Specifications - Repair Tank Farms 3 and 4 - DRAFT.pdf

PDF 23 MB Posted

Attached to
Repair Tank Farm 3 and 4, JBER, Alaska
Solicitation number
FA500023B0001
Issued by

About this file

This pre-solicitation notice seeks bids for a construction project to repair tank farms 3 and 4 at Joint Base Elmendorf-Richardson in Alaska. The project scope includes replacing underground storage tanks and buildings at the two tank farms, constructing a new retail service station and truck fill stand, installing a product recovery tank and generator, and completing associated site work. Bids are due by May 24, 2023. The estimated value of the contract is between $10-25 million. The solicitation will be set aside for 8(a) small businesses and posted to SAM.gov on April 24, 2023. Interested firms must be registered in SAM to be eligible. Drawings can be requested from the points of contact.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Tank Farm 3 & 4

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 19 30.00 29 SPECIAL ITEMS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 36 00.00 29 RADIOACTIVE MATERIALS PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 04.00 29 CONTRACTOR QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 57 20.01 29 ENVIRONMENTAL PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 65 00 UNDERGROUND STORAGE TANK REMOVAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00 ASBESTOS REMEDIATION

02 83 00 LEAD REMEDIATION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

05 59 10 ROLLING COVER FOR AVIATION REFUELING VAULTS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 11 13 BITUMINOUS DAMPPROOFING

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 41 63 FABRICATED ROOF PANEL ASSEMBLIES

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

PROJECT TABLE OF CONTENTS Page 1

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis Specifications - Tank farms 3 and 4 - DRAFT

Repair Tank Farm 3 & 4 JBER, AK

08 11 13 STEEL DOORS AND FRAMES

08 53 00 PLASTIC WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 90 00 PAINTS AND COATINGS

09 96 00 HIGH-PERFORMANCE COATINGS

09 97 13.15 LOW VOC POLYSULFIDE INTERIOR COATING OF WELDED STEEL

PETROLEUM FUEL TANKS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 13 - SPECIAL CONSTRUCTION

13 34 19 METAL BUILDING SYSTEMS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 53.00 20 SPACE TEMPERATURE CONTROL SYSTEMS

23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL

23 31 13.00 40 METAL DUCTS

23 34 23.00 40 HVAC POWER VENTILATORS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLES

23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 26 - ELECTRICAL

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 13.00 40 MEDIUM-VOLTAGE CABLES

26 05 19.10 10 INSULATED WIRE AND CABLE

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES

26 08 00 APPARATUS INSPECTION AND TESTING

26 12 19.00 40 PAD-MOUNTED, LIQUID-FILLED, MEDIUM-VOLTAGE TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 27 14.00 10 ELECTRICITY METERING

26 28 00.00 10 MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS

26 28 21.00 40 AUTOMATIC TRANSFER SWITCHES

26 32 13.00 20 SINGLE OPERATION GENERATOR SETS

26 41 00 LIGHTNING PROTECTION SYSTEM

PROJECT TABLE OF CONTENTS Page 2

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

26 42 13.00 20 CATHODIC PROTECTION BY GALVANIC ANODES

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS

32 11 20 BASE COURSE AND SUBBASE

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

DIVISION 33 - UTILITIES

33 01 50.60 CLEANING OF PETROLEUM STORAGE TANKS

33 08 55 FUEL DISTRIBUTION SYSTEM START-UP (NON-HYDRANT)

33 09 52 FUEL PUMP CONTROL AND ANNUNCIATION SYSTEM (NON-HYDRANT)

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 40 00 STORM DRAINAGE UTILITIES

33 52 10 FUEL SYSTEMS PIPING (SERVICE STATION)

33 52 23.15 POL SERVICE PIPING WELDING

33 52 40 FUEL SYSTEMS PIPING (NON-HYDRANT)

