicates no exception taken or "make corrections as noted".
100% Construction Documents 26 00 00 - 4
13. Operation and Maintenance Manuals, Owner's Instructions:
a. Submit, at one time, electronic files (PDF format) of manufacturer's operation and maintenance instruction manuals and parts lists for equipment or items requiring servicing. Submit data when work is substantially complete and in same order format as submittals. Include name and location of source parts and service for each piece of equipment.
1) Include copy of approved submittal data along with submittal review letters received from Engineer. Data to clearly indicate installed equipment model numbers. Delete or cross out data pertaining to other equipment not specific to this project.
2) Include copy of manufacturer's standard Operations and Maintenance for equipment. At front of each tab, provide routine maintenance documentation for scheduled equipment. Include manufacturer's recommended maintenance schedule and highlight maintenance required to maintain warranty. Furnish list of routine maintenance parts, including part numbers, sizes, quantities, relevant to each piece of equipment.
3) Include Warranty per Division 00, Procurement and Contracting Requirements and Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
4) Include product certificates of warranties and guarantees.
5) Include copy of complete parts list for equipment. Include available exploded views of assemblies and sub assemblies.
6) Include copy of startup and test reports specific to each piece of equipment.
7) Engineer will return incomplete documentation without review. Engineer will provide one set of review comments in Submittal Review format. Contractor must arrange for additional reviews; Contractor to bear costs for additional reviews at Engineer's hourly rates.
b. Thoroughly instruct Owner in proper operation of equipment and systems. Where noted in individual Sections, training will include classroom instruction with applicable training aids and systems demonstrations. Field instruction per Section 26 00 00, Electrical Basic Requirements, Demonstration.
c. Copies of certificates of code authority inspections, acceptance, code required acceptance tests, letter of conformance and other special guarantees, certificates of warranties, specified elsewhere or indicated on Drawings.
14. Record Drawings:
a. Maintain at site at least one set of drawings for recording “As-constructed” conditions.
Indicate on drawings changes to original documents by referencing revision document, and include buried elements, location of conduit, and location of concealed electrical items. Include items changed by field orders, supplemental instructions, and constructed conditions.
b. Record Drawings are to include equipment and fixture/connection schedules that accurately reflect "as constructed or installed" for project.
c. At completion of project, input changes to original project on CAD Drawings and make one set of black-line drawings created from CAD Files in version/release equal to contract drawings. Submit CAD disk and drawings upon substantial completion.
d. See Division 26, Electrical individual Sections for additional items to include in record drawings.
1.05 QUALITY ASSURANCE
A. Regulatory Requirements: Work and materials installed to conform with all local, State and
Federal codes, and other applicable laws and regulations. Where code requirements are at variance with Contract Documents, meet code requirements as a minimum requirement and include costs necessary to meet these in Contract. Machinery and equipment are to comply with OSHA requirements, as currently revised and interpreted for equipment manufacturer requirements. Install equipment provided per manufacturer recommendations.
100% Construction Documents 26 00 00 - 5
B. Whenever this Specification calls for material, workmanship, arrangement or construction of higher quality and/or capacity than that required by governing codes, higher quality and/or capacity take precedence.
C. Drawings are intended to be diagrammatic and reflect the Basis of Design manufacturer's equipment. They are not intended to show every item in its exact dimensions, or details of equipment or proposed systems layout. Verify actual dimensions of systems and equipment proposed to assure that systems and equipment will fit in available space. Contractor is responsible for design and construction costs incurred for equipment other than Basis of Design, including, but not limited to, architectural, structural, electrical, HVAC, fire sprinkler, and plumbing systems.
D. Manufacturer's Instructions: Follow manufacturer's written instructions. If in conflict with Contract Documents, obtain clarification. Notify Engineer, in writing, before starting work.
E. Items shown on Drawings are not necessarily included in Specifications or vice versa. Confirm requirements in all Contract Documents.
