SECTION 011000 - SUMMARY
GENERAL
SUMMARY
Section Includes:
Project information.
Work covered by Contract Documents.
Work under other contracts.
Use of premises.
Public use of site.
Work restrictions.
Specification formats and conventions.
PROJECT INFORMATION
Project Identification: South Shore Bank Treatment Project Location: Southwest shore of Henrys Lake, Fremont County, Idaho
WORK COVERED BY CONTRACT DOCUMENTS
The Work consists of the following:
Furnish labor, equipment and supplies to construct the following:
Grade shoreline bank to 3:1 slope Placement of log structures Placement of Coir
USE OF PREMISES
Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Government right to perform work or to retain other contractors on portions of Project.
Schedule operations so that Work is conducted during regular office hours.
Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
PUBLIC USE OF SITE
Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Road closures will be permitted, when required, upon specific approval of Contracting Officer for the duration of operations.
WORK RESTRICTIONS
On-Site Work Hours: Work shall be generally performed during normal business working hours of 6:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.
Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
Existing Utilities Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
SPECIFICATION FORMATS AND CONVENTIONS
Specification Format: The Specifications are organized into Divisions and Sections using the CSI/CSC's "MasterFormat" numbering system.
Division 01 – General Requirements: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
Division 31 – Earthwork Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
Terminology: All references to “Owner” shall be replaced with the term “Government” or “Contracting Officer” (when referring to the person acting for the Government). All references to “Architect” shall be replaced with the term “Contracting Officer”.
END OF SECTION 011000
| 07/08/2022 | SUMMARY |
| SOUTH SHORE BANK TREATMENT | 011000-2 |
SECTION 012200 - UNIT PRICES
1. GENERAL
SUMMARY
Section includes administrative and procedural requirements for unit prices.
DEFINITIONS
Unit price is a price per unit of measurement for materials or services added to or deducted from the Contract Sum by appropriate modification, if estimated quantities of Work required by the Contract Documents are increased or decreased.
PROCEDURES
Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government expense, by an independent surveyor acceptable to Contractor.
List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
PRODUCTS (Not Used)
EXECUTION
SCHEDULE OF UNIT PRICES
Unit Price No. 01 – Mobilization:
Description: Mobilization consists of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of offices, buildings, and other facilities necessary for the work; for premiums on bond and insurance for the work; and for other operations performed or costs incurred before the beginning of work according to Division 01 Section "Mobilization" Unit of Measurement: Lump Sum (LS) Unit Price No. 02 – Bank Slope Grading:
Description: Bank Slope Grading consists of all labor, equipment and supplies to complete the following tasks according to Division 31 Section "Earth Moving”:
Establish a 5’ to 10’ wide platform area at the high-water mark designed to anchor tree boles.
Remove 1’ to 1 ½’ of topsoil from designated bank excavation area and stockpile at topsoil staging area for later use.
Pull remaining bank material from the designated bank excavation area to a rough 3:1 slope, permitting the 5’ to 10’ wide platform at the toe of the slope. Stockpile material at the designated sediment repository location.
Unit of Measurement: Lump Sum (LS) Unit Price No. 03 – Log Structure Placement:
Description: Log Structure Placement consists of all labor, equipment and supplies to trim, anchor and place tree boles along shore edge according to Division 31 Section "Earth Moving" Unit of Measurement: Each (EA) Unit Price No. 04 – Coir Placement:
Description: Coir Placement consists of all labor, equipment and supplies to complete the following tasks according to Division 31 Section "Earth Moving”:
Lay coir 70 fabric lengthwise along shore at the edge of the high-water mark. Place topsoil on shore side half of coir to lift height of 1 ½’. Allow government workers time to spread seed on topsoil. Pull remaining unburied fabric over topsoil and anchor in place with fabric stakes.
Place topsoil over freshly created 3:1 slope at a lift height of 8” to 10”. Allow government workers time to spread seed on topsoil. Lay coir 40 fabric over entire 3:1 slope. Burry top edge of coir in 1’ to 2’ trench at top of slope. Anchor all other edges of coir in place with fabric stakes.
Unit of Measurement: Lump Sum (LS)
END OF SECTION 012200
| 07/08/2022 | UNIT PRICES |
| SOUTH SHORE BANK TREATMENT | 012200-2 |
| 07/08/2022 | UNIT PRICES |
| SOUTH SHORE BANK TREATMENT | 012200-2 |
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
1. GENERAL
SUMMARY
Section includes administrative and procedural requirements for handling and processing Contract modifications.
MINOR MODIFICATIONS IN THE WORK
Contracting Officer will issue supplemental instructions authorizing minor modifications in the Work, not involving adjustment to the Contract Sum or the Contract Time
PROPOSAL REQUESTS
Government-Initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed modifications in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
Proposal Requests issued by Contracting Officer are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed modification.
Within 14 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the modification.
Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
Include costs of labor and supervision directly attributable to the modification.
Include an updated Contractor's Construction Schedule that indicates the effect of the modification, including, but not limited to, modifications in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
Contractor-Initiated Proposal Requests: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose modifications by submitting a request for a modification to Contracting Officer.
Include a statement outlining reasons for the modification and the effect of the modification on the Work. Provide a complete description of the proposed modification. Indicate the effect of the proposed modification on the Contract Sum and the Contract Time.
Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
Include costs of labor and supervision directly attributable to the modification.
Include an updated Contractor's Construction Schedule that indicates the effect of the modification, including, but not limited to, modifications in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
Comply with requirements in Division 01 Section "Product Requirements" if the proposed modification requires substitution of one product or system for product or system specified.
Proposal Request Form: Use forms provided by Contracting Officer.