33 52 43.11 AVIATION FUEL MECHANICAL EQUIPMENT

33 52 43.14 AVIATION FUEL CONTROL VALVES

33 52 43.23 AVIATION FUEL PUMPS

33 52 43.28 FILTER SEPARATOR, AVIATION FUELING SYSTEM

33 52 80 LIQUID FUELS PIPELINE COATING SYSTEMS

33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS

33 57 55 FUEL SYSTEM COMPONENTS (NON-HYDRANT)

33 58 00 LEAK DETECTION FOR FUELING SYSTEMS

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

SECTION 01 19 30.00 29

SPECIAL ITEMS

PART 1 GENERAL

1.1 SCOPE

Items included in this section cover special features and/or requirements which are not otherwise specified or indicated.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

ASTM INTERNATIONAL (ASTM)

ASTM E 1527 (1993) Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1926 Safety and Health Regulations for Construction

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 51B (2014) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-05 Design Data

Temporary Site Electrical Plan; G

01 19 30.00 29 Page 4

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

1.4 FIRE SAFETY

1.4.1 Fire Protection

The Contractor shall comply with local Air Force fire protection requirements and NFPA 241.

1.4.2 Welding Permit

Prior to using any flame devices or welding equipment, or performing other similar operations, Contractor personnel shall be certified to issue AF Form 592 "USAF Welding, Cutting, and Brazing Permit" (copy attached to this section). Certification training is provided by appointment and can be scheduled by contacting the Base Technical Services Office, through the Contracting Officer. If permits are required for hot work prior to attendance in the certification class, permits may be obtained from Technical Services. Work shall comply with NFPA 241, NFPA 51B, and applicable portions of 29 CFR 1910 and 29 CFR 1926.

1.5 WORK CLEARANCE AND UTILITY OUTAGES

1.5.1 Clearance Request

The Contractor shall have a properly executed , Base Civil Engineering Work Clearance Request (copy attached to this section), coordinated through the Contracting Officer and signed by the Base Civil Engineer prior to any work at the project site.

1.5.2 Utility Outages

Utility outages shall be coordinated with the Base Civil Engineer through the Contracting Officer at least 7 days prior to the planned utility interruption. Outage periods shall exclude Saturdays, Sundays and holidays.

1.6 NOT USED

1.7 TEMPORARY UTILITY SERVICES

The Government will make all reasonably required utilities available to the Contractor from existing power, and water outlets, for the Contractor's temporary use during construction at a charge to the Contractor. The Contractor shall carefully conserve any utilities furnished without charge.

The Contractor is responsible for coordinating with Doyon Utilities to extend temporary lines and for any fees and expenses associated with providing and maintaining necessary temporary connections, meters, and distribution lines. For Utility see attachment at end of this section, and verify current rates with:

Sonny Turpin griffith.turpin@elmendorf.af.mil JBER - Utilities Engineer

673 CES/CEAO

907-384-2763

The Contractor is responsible for submitting all work plans for permanent or temporary utilities to 673rd CES and 773rd CES Utilities for approval, a

01 19 30.00 29 Page 5

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis minimum of 30 working days prior to when requested services are needed.

a. The Contractor should not assume that permanent utilities will be installed to the facility at a time most convenient for the Contractor, and may want to consider obtaining access to temporary utility services. DU will extend temporary service to contractors performing work on the Installation when requested by the Government and the Contractor. The Contractor shall provide written notification to DU, copy furnish the Government, a minimum of 30 working days prior to when requested services are needed. Written notification shall be provided using Doyon Utilities' Service Application Form. As a minimum, the request will include requested date of temporary service installation, expected duration of the connection, a description of requested connection, and the name, title, and phone number of Contractor Point of Contact responsible for coordinating the temporary service connection with DU. The Contractor shall be responsible for any fees charged by DU to extend/provide temporary utility lines to project site and making any required connections to Contractor provided equipment.

b. The Contractor shall submit a Temporary Site Electrical Plan for Government and 773rd CES Utilities approval. The Contractor shall comply with all applicable rules and regulations. The temporary site electrical plan shall identify safety procedures to include lock-out/tag-out procedures, NEC and NESC safety requirements.

c. 773rd CES Utilities must review and approve plans for disinfecting and preventing contamination/cross-connection from any temporary water supply connection; and 773rd CES must operate the valve that charges/opens any temporary connection. The Contractor shall provide the documentation and coordination to facilitate these actions as applicable.

d. The Contractor shall reimburse the Government for use of temporary utility services. The Contractor shall carefully conserve any utilities furnished without charge.

e. Before completion of the work and final acceptance of the work by the Government, the Contractor shall notify the Contracting Officer in writing, 5 working days before termination is desired. The Contractor shall then remove their respective temporary distribution lines and associated paraphernalia. The Contractor shall pay all outstanding utility bills before final acceptance of the work by the Government.