F. Provide products that are UL listed.
1.06 WARRANTY
A. Provide written warranty covering the work for a period of one year from date of Substantial Completion in accordance with Division 00, Procurement and Contracting Requirements and Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
B. Sections under this Division can require additional and/or extended warranties that apply beyond basic warranty under Division 01, General Requirements and the General Conditions.
Confirm requirements in all Contract Documents.
1.07 COORDINATION DOCUMENTS
A. Prior to construction, coordinate installation and location of HVAC equipment, ductwork, grilles, diffusers, piping, plumbing equipment/fixtures, fire sprinklers, plumbing, lights, cable tray and electrical services with architectural and structural requirements, and other trades (including ceiling suspension and tile systems), and provide maintenance access requirements.
Coordinate with submitted architectural systems (i.e. roofing, ceiling, finishes) and structural systems as submitted.
B. Advise Engineer in event a conflict occurs in location or connection of equipment. Bear costs resulting from failure to properly coordinate installation or failure to advise Engineer of conflict.
C. Verify in field exact size, location, and clearances regarding existing material, equipment and apparatus, and advise Engineer of discrepancies between that indicated on Drawings and that existing in field prior to installation related thereto.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Articles, fixtures, and equipment of a kind to be standard product of one manufacturer.
2.02 STANDARDS OF MATERIALS AND WORKMANSHIP
A. Base contract upon furnishing materials as specified. Materials, equipment, and fixtures used for construction are to be new, latest products as listed in manufacturer's printed catalog data and are to be UL approved or have adequate approval or be acceptable by state, county, and city authorities. Equipment/fixture supplier is responsible for obtaining State, County, and City acceptance on equipment/fixtures that are not UL approved or are not listed for installation.
B. Names and manufacturer's names denote character and quality of equipment desired and are not to be construed as limiting competition.
C. Hazardous Materials:
1. Comply with local, State of Oregon, and Federal regulations relating to hazardous materials.
100% Construction Documents 26 00 00 - 6
2. Comply with Division 00, Procurement and Contracting Requirements and Division 01, General Requirements for this project relating to hazardous materials.
3. Do not use any materials containing a hazardous substance. If hazardous materials are encountered, do not disturb; immediately notify Owner and Architect. Hazardous materials will be removed by Owner under separate contract.
PART 3 - EXECUTION
3.01 ACCESSIBILITY AND INSTALLATION
A. Confirm Accessibility and Installation requirements in Division 00, Procurement and Contracting Requirements, Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
B. Install equipment requiring access (i.e., junction boxes, combiner boxes, inverters, power supplies, etc.) so that they may be serviced, reset, replaced or recalibrated by service people with normal service tools and equipment. Do not install equipment in passageways, doorways, scuttles or crawlspaces which would impede or block the intended usage.
C. Install equipment and products complete as directed by manufacturer's installation instructions.
Obtain installation instructions from manufacturer prior to rough-in of equipment and examine instructions thoroughly. When requirements of installation instructions conflict with Contract Documents, request clarification from Engineer prior to proceeding with installation. This includes proper installation methods, sequencing, and coordination with other trades and disciplines.
D. Earthwork:
1. Confirm Earthwork requirements in Contract Documents. In the absence of specific requirements, comply with individual Division 26, Electrical Sections and the following:
a. Perform excavation, dewatering, shoring, bedding, and backfill required for installation of work in this Division in accordance with related earthwork Sections. Contact utilities and locate existing utilities prior to excavation. Repair any work damaged during excavation or backfilling.
b. Excavation: Do not excavate under footings, foundation bases, or retaining walls.
c. Provide protection of underground systems.
E. Firestopping:
1. Confirm requirements in Division 07, Thermal and Moisture Protection. In the absence of specific requirements, comply with individual Division 26, Electrical Sections and the following:
a. Coordinate location and protection level of fire and/or smoke rated walls, ceilings, and floors. When these assemblies are penetrated, seal around piping and equipment with approved firestopping material. Install firestopping material complete as directed by manufacturer's installation instructions. Meet requirements of ASTM E814, Standard Test Method for Fire Tests of Through-Penetration Fire Stops.