MODIFICATION PROCEDURES
On Contracting Officer's approval of a Proposal Request, Contracting Officer will issue a Modification for signatures of Contracting Officer and Contractor on form included at end of Part 3.
END OF SECTION 012600
| 07/08/2022 | CONTRACT MODIFICATION PROCEDURES |
| SOUTH SHORE BANK TREATMENT | 012600-2 |
SECTION 017113 - MOBILIZATION
1. GENERAL
SUMMARY
Selection Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site. Also includes other work and operations which must be performed and/or costs incurred prior to beginning work on the components listed in the schedule of items.
1. PRODUCTS (Not Used) EXECUTION (Not Used)
MEASUREMENT AND PAYMENT
MEATHOD OF MEASUREMENT
Progress payments for Mobilization will be made as follows:
When 5% of the original contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original contract amount, whichever is the lesser will be paid.
When 10% of the original contract amount is earned from other bid items, 100% of the bid for mobilization or 10% of the original contract amount, whichever is the lesser will be paid.
BASIS OF PAYMENT
Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item 017113 – 01 Mobilization Lump Sum
END OF SECTION 017113
| 07/08/2022 | MOBILIZATION |
| SOUTH SHORE BANK TREATMENT | 017113-2 |
SECTION 312000 - EARTH MOVING
1. GENERAL
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
SUMMARY
Section Includes: Excavating and filling for rough grading the Site, placement of conifer tree boles and placement of coir fabric. See drawings for clarification.
Bank Slope Grading:
Establish a 5’ to 10’ wide platform area just above the high-water mark designed to anchor tree boles.
Remove 1’ to 1 ½’ of topsoil from designated bank excavation area and stockpile at topsoil staging area for later use.
Pull remaining bank material from the designated bank excavation area to a rough 3:1 slope, permitting the 5’ to 10’ wide platform at the toe of the slope. Stockpile material at the designated sediment repository location.
Log Structure Placement:
Parallel Logs: Parallel logs shall be placed parallel to shoreline with 2’ to 3’ overlap and root wad end pointing in the westward direction. Non-root wad end shall be placed shoreward of next log. Parallel logs shall be placed 5’ to 10’ lakeward from the high-water mark (HWM). Top of parallel log shall be placed within 2” of the HWM.
Buried Logs: Buried logs shall be placed perpendicular to shoreline with root wad end pointing toward the lake. Spacing between the buried logs shall be 25’. Cut top end of logs before placement, leaving the desired 20’ on the root wad end. Bury top end of newly trimmed log 10’ in the shore. The root wad end of the buried logs shall be snuggly keyed on top of the overlapped portion of the parallel logs.
Coir Placement:
Lay coir 70 fabric lengthwise along shore at the edge of the high-water mark. Place topsoil on shore side half of coir to lift height of 1 ½’. Allow government workers time to spread seed on topsoil. Pull remaining unburied fabric over topsoil and anchor in place with fabric stakes.
Place topsoil over freshly created 3:1 slope at a lift height of 8” to 10”. Allow government workers time to spread seed on topsoil. Lay coir 40 fabric over entire 3:1 slope. Burry top edge of coir in 1’ to 2’ trench at top of slope. Anchor all other edges of coir in place with fabric stakes.
UNIT PRICES
Work of this Section is affected by unit prices for earth moving specified in Section 012200 "Unit Prices."
DEFINITIONS
Backfill: Soil material or controlled low-strength material used to fill an excavation.
Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.
Final Backfill: Backfill placed over initial backfill to fill a trench.
Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.
FIELD CONDITIONS
Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations.
Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Government.
Provide alternate routes around closed or obstructed traffic ways if required by Government.
Utility Locator Service: Notify “Call Before You Dig” for area where Project is located before beginning earth-moving operations.
PRODUCTS
CONTRATOR FUNISHED MATERIALS
There is no contractor furnished material.
GOVERNMENT FUNISHED MATERIALS
Logs: (65) Conifers boles with a minimum length of 30 feet with or without limbs and a diameter between 12” and 20”.
Coir 70 Fabric: (10) 13’ x 87’ roles.
Coir 40 Fabric: (40) 13’ x 87’ roles.
Fabric Stakes: 1’ – 2’ assorted stakes with a minimum 1.5” x 1.5” cross section.
1. EXECUTION
EXPLOSIVES
Explosives: Do not use explosives.
EXCAVATION, GENERAL
Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.
STORAGE OF SOIL MATERIALS
Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
Stockpile soil materials away from edge of excavations.
BACKFILL
Place and compact backfill in excavations promptly.
Place backfill on subgrades free of mud, frost, snow, or ice.
GRADING
General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.
Provide a smooth transition between adjacent existing grades and new grades.
Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances.
FIELD QUALITY CONTROL
Special Inspections: Government will engage a qualified special inspector to perform the following special inspections:
Determine prior to placement of fill that site has been prepared in compliance with requirements.
PROTECTION
Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.
Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.
Scarify or remove and replace soil material to depth as directed by special inspector; reshape and recompact.
Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.
Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.
MEASUREMENT AND PAYMENT
MEATHOD OF MEASUREMENT
The work described in this section will be measured and paid for by lump sum for bank slope grading and coir placement. The quantities each log structure placement will be the actual number of these items.
BASIS OF PAYMENT
Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item
| 312000 – 01 Bank Slope Grading | Lump Sum |
| 312000 – 02 Log Structure Placement | Each |
| 312000 – 03 Coir Placement | Lump Sum |
END OF SECTION 312000
| 07/08/2022 | EARTH MOVING |
| SOUTH SHORE BANK TREATMENT | 312000-1 |