1.8 DISPOSITION OF MATERIALS

Combustible and noncombustible waste material, except asbestos, shall be disposed of off-site at an authorized solid waste disposal facility. No burning will be permitted. Asbestos containing materials shall be disposed of at the Base Landfill where shown. The Contractor shall comply with applicable waste hauling requirements of the State of Alaska and the Municipality of Anchorage.

1.8.1 Salvageable Material

Salvageable material, if not otherwise indicated, shall become the property of the Contractor. The value of such salvage shall be reflected in the contract price.

01 19 30.00 29 Page 6

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

1.9 TESTS

The Contractor shall provide testing, except where specifically noted to be performed by the Government, in accordance with SECTION 01 45 04.00 29

CONTRACTOR QUALITY CONTROL.

1.10 WARRANTY OF CONSTRUCTION

Reference 00 72 00, contract clause 52.246-21 "Warranty of Construction" for additional requirements.

1.10.1 Failures

Upon receipt of notice from the Government of failure of any part of warranted items during the warranty period, the affected part or parts shall be promptly replaced. Such replacement shall include furnishing and installing the necessary new part or parts, making all necessary repairs, restoring the affected item to the operating condition specified in this contract and making all such tests as are necessary to ensure that there are no remaining defects. Such tests shall be performed in the presence of representatives of the Using Agency indicated below. Upon final acceptance of the work or transfer of responsibility to the Government for operation and maintenance of the items covered, whichever is earlier, the Contractor shall be responsible to the Using Agency for the warranty provisions of this contract. A letter stating the applicable warranty provisions shall be furnished to the Contracting Officer in duplicate, in the format and text shown in the sample letter attached to this section.

1.11 CAMP FACILITIES

There are no Government owned camp facilities at the jobsite for the Contractor's use.

1.12 TEMPORARY HEATING

EM 385-1-1, Section 09.D.02.c, requires "close surveillance" of temporary heating devices. The Contractor shall interpret this to mean "continuous monitoring during operation of the temporary heater" to ensure the proper operation of the heater and that appropriate fire prevention/response measures are taken. Continuous monitoring may be accomplished by on-site personnel, or through the use of a wired, a wireless, or in the case of steam or hydronic heating systems where combustion is taking place external to the construction, an internal monitoring system located at the source of combustion. Submit Temporary Heating Monitoring Plan for approval with Accident Prevention Plan (APP) or prior to commencement of applicable definable feature of work.

With regard to fuel combustion heaters, the following also applies: When fuel combustion heaters are used in enclosed structures, carbon monoxide (CO) shall be continuously monitored.

1.13 NON-GOVERNMENT BORROW SOURCES

The Contractor shall check any non-Government, proposed borrow sources for the presence of hazardous substances and petroleum products as defined in ASTM E 1527. The publication includes guidance on previously examined sites. A Phase I Environmental Site Assessment, also as defined therein, shall be submitted for each proposed borrow site as a supplement to the

01 19 30.00 29 Page 7

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

Environmental Protection Plan specified in SECTION 01 57 20.01 29 ENVIRONMENTAL PROTECTION. The report shall identify any previous or current presence of hazardous substances at the site, regardless of whether they have been, or can be, released to the environment. The Assessment shall be performed under the direct supervision of an independent, registered professional engineer, currently licensed by the State in which the borrow source is located, and within such time frame as will ensure reports are valid when submitted. The engineer shall have a minimum of 3 years experience in performing satisfactory Environmental Site Assessments. All reports shall be certified in writing by the engineer and submitted in the standard format specified in the referenced publication, through the Contracting Officer, to the Base Environmental Office for review. Reports shall be submitted at least 30 days prior to needing borrow materials in the work. The qualifications of the engineer performing the Assessment shall be included with the report. Where hazardous materials are indicated, use of the source will not be allowed.