F. Start up equipment, in accordance with manufacturer's start-up instructions, and in presence of manufacturer's representative. Test controls and demonstrate compliance with requirements.
Replace damaged or malfunctioning controls and equipment.
G. Provide miscellaneous supports/metals required for installation of equipment and conduit.
3.02 SEISMIC CONTROL
A. Confirm Seismic Control requirements in Division 01, General Requirements, and individual Division 26 Electrical Sections.
B. General:
1. Earthquake resistant designs for Electrical (Division 26) equipment and distribution, i.e.
power distribution equipment, etc. to conform to regulations of jurisdiction having authority.
2. Restraints which are used to prevent disruption of function of piece of equipment because of application of horizontal force to be such that forces are carried to frame of structure in such a way that frame will not be deflected when apparatus is attached to a mounting base and equipment pad, or to structure in normal way, utilizing attachments provided. Secure
100% Construction Documents 26 00 00 - 7 equipment and distribution systems to withstand a force in direction equal to value defined by jurisdiction having authority.
3. Provide stamped shop drawings from licensed Structural Engineer of seismic bracing and seismic movement assemblies for conduit and equipment. Submit shop drawings along with equipment submittals.
4. Provide stamped shop drawings from licensed Structural Engineer of seismic flexible joints for conduit crossing building expansion or seismic joints. Submit shop drawings along with seismic bracing details.
5. Provide means to prohibit excessive motion of electrical equipment during earthquake.
3.03 REVIEW AND OBSERVATION
A. Confirm Review and Observation requirements in Division 00, Procurement and Contracting Requirements, Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
B. Notify Engineer, in writing, at following stages of construction so that they may, at their option, visit site for review and construction observation:
1. When main systems, or portions of, are being tested and ready for inspection by AHJ.
3.04 CONTINUITY OF SERVICE
A. Confirm requirements in Division 00, Procurement and Contracting Requirements and Division
01, General Requirements. In the absence of specific requirements in Division 01, General Requirements, comply with individual Division 26, Electrical Sections and the following:
1. During remodeling or addition to existing structure, while existing structure is occupied, present services to remain intact until new construction, facilities or equipment is installed.
2. Prior to changing over to new service, verify that every item is thoroughly prepared. Install new wiring, and wiring to point of connection.
3. Coordinate transfer time to new service with Owner. If required, perform transfer during off-peak hours. Once changeover is started, pursue to its completion to keep interference to a minimum.
a. If overtime is necessary, there will be no allowance made by Owner for extra expense for such overtime or shift work.
4. No interruption of services to any part of existing facilities will be permitted without express permission in each instance from Owner. Requests for outages must state specific dates, hours and maximum durations, with outages kept to these specific dates, hours and maximum durations. Obtain written permission from Owner for any interruption of power, lighting or signal circuits and systems.
a. Organize work to minimize duration of power interruption.
b. Coordinate utility service outages with utility company.
3.05 CUTTING AND PATCHING
A. Confirm requirements in Division 00, Procurement and Contracting Requirements and Division
01, General Requirements. In the absence of specific requirements in Division 01, General Requirements, comply with individual Division 26, Electrical Sections and the following:
1. Proposed floor cutting/core drilling/sleeve locations to be approved by Project Structural
Engineer. Submit proposed locations to Project Structural Engineer.
2. Cutting, patching and repairing for work specified in this Division including plastering, masonry work, concrete work, carpentry work, and painting included under this Section will be performed by skilled craftsmen of each respective trade in conformance with appropriate Division of Work.
3. Additional openings required in building construction to be made by drilling or cutting. Use of jack hammer is specifically prohibited. Patch openings in and through concrete and masonry with grout.
4. Restore new or existing work that is cut and/or damaged to original condition. Patch and repair specifically where existing items have been removed. This includes repairing and painting walls, ceilings, etc. where existing conduit and devices are removed as part of this
100% Construction Documents 26 00 00 - 8 project. Where alterations disturb paving and/or walks, surfaces to be repaired, refinished and left in condition matching existing prior to commencement of work.
