Orange Avenue Transmission Main Improvements Project (WD-01-26)

This is a specification and bidding document issued by the Board of Public Utilities Commissioners of the City of Long Beach for the Orange Avenue Transmission Main Improvements project (MC-5265). The project involves replacing approximately 2,770 linear feet of existing 20-inch cast iron water transmission main with 22-inch high-density polyethylene (HDPE) pipe using pipe bursting installation methods, along with associated insertion and receiving pits, appurtenances, connections to existing water systems, and concrete and asphalt pavement restoration. The work site is located in the City of Long Beach along Orange Avenue between East Bixby Road and West Wardlow Road. A mandatory pre-bid conference will be held online on June 3, 2026 at 11:00 a.m., with prospective bidders required to attend. Electronic bids must be submitted through the Long Beach Buys portal by 3:00 p.m. on June 23, 2026, with a hard copy of the original bid security received at the Long Beach Utilities Department by bid opening time. The contract term is 150 calendar days from the Notice to Proceed, with no renewal options specified.

Award will be made to the lowest responsible bidder complying with all contract documents. Bid security equal to 10 percent of the total bid amount is required, with bids remaining open for 120 calendar days following bid opening. Upon contract execution, the successful bidder must furnish a performance bond and labor and material bond, each equal to 100 percent of the contract price. The work is subject to California prevailing wage requirements under Labor Code Section 1720 et seq. and is covered by a City-wide Project Labor Agreement with the Los Angeles/Orange Counties Building and Construction Trades Council. Bidders must hold a valid California Class A General Engineering Contractor license and register with the Department of Industrial Relations. Contracts exceeding $100,000 are subject to the Equal Benefits Ordinance, and contracts of $1,000,000 or more require Iran Contracting Act compliance certification. The bid document includes 20 base bid items and five optional bid items covering various construction activities, materials, and services necessary for project completion.

View the file

Other files

File Type Posted
Specifications MC-5265.pdf PDF
Addendum 1 MC-5265 UD-26-335 Orange Ave.pdf PDF
Plans MC-5265.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Long Beach Public Utilities Department

ORANGE AVENUE TRANSMISSION MAIN

IMPROVEMENTS

Contract Documents and Specifications WD-01-26

April 24, 2026

DRAWING NO. MC-5265

Board of Public Utilities Commissioners

Long Beach, California

PLANS AND SPECIFICATIONS

WD-01-26

LONG BEACH PUBLIC UTILITIES DEPARTMENT

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTS

CONTRACT DOCUMENTS

BIDDING REQUIREMENTS, CONTRACT FORMS,

CONDITIONS OF THE CONTRACT, AND

TECHNICAL SPECIFICATIONS

Prepared by:

Dudek

687 S Coast Hwy 101

Encinitas, CA 92024

Board of Public Utilities Commissioners

Long Beach, California

This information is available in an alternative format

By request to Thomas Cassidy at (562) 570-2382

SPECIFICATIONS

Approved this 19th day of May, 2026

Thomas Bekele

Senior Director of Engineering

Authorized this _______ day of _______________, 20___

B. Anatole Falagán General Manager

Approved as to Form this _________ day of _________________, 20___

Dawn McIntosh City Attorney

By: _________________________________________ Marsha Yasuda

Deputy City Attorney

6th May 26

19th May 26

Board of Public Utilities Commissioners Table of Contents Contract Documents Page i

CONTRACT DOCUMENTS

TABLE OF CONTENTS

WD-01-26

Page

PART 1 – BIDDING REQUIREMENTS

Notice Inviting Bids .............................................................................................................1-3 Instructions to Bidders ........................................................................................................1-6 Bid ................................................................................................................................... 1-12 Bidder’s Bond ....................................................................................................................1-1 Equal Benefits Ordinance Disclosure Form ........................................................................1-2 Iran Contracting Act Compliance Affidavit ..........................................................................1-1