No borrow materials shall be brought onto Government property without approval of the Contracting Officer. The Government reserves the right to sample and test any borrow materials delivered to the project for conformance with this specification.

1.14 WEEKLY COORDINATION MEETINGS

The Contractor shall participate in weekly coordination meetings with the Contracting Officer and other Government representatives-as applicable.

The Contractor shall be responsible for preparing the agenda in coordination with the Contracting Officer, distributing the agenda, conducting the meeting, preparing the meeting minutes, distributing the minutes, and tracking action items. The Contractor's superintendent and QC System Manager shall attend each meeting. Typical topics shall consist of but not limited to the following: review of the previous week's activities and progress; forecast of the following two week's activities and progress;

upcoming utility outage or street closure; status of shop drawing submittals and reviews; status of outstanding requests-for-information (RFI); status of pending modifications; anticipated modifications; proposed schedule changes; other concerns/and or issues.

1.15 RED ZONE MEETING

Red Zone Meeting (RZM) At approximately 75% completion, but not less than 60 days from anticipated completion, the Contractor shall participate in the RED ZONE Meeting (RZM). The Contractor shall be responsible for contributing to the agenda in support of the Administrative Contracting Officer (ACO) and the 673rd CES Project Manager. The Government is responsible for distributing the agenda, conducting the meeting, preparing the minutes, distributing the minutes, and assigning action items. The purpose of the RZM is to coordinate all of the activities leading up to project acceptance by the customer as well as completing contract and project closeout.

Items to be discussed include, but are not limited to, the following:

verify O&M manual requirements and submittal dates; review status of all outstanding submittals; verify spare parts, keys, etc.; turnover requirements and turnover dates; acceptance inspection and final acceptance; LEED documentation; identify and schedule all tests to be witnessed by Government personnel; mechanical system tests and balances;

commissioning; training sessions; preliminary as-built submittals; final as-built submittals; warranty conference; building interior inspections;

separate building exterior inspections, if necessary before snowfall; final

01 19 30.00 29 Page 8

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis utility readings; erosion control and turf requirements; installation of specialized equipment and communications infrastructure; permanent keys for building, whose responsibility and when needed; site demobilization.

Additionally the project team will discuss the processes for completing the Contractor's Release of Claims (RoC) and Contractor Performance Assessment Reporting System (CPARS). The Contractor is explicitly responsible for presenting five (5) copies of the following documents to the ACO at the RZM:

1. Current progress schedule.

2. Current punch list.

3. Schedule of all tests to be witnessed by Government.

4. In-season HVAC Testing and Balancing schedule.

The Contractor is explicitly responsible for presenting one (1) copy of the following documents to the ACO at the RZM:

1. Up-to-date Redline drawings and/or draft-final Computer Aided Design & Drafting (CADD) as-built drawings.

2. Draft of O&M manual.

3. Draft of Warranty Plan.

The RZM is also the forum for the Government Team and the Contractor to discuss any requirements for potential Final Contract Modifications to minimize the impact on the BOD and other key project milestones. The Government Team and the Contractor are jointly responsible for tracking all action items through resolution and addressing open issues in regularly scheduled management meetings following the RZM.

1.16 PROHIBITION OF DRY WELLS ON SITE

In order to comply with the Safe Drinking Water Act and ensure that any surface fluids entering the ground meet water quality standards, and to reduce potential impacts to contaminated sites managed under the RCRA/CERCLA cleanup program, JBER has established a prohibition on the construction or installation of any new Class V Underground Injection Control(UIC) wells (i.e., "dry wells"). Although JBER-Richardson recognizes that EPA is authorized to permit the installation of Class V UIC wells under certain circumstances, the installation of such wells are contrary to JBER's long-term environmental management plan. The Corps of Engineers and the JBER-Richardson jointly consider and grant exceptions to this prohibition on a case-by-case basis for those projects for which it is determined that avoidance of Class V UIC well use is technologically impracticable. Absent such an exception, no UIC well or wells may be constructed or installed under this contract.