5. Additional work required by lack of proper coordination will be provided at no additional cost to the Owner.
3.06 EQUIPMENT SELECTION AND SERVICEABILITY
A. Replace or reposition equipment which is too large or located incorrectly to permit servicing, at no additional cost to Owner.
3.07 DELIVERY, STORAGE AND HANDLING
A. Confirm requirements in Division 00, Procurement and Contracting Requirements and Division 01, General Requirements. In the absence of specific requirements, comply with individual Division 26, Electrical Sections and the following:
1. Handle materials delivered to project site with care to avoid damage. Store materials on site inside building or protected from weather, dirt and construction dust. Products and/or materials that become damaged due to water, dirt, and/or dust as a result of improper storage and handling to be replaced before installation.
2. Protect equipment to avoid damage. Close conduit openings with caps or plugs.
3. Protect bus duct and similar items until in service.
3.08 DEMONSTRATION
A. Confirm Demonstration requirements in Division 00, Procurement and Contracting
Requirements, Division 01, General Requirements, and individual Division 26, Electrical Sections.
B. Upon completion of work and adjustment of equipment, test systems and demonstrate to Owner's Authorized Representative and Engineer that equipment furnished and installed or connected under provisions of these Specifications functions in manner required. Provide field instruction to Owner's Maintenance Staff as specified in Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
C. Manufacturer's Field Services: Furnish services of a qualified person at time approved by Owner, to instruct maintenance personnel, correct defects or deficiencies, and demonstrate to satisfaction of Owner that entire system is operating in satisfactory manner and complies with requirements of other trades that may be required to complete work. Complete instruction and demonstration prior to final job site observations.
3.09 CLEANING
A. Confirm Cleaning requirements in Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
B. Upon completion of installation, thoroughly clean electrical equipment, removing dirt, debris, dust, temporary labels and traces of foreign substances. Throughout work, remove construction debris and surplus materials accumulated during work.
3.10 INSTALLATION
A. Confirm Installation requirements in Division 00, Procurement and Contracting Requirements and Division 01, General Requirements, Section 26 00 00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
B. Install equipment in accordance with manufacturer's installation instructions, plumb and level and firmly anchored. Maintain manufacturer's recommended clearances.
C. Start up equipment, in accordance with manufacturer's start-up instructions, and in presence of manufacturer's representative. Test controls and demonstrate compliance with requirements.
Replace damaged or malfunctioning controls and equipment.
D. Provide miscellaneous supports/metals required for installation of equipment.
100% Construction Documents 26 00 00 - 9
3.11 DEMOLITION
A. Confirm requirements in Division 01, General Requirements and Division 02, Existing
Conditions. In the absence of specific requirements, comply with individual Division 26, Electrical Sections and the following:
1. It is the intent of these documents to provide necessary information and adjustments to electrical system required to meet code, and accommodate installation of new work.
2. Coordinate with Owner so that work can be scheduled not to interrupt operations, normal activities, building access or access to different areas. Owner will cooperate to best of their ability to assist in coordinated schedule, but will remain final authority as to time of work permitted.
3. Examination:
a. Determine exact location of existing utilities and equipment before commencing work, compensate Owner for damages caused by failure to locate and preserve utilities.
Replace damaged items with new material to match existing.
b. Report discrepancies to Engineer before disturbing existing installation.
1) Promptly notify Owner if utilities are found which are not shown on Drawings.