PART 2 – CONTRACT FORMS

Bond for Faithful Performance ............................................................................................1-2 Labor and Material Bond ....................................................................................................1-2 City Policy for Minority- and Women-Owned Businesses ...................................................1-3 Information to Comply with Labor Code Section 2810 ........................................................1-1 Workers’ Compensation Certificate ....................................................................................1-1

PART 3 – CONDITIONS OF THE CONTRACT

General Conditions .......................................................................................................... 1-71 Supplementary General Conditions ....................................................................................1-2 Supplementary General Conditions (Other) ........................................................................1-1

PART 4 – TECHNICAL SPECIFICATIONS

DIVISION 01 – GENERAL REQUIREMENTS

01 10 01 Summary of Work and Sequence of Construction 01 10 03 Coordination 01 22 00 Unit Prices 01 29 73 Schedule of Values 01 31 19 Progress Meetings 01 32 00 Construction Progress Documentation 01 32 23 Construction Survey Staking 01 32 33 Construction Photographic and Video Documentation 01 33 00 Submittal Procedures 01 35 26 Government Safety Requirements 01 35 44 Environmental Procedures for Hazardous Materials 01 40 00 Quality Requirements 01 41 26 Permit Requirements 01 50 00 Temporary Facilities and Controls 01 55 26 Traffic Control and Restriping 01 57 23 Temporary Storm Water Pollution Control 01 66 00 Product Shipment Storage and Handling Requirements 01 71 13 Mobilization and Demobilization

Contract Documents Page ii

01 74 00 Cleaning and Waste Management 01 77 00 Closeout Procedures 01 78 39 Project Record Documents

DIVISION 02 – SITE WORK

02 41 14 Paving Removal and Resurfacing 02 41 15 Utility Pipeline Removal or Abandonment

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete Conforming to Greenbook Specifications ................... 1-19

DIVISION 09 – CONCRETE

09 90 00 Painting and Coating 09 96 56 Epoxy Linings and Coatings

DIVISION 31 – EARTHWORK

31 05 50 Protecting Existing Utilities 31 23 24 Controlled Low-Strength Material (CLSM) 31 23 33 Trenching and Backfilling

DIVISION 33 – SITE UTILITIES

33 01 12 Pipe Bursting for Water Mains 33 01 19 Connecting to Existing Pressure Pipelines 33 05 26 Utility Identification 33 05 31 Pipeline Joint Materials 33 05 21 Insulating Flange Kits 33 05 33 Couplings, Tie Rods, Flange Connections, and Unions 33 05 39 Manual Valve Operators 33 08 11 Hydrostatic Pressure Testing and Flushing of Water Utilities 33 11 11 Ductile Iron Pipe 33 11 13 Carbon Steel Mill Pipe 33 11 18 Cement Mortar Lining and Coating of Steel Pipe 33 11 19 Coatings, Mastic and Tape-Wrap Systems for Metal Pipe 33 11 20 Polyethylene Encasement for Iron Pipe, Fittings, Couplings, and Valves 33 11 34 High Density Polyethylene Pipe 33 12 12 Resilient-Wedge Gate Valves 33 12 14 Butterfly Valves 33 12 21 Blow-off Assemblies and Plugs 33 12 25 Air-Vacuum Water Valves 33 13 00 Disinfecting of Water Utility Distribution

PART 5 – DRAWINGS (BOUND SEPARATELY)

Contract Documents Page iii

PART 7 – APPENDICES

Appendix A Bid Protest Procedures Appendix B Sample Contract Appendix C PLA Agreement Appendix D Conceptual Traffic Control Plans Appendix E Geotechnical Report

PART 1

BIDDING

REQUIREMENTS

Board of Public Utilities Commissioners Notice Inviting Bids of the City of Long Beach Page 1 of 5