1.17 ACCESS REQUEST

Complete the access request form attached to the end of this specification. Instructions are included.

1.18 ATTACHMENTS

a. JBER Forms

01 19 30.00 29 Page 9

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

b. Sample Letter

c. Base Access Program

d. Construction Phase Joint Risk Management

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

01 19 30.00 29 Page 10

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "L" shall be submitted through serial letter to the government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; L

Initial Project Schedule; L

Periodic Schedule Update; L

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this

01 32 01.00 10 Page 11

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

01 32 01.00 10 Page 12

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

01 32 01.00 10 Page 13

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 [Enter Appropriate Subpart Title Here]NOT USED

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

01 32 01.00 10 Page 14

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Requirements.

Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

01 32 01.00 10 Page 15

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.

3.3.11 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.3.12 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.3.13 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.3.14 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.15 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

01 32 01.00 10 Page 16

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

3.3.16 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.

3.3.17 Remaining Duration

Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.

3.3.18 Cost Loading of Closeout Activities

Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).

3.3.18.1 As-Built Drawings

If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.

3.3.18.2 O & M Manuals

Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.

3.3.19 Early Completion Schedule and the Right to Finish Early

An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.

a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.

b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.

3.4 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress

01 32 01.00 10 Page 17

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis payment can be made.

Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.

3.4.1 Preliminary Project Schedule Submission

Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code (FOW).

3.4.2 Initial Project Schedule Submission

Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.

3.4.3 Periodic Schedule Updates

Update the Project Schedule on a regular basis, monthly at a minimum.

Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE MEETINGS.

These updates will enable the Government to assess Contractor's progress.

a. Update information including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete is subject to the approval of the Government at the meeting.

b. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.

3.5 SUBMISSION REQUIREMENTS

Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:

3.5.1 Data CD/DVDs

Provide two sets of data CD/DVDs containing the current project schedule

01 32 01.00 10 Page 18

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis and all previously submitted schedules in the format of the scheduling software (e.g. .xer). Also include on the data CD/DVDs the Narrative Report and all required Schedule Reports. Label each CD/DVD indicating the type of schedule (Preliminary, Initial, Update), full contract number, Data Date and file name. Each schedule must have a unique file name and use project specific settings.

3.5.2 Narrative Report

Provide a Narrative Report with each schedule submission. The Narrative Report is expected to communicate to the Government the thorough analysis of the schedule output and the plans to compensate for any problems, either current or potential, which are revealed through that analysis. Include the following information as minimum in the Narrative Report:

a. Identify and discuss the work scheduled to start in the next update period.

b. A description of activities along the two most critical paths where the total float is less than or equal to 20 work days.

c. A description of current and anticipated problem areas or delaying factors and their impact and an explanation of corrective actions taken or required to be taken.

d. Identify and explain why activities based on their calculated late dates should have either started or finished during the update period but did not.

e. Identify and discuss all schedule changes by activity ID and activity name including what specifically was changed and why the change was needed. Include at a minimum new and deleted activities, logic changes, duration changes, calendar changes, lag changes, resource changes, and actual start and finish date changes.

f. Identify and discuss out-of-sequence work.

3.5.3 Schedule Reports

The format, filtering, organizing and sorting for each schedule report will be as directed by the Contracting Officer. Typically, reports contain Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. Provide the reports electronically in .pdf format. The following lists typical reports that will be requested:

3.5.3.1 Activity Report

List of all activities sorted according to activity number.

3.5.3.2 Logic Report

List of detailed predecessor and successor activities for every activity in ascending order by activity number.

3.5.3.3 Total Float Report

A list of all incomplete activities sorted in ascending order of total

01 32 01.00 10 Page 19

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.