4. Execution:
a. Provide temporary wiring and connections to maintain electrical continuity of existing systems during construction. Remove or relocate electrical boxes, conduit, wiring, equipment, and luminaires, as encountered in removed or remodeled areas in existing construction affected by this work.
b. Remove and restore wiring which serves usable existing outlets clear of construction or demolition.
c. If existing junction boxes will be made inaccessible, or if abandoned outlets serve as feed through boxes for other existing electrical equipment which is being retained, provide new conduit and wire to bypass inaccessible junction boxes and abandoned outlets.
d. Remove abandoned wiring to source of supply.
e. Remove exposed abandoned conduit, including abandoned conduit above accessible ceiling finishes. Cut conduit flush with walls and floors, and patch surfaces.
f. Disconnect abandoned outlets and remove devices. Remove abandoned outlets if conduit servicing them is abandoned and removed. Provide blank cover for abandoned outlets which are not removed.
g. Disconnect and remove abandoned panelboards and distribution equipment.
h. Existing lighting which is to remain, leave luminaires in proper working order.
i. Repair adjacent construction and finishes damaged during demolition work.
j. Maintain access to existing electrical installations which remain active. Modify installation or provide access panel as appropriate.
3.12 ACCEPTANCE
A. Confirm requirements in Division 00, Procurement and Contracting Requirements and Division 01, General Requirements. In the absence of specific requirements, comply with individual Division 26, Electrical Sections and the following:
1. System cannot be considered for acceptance until work is completed and demonstrated to
Owner that installation is in strict compliance with Specifications, Drawings and manufacturer's installation instructions, particularly in reference to following:
a. Cleaning
b. Operation and Maintenance Manuals
c. Training of Operating Personnel
d. Record Drawings
e. Warranty and Guaranty Certificates
f. Start-up/Test Document
100% Construction Documents 26 00 00 - 10
3.13 FIELD QUALITY CONTROL
A. Confirm Field Quality Control requirements in Division 01, General Requirements, Section 26 00
00, Electrical Basic Requirements and individual Division 26, Electrical Sections.
B. Tests:
1. Conduct tests of equipment and systems to demonstrate compliance with requirements specified. Reference individual Specification Sections for required tests. Document tests and include in operation and maintenance manuals.
2. During site evaluations by Engineer, provide appropriate personnel with tools to remove and replace trims, covers, and devices so that proper evaluation of installation can be performed.
3.14 LETTER OF CONFORMANCE
A. Provide Letter of Conformance, copies of manufacturers' warranties and extended warranties with a statement that Electrical items were installed in accordance with manufacturer's recommendations and UL listings. Include Letter of Conformance, copies of manufacturers' warranties and extended warranties in Operation and Maintenance Manuals.
END OF SECTION
ODOT Hermiston MS LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
100% Construction Documents 26 05 19 - 1
SECTION 26 05 19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Lugs and Pads
2. Wires and Cables
3. Connectors
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and
Division 01, General Requirements.
1.04 SUBMITTALS
A. Submittals as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. Cable insulation test reports in project closeout documentation.
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division
01, General Requirements.
1.06 WARRANTY
A. Warranty of materials and workmanship as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Lugs and Pads:
1. Anderson
2. Ilsco
3. Panduit
4. Thomas & Betts
5. 3M
6. Or approved equivalent.
B. Wires and Cables:
1. General:
a. General Cable
b. Okonite
c. Southwire
d. Encore Wire
e. Or approved equivalent.
C. Connectors:
1. Anderson Power Products
2. Burndy
3. Ilsco
4. 3M
5. Thomas & Betts
6. Or approved equivalent.
100% Construction Documents 26 05 19 - 2
2.02 LUGS AND PADS
A. Ampacity: Cross-sectional area of pad for multiple conductor terminations to match ampere rating of panelboard bus or equipment line terminals.
B. Copper Pads: Drilled and tapped for multiple conductor terminals.
C. Lugs: Compression type for use with stranded branch circuit or control conductors; mechanical lugs for use with solid branch and feeder circuit conductors.
2.03 WIRES AND CABLES
A. Building Wires:
1. Copper: Soft-drawn with conductivity of not less than 98 percent IACS at 20 degrees C (68 degrees F). 600 volt rated throughout. Conductors 12 AWG and 10 AWG, solid.