NOTICE INVITING BIDS

WD-01-26

LONG BEACH PUBLIC UTILITIES DEPARTMENT

RECEIPT OF BIDS: Bids will be accepted on behalf of the Board of Public Utilities Commissioners of the City of Long Beach, California, Owner of the Work, until 03:00 PM Tuesday, June 23, 2026 for Orange Avenue Transmission Main Improvements (WD-01-26) through the City of Long Beach’s online procurement system website (Long Beach Buys):

https://longbeachbuys.buyspeed.com/bso

The bids must be submitted electronically. Each electronic bid must be accompanied with a scanned copy of the full Bid, Bidder’s Bond, a notarized Non-collusion Affidavit, and a completed Equal Benefits Ordinance disclosure form.

A hard copy of the original Bidder’s Bond must also be received by the time of the Bid Opening to:

Long Beach Utilities Department Attn: Engineering Office Administrator 1800 E Wardlow Road Long Beach, CA 90807

In the event of a discrepancy between the line item bid schedule input in the Long Beach Buys portal and the scanned bid schedule in the specifications, the bid schedule with the lower total amount shall take precedence.

DESCRIPTION OF WORK: The Work consists of replacing approximately 2,770 linear feet of existing 20-inch cast iron water transmission main with 22-inch high density polyethylene (HDPE) pipe to be installed by pipe bursting methods, including insertion and receiving pits, appurtenances, connections to the existing water system, and concrete and asphalt concrete pavement restoration.

WORK SITE: The Work Site is located in the City of Long Beach, California along Orange Avenue between E Bixby Road and W Wardlow Road.

PRE-BID CONFERENCE: Prospective bidders are required to attend a pre-bid conference with the Long Beach Public Utilities Department (LBUD) and LBUD’s representatives. The pre-bid conference will be an online presentation of technical parameters at 11:00 AM on Wednesday June 3, 2026. The purpose will be to discuss the scope of work to be performed under these specifications. Request the pre-bid conference information by sending an e-mail to Thomas Cassidy at of the City of Long Beach Page 2 of 5 thomas.cassidy@lbwater.org and include the subject line “Orange Avenue Transmission Main Improvements Project (MC-5265): RSVP to Pre-Bid Conference”.

PROJECT LABOR AGREEMENT (PLA): This Work is covered by a City-wide Project Labor Agreement (PLA) entered into by the Long Beach Public Utilities Department with the Los Angeles/Orange Counties Building and Construction Trades Council and the signatory Craft Unions. The PLA establishes the labor relations Policies and Procedures for the City, the Contractor and subcontractors awarded contracts for the Work and for the craft persons employed by the Contractor or subcontractor while engaged in the Work. See Appendix D for the applicable PLA.

COMPLETION OF WORK: The Work must be completed within one hundred fifty

(150) calendar days after the commencement date stated in the Notice to Proceed.

OPENING OF BIDS: All Bids received in a timely manner will be subject to further evaluation with respect to:

• The responsiveness of the Bid

• Determination that Bidder is responsible

CONTRACT DOCUMENTS: Plans and specifications are available for free download through Long Beach Buys at https://longbeachbuys.buyspeed.com/bso/. However, you must be registered and logged in to submit a bid. Registration is free and may be accomplished at the same URL.

BID SECURITY: Bidders must scan and upload with their bid documents a certified check or bank draft payable to the Long Beach Public Utilities Department, drawn on a solvent bank in the United States of America, or a satisfactory bond in an amount not less than 10 percent of the Bid, to Long Beach Buys. The original of the document shall be submitted to the Long Beach Public Utilities Department in a sealed envelope and must be received and time/date stamped by the Long Beach Public Utilities Department by the time and date stated for receipt of bids. The outside of this envelope shall clearly state “Bid Security for WD-01-26, Orange Avenue Transmission Main Improvements. DO NOT OPEN WITH REGULAR MAIL.” The Long Beach Public Utilities Department is located at 1800 East Wardlow Road, Long Beach, CA 90807.