3.5.3.4 Earnings Report by CLIN

A compilation of the Total Earnings on the project from the NTP to the data date, which reflects the earnings of activities based on the agreements made in the schedule update meeting defined herein. Provided a complete schedule update has been furnished, this report serves as the basis of determining progress payments. Group activities by CLIN number and sort by activity number. Provide a total CLIN percent earned value, CLIN percent complete, and project percent complete. The printed report must contain the following for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Earnings to Date, Earnings this period, Total Quantity, Quantity to Date, and Percent Complete (based on cost).

3.5.3.5 Schedule Log

Provide a Scheduling/Leveling Report generated from the current project schedule being submitted.

3.5.4 Network Diagram

The Network Diagram is required for the Preliminary, Initial and Periodic Updates. Depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:

3.5.4.1 Continuous Flow

Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.

3.5.4.2 Project Milestone Dates

Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

3.5.4.3 Critical Path

Show all activities on the critical path. The critical path is defined as the longest path.

3.5.4.4 Banding

Organize activities using the WBS or as otherwise directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by major elements of work, category of work, work area and/or responsibility.

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

With each schedule submission, provide a SVC diagram showing 1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates, and 2) Earned Value to-date.

01 32 01.00 10 Page 20

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

Conduct periodic schedule update meetings for the purpose of reviewing the proposed Periodic Schedule Update, Narrative Report, Schedule Reports, and progress payment. Conduct meetings at least monthly within five days of the proposed schedule data date. Provide a computer with the scheduling software loaded and a projector which allows all meeting participants to view the proposed schedule during the meeting. The Contractor's authorized scheduler must organize, group, sort, filter, perform schedule revisions as needed and review functions as requested by the Contractor and/or Government. The meeting is a working interactive exchange which allows the Government and Contractor the opportunity to review the updated schedule on a real time and interactive basis. The meeting will last no longer than 8 hours. Provide a draft of the proposed narrative report and schedule data file to the Government a minimum of two workdays in advance of the meeting. The Contractor's Project Manager and scheduler must attend the meeting with the authorized representative of the Contracting Officer.

Superintendents, foremen and major subcontractors must attend the meeting as required to discuss the project schedule and work. Following the periodic schedule update meeting, make corrections to the draft submission. Include only those changes approved by the Government in the submission and invoice for payment.

3.6.2 Update Submission Following Progress Meeting

Submit the complete Periodic Schedule Update of the Project Schedule containing all approved progress, revisions, and adjustments, pursuant to paragraph SUBMISSION REQUIREMENTS not later than 4 work days after the periodic schedule update meeting.

3.7 WEEKLY PROGRESS MEETINGS

Conduct a weekly meeting with the Government (or as otherwise mutually agreed to) between the meetings described in paragraph entitled PERIODIC SCHEDULE UPDATE MEETINGS for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. Use the current approved schedule update for the purposes of this meeting and for the production and review of reports. At the weekly progress meeting, address the status of RFIs, RFPs and Submittals.

3.8 REQUESTS FOR TIME EXTENSIONS

Provide a justification of delay to the Contracting Officer in accordance with the contract provisions and clauses for approval within 10 days of a delay occurring. Also prepare a time impact analysis for each Government request for proposal (RFP) to justify time extensions.

3.8.1 Justification of Delay

Provide a description of the event(s) that caused the delay and/or impact to the work. As part of the description, identify all schedule activities impacted. Show that the event that caused the delay/impact was the responsibility of the Government. Provide a time impact analysis that demonstrates the effects of the delay or impact on the project completion date or interim completion date(s). Evaluate multiple impacts chronologically; each with its own justification of delay. With multiple

01 32 01.00 10 Page 21

FXSB 17-4704 and FXSB 17-4720, Repair Tank Farms 3 and 4

Synopsis impacts consider any concurrency of delay. A time extension and the schedule fragnet becomes part of the project schedule and all future schedule updates upon approval by the Contracting Officer.

3.8.2 Time Impact Analysis (Prospective Analysis)

Prepare a time impact analysis for approval by the Contracting Officer based on industry standard AACE 52R-06.