Conductors 8 AWG and larger, stranded. 12 AWG minimum conductor size. Minimum insulation rating of 90 degrees C. Insulation Type: THHN/THWN-2 above grade and XHHW-2 below grade.
2. Aluminum conductors are not permitted unless written approval is received from the Engineer.
B. Phase color to be consistent at feeder terminations; A-B-C, top to bottom, left to right, front to back.
C. Color Code Conductors as Follows:
PHASE 208 VOLT WYE 240 VOLT DELTA 480 VOLT
A Black Black Brown B Red Orange (High Leg) Orange C Blue Blue Yellow Neutral White White Gray Ground Green Green Green Isolated Ground Green w/yellow trace N/A N/A
D. MC Cable: Not allowed.
E. AC Cable (Armored Cable): Not allowed.
F. NMB Cable: Not allowed.
2.04 CONNECTORS
A. Split bolt connectors not allowed.
B. Conductor Branch Circuits: Wire nuts with integral spring connectors for conductors 12 AWG through 8 AWG. Push-in type connectors where conductors are not required to be twisted together are not acceptable.
PART 3 - EXECUTION
3.01 GENERAL INSTALLATION REQUIREMENTS
A. Install per manufacturer instructions and NEC and OESC.
B. Field Quality Control:
1. Test conductor insulation on feeders of 100 amp and greater for conformity with 1000 volt megohmmeter. Use Insulated Cable Engineers Association testing procedures. Minimum insulation resistance acceptable is 1 megohm for systems 600 volts and below. Notify Architect if insulation resistance is less than 1 megohm.
2. Test Report: Prepare a typed tabular report indicating the testing instrument, the feeder tested, amperage rating of the feeder, insulation type, voltage, the approximate length of the feeder, conduit type, and the measured resistance of the megohmmeter test. Submit test reports with project closeout documents.
3. Inspect and test in accordance with NETA Standard ATS, except Section 4.
4. Perform inspections and tests listed in NETA Standard ATS, Section 7.3.2.
100% Construction Documents 26 05 19 - 3
3.02 LUGS AND PADS
A. Thoroughly clean surfaces to remove all dirt, oil, great or paint.
B. Use torque wrench to tighten per manufacturer's directions.
3.03 WIRES AND CABLES
A. General:
1. Do not install or handle thermoplastic insulated wire and cable in temperatures below -10 degrees C (14 degrees F). Do not handle thermoset insulated wire and cable in temperatures below -40 degrees C (-40 degrees F). All wire and cable must be acclimated to temperatures above freezing for no less than 24 hours prior to installation.
2. Install conductors in raceways having adequate, code size cross-sectional area for wires indicated.
3. Install conductors with care to avoid damage to insulation.
4. Do not apply greater tension on conductors than recommended by manufacturer during installation.
5. Use of pulling compounds is permitted. Clean residue from exposed conductors and raceway entrances after conductor installation.
6. Conductor Size and Quantity:
a. Install no conductors smaller than 12 AWG unless otherwise shown.
b. Provide required conductors for a fully operable system.
c. Power Circuits: No. 12 AWG minimum, except as follows:
1) No. 10 AWG for 15A, 120V circuits longer than 100 ft.
2) No. 8 AWG for 15A, 120V circuits longer than 150 ft.
3) No. 10 AWG for 20A, 120V circuits longer than 70 ft.
4) No. 8 AWG for 20A, 120V circuits longer than 100 ft.
d. When exact run lengths are determined for all branch circuits, and prior to installation of the conductors, ensure that the maximum voltage drop, based on 80 percent of the circuit protective device, does not exceed 3 percent. Increase wire size from #12AWG, if necessary, to ensure that the 3 percent voltage drop is not exceeded.
7. Provide dedicated neutrals (one neutral conductor for each phase conductor) in all 120V circuits and all 277V circuits.