BIDS TO REMAIN OPEN: The Bidder shall guarantee the Total Bid Price for a period of 120 calendar days after the date of Bid opening.

CONTRACTOR’S LICENSE: The Contractor shall possess a valid California Class “A” General Engineering Contractor license at the time the Contract is awarded.

Failure to possess the specified license(s) will render the Bid as non-responsive.

CALIFORNIA WAGE RATE REQUIREMENTS: This project is a public work under Labor Code § 1720 et seq. Pursuant to Division 2, Part 7, Chapter 1 of the Labor Code of the State of California, the Director of Public Works of the City by and on of the City of Long Beach Page 3 of 5 behalf of the City Council has obtained from the Director of the Department of Industrial Relations of the State of California the general prevailing rate of per diem wages, and the general prevailing rate of holiday and overtime work in the locality in which the public work is to be performed for each craft, classification or type of workers needed to perform the Work. Copies of prevailing rate of per diem wages are on file in the office of the City Engineer, 5th floor, City Hall, 411 West Ocean Boulevard, Long Beach, California 90802, and shall be made available upon request. Copies may also be obtained on the California Department of Industrial Relations website http://www.dir.ca.gov/dlsr. This project will be subject the 2026-1 prevailing wage rate, as determined by the Director of the Department of Industrial Relations for the State of California. The Contractor to whom the Contract is awarded, and its subcontractors is directed to pay not less than the general rate of per diem wages for each craft, classification, or type of worker needed to execute the contract. Contractor is required to post a copy of the determination of the director of the prevailing rate of per diem wages at each job site. Contractors are required to pay at least the California minimum wage for the basic hourly rate in all cases where the published prevailing wage rate is below the California minimum wage. Any and all employer payments required by the prevailing wage determinations must also be paid. If the California minimum wage is increased in the future to an amount above that shown in the prevailing wage determination, the basic hourly rate in that determination automatically increases to the new minimum wage.

DEPARTMENT OF INDUSTRIAL RELATIONS (DIR) COMPLIANCE: This project is a public work and subject to the following: No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Contractors are further cautioned that certified payrolls shall be submitted electronically directly to the Department of Industrial Relations.

CERTIFIED PAYROLL SUBMISSION: Pursuant to the provisions of Labor Code Section 1776, Contractor shall keep and shall cause each subcontractor performing any portion of the work under this Contract to keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by Contractor or subcontractor in connection with the work. Such payroll records for Contractor and all subcontractors shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor pursuant to the provisions of Section 1776 of the Labor Code. Contractor's failure to furnish such records to the Long Beach Public Utilities Department or the Long Beach Public Utilities Department’s authorized Labor Compliance representative in the manner provided herein for notices shall of the City of Long Beach Page 4 of 5 entitle the Long Beach Public Utilities Department to withhold the penalty prescribed by law from progress payments due to Contractor.

APPRENTICESHIP EMPLOYMENT: The Contractor shall comply with Section

1777.5 of the Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under the Contractor and, by submitting a Bid and executing the Contract, the Contractor stipulates that it shall so comply. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.

EQUAL BENEFITS ORDINANCE: Bidders are advised that any contract awarded pursuant to this procurement process that exceeds $100,000 shall be subject to the applicable provisions of Long Beach Municipal Code Section 2.73 et seq, the Equal Benefits Ordinance.

NONDISCRIMINATION: The Awarded Contractor and any of its subcontractor must agree that they will not discriminate against any person in the performance of the contract and will comply with applicable federal, State and City of Long Beach, Equal Opportunity Laws, Rules and Regulations. Awarded Contractor and any of its subcontractors must agree to refrain from discriminating in employment and discriminating with respect to performance under the contract or purchase order on the basis of race, color, religion, national origin, sex, sexual orientation, gender identity, AIDS, HIV status, age, disability, or handicap, subject to federal and State laws, rules and regulations

IRAN CONTRACTING ACT: In accordance with California Public Contracting Code Section 2200-2208, all bidders submitting proposals for, entering into, or renewing contracts with the LBPUD and estimated at $1,000,000 or more are required to complete, sign and submit the “Iran Contracting Act of 2010 Compliance Affidavit” attached to this Notice Inviting Bids.