B. Conductors in Cabinets:
1. Cable and tree wires in panels and cabinets for power and control. Use plastic ties in panels and cabinets.
2. Tie and bundle feeder conductors in wireways of panelboards.
3. Hold conductors away from sharp metal edges.
C. Homeruns:
1. Do not change intent of branch circuit homeruns without approval. Homeruns for 20A branch circuits may be combined to a maximum of six current carrying conductors including neutral conductors in homeruns. Apply derating factors as required per NEC.
Increase conductor size as needed.
D. Identify wire and cable under the provisions of Section 26 05 53, Identification for Electrical Systems. Identify each conductor with its panel and circuit number as indicated.
E. Exposed cable is not allowed.
F. All cable must be run parallel or perpendicular to building lines and hidden from view when possible. Where installed in tray each power cable is to be identified with Lamacoid nametag engraved with identification of equipment being fed. Tag to be fastened to cable using tie-wraps.
Provide nametag at each floor level.
3.04 CONNECTORS
A. Install to assure a solid and safe connection.
B. Select hand twist connectors for wire size and install tightly on conductors.
100% Construction Documents 26 05 19 - 4
C. Install compression connectors using methods and tools recommended by the manufacturer.
D. Do not install stranded conductors under screw terminals unless compression lugs are installed.
E. Do not connect wiring without UL listed connectors that are listed for the purposes.
ODOT Hermiston MS GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
100% Construction Documents 26 05 26 - 1
SECTION 26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Connectors and Accessories
2. Grounding Conductor
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and
Division 01, General Requirements.
1.04 SUBMITTALS
A. Submittals not required for this Section.
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, meet the following:
1. Comply with the requirements of ANSI/NFPA 70.
1.06 WARRANTY
A. Warranty of materials and workmanship as required by Section 26 00 00, Electrical Basic
Requirements and Division 01, General Requirements.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Connectors and Accessories:
1. Burndy Hyground Compression System
2. Erico/Cadweld
3. Amp Ampact Grounding System
4. Pipe Grounding Clamp:
a. Burndy GAR Series
b. O Z Gedney
c. Thomas & Betts
d. Or approved equivalent.
B. Grounding Conductor
1. General Cable
2. Okonite
3. Southwire
4. Or approved equivalent
2.02 CONNECTORS AND ACCESSORIES
A. Grounding Connectors: Hydraulic compression tool applied connectors or exothermic welding process connectors or powder actuated compression tool applied connectors.
B. Pipe Grounding Clamp: Mechanical ground connector with cable parallel or perpendicular to pipe.
2.03 GROUNDING CONDUCTOR
A. Grounding Electrode Conductor: Soft-draw bare stranded copper for wire sizes larger than #10 AWG Bare. Solid copper for wire sizes #10 AWG and smaller.
B. Equipment Grounding Conductor: Green insulated, insulation type to match that of associated feeder or branch circuit wiring, size as indicated on drawings.
ODOT Hermiston MS GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
100% Construction Documents 26 05 26 - 2
PART 3 - EXECUTION
3.01 GENERAL INSTALLATION REQUIREMENTS
A. Verify site conditions prior to beginning work.
B. Bond Sections of service equipment enclosure to service ground bus.
C. Ground new electrical service to existing electrode system per NEC Article 250.
D. Corrosion inhibitors: Apply a corrosion inhibitor to contact surfaces when making grounding and bonding connections. Use corrosion inhibitor appropriate for protecting a connection between metals used.
E. Inspect and test in accordance with NETA Standard ATS, Except Section 4.
F. Perform inspections and tests listed in NETA Standard AB, Section 7.13.
3.02 CONNECTORS AND ACCESSORIES INSTALLATION
A. Install per manufacturer's instructions.
3.03 GROUNDING CONDUCTOR INSTALLATION
A. Raceways:
1. Ground metallic raceway systems. Bond to ground terminal with code size jumper except where code size or larger equipment grounding conductor is included with circuit, use grounding bushing with lay-in lug.
2. Connect metal raceways, which terminate within an enclosure but without mechanical connection to enclosure, by grounding bushings and ground conductor to grounding bus.
3. Where equipment supply…
This is the start of the file's text. The full file is on GovTribe.