PENALTIES: Contractor and subcontractors are subject to penalties, including, but not limited to, under Labor Code §§ 1775, 1776, 1777.7 and 1813, for failure to comply with Sections 13.28 through 13.31 and/or Labor Code § 1720 et seq.

NOTICE OF INTENT TO AWARD: The notice of intent to award a contract will be posted electronically on Long Beach Buys after all bids have been reviewed and evaluated for responsiveness. Actual posting time may vary.

RETAINAGE FROM PAYMENTS: The Contractor may elect to receive 100 percent of payments due under the terms of the Contract Documents without retention of any portion of the payment by the LBUD by depositing securities of equivalent or greater value with the LBUD in accordance with the provisions of Section 22300 of the Public Contract Code. Such securities, if deposited by the Contractor, shall be valued by the of the City of Long Beach Page 5 of 5

LBUD, whose decision on valuation of the securities shall be final. Eligible securities shall be limited to those listed in Section 16430 of the Government Code, bank or savings and loan certificates of deposit, interest-bearing demand accounts, standby letters of credit, or any other security mutually agreed to by the Contractor and the

LBUD.

CONTACT: All communications relative to this Work shall be directed to the LBUD prior to opening of the bids:

Board of Public Utilities Commissioners of the City of Long Beach 1800 East Wardlow Road Long Beach, CA 90807-4931 Attention: Mr. Thomas Cassidy Telephone: (562) 570-2382 E-mail: thomas.cassidy@lbwater.org

Communications may be written or oral, but LBUD is not bound by any oral interpretation of the Contract Documents made by any City/LBUD employee, nor does LBUD guarantee the accurate transcription of oral questions.

OWNER’S RIGHTS RESERVED: The LBUD reserves the right to reject any or all bids and to waive any informality in a bid.

DATE: _________________________

OWNER: Board of Public Utilities Commissioners of the City of Long Beach

By: __________________________ B. Anatole Falagán, General Manager

Long Beach Public Utilities Department

END OF NOTICE INVITING BIDS

May 19, 2026

Board of Public Utilities Commissioners Instructions to Bidders of the City of Long Beach Page 1 of 7

INSTRUCTIONS TO BIDDERS

REQUIREMENTS AND CONDITIONS

CONTRACT DOCUMENTS

The documents that comprise the Contract Documents are set forth in the Contract, located in the Appendices, and the definition of “Contract Documents” in Article 1 of the General Conditions.

CONTRACTOR’S LICENSE

No bid will be accepted from a Bidder who is not a properly licensed contractor in the State of California. Bidders shall possess the appropriate licenses at the time the bid is submitted. Each Bidder shall record on the bid, the number and termination dates of all necessary licenses. A valid state license sufficient to qualify as the prime contractor is a pre-requisite for bidding. Necessary City licenses may be secured after the bids are opened but must be obtained prior to execution of the Contract.

BUSINESS LICENSE

The Long Beach Municipal Code (LBMC) requires all businesses operating in the City of Long Beach to pay a business license tax. In some cases the City may require a regulatory permit and/or evidence of a State or Federal license. Prior to issuing a business license, certain business types will require the business license application and/or business location to be reviewed by the Development Services, Fire, Health, and/or Police Departments. For more information, go to www.longbeach.gov/finance/business_license.

In accordance with Municipal Code (Section 3.80.210) a business license is required under the following conditions:

(a) If you are providing a service in Long Beach, CA

(b) If you are providing and delivering a product in Long Beach, CA

For more information, contact the Business License Section at 562-570-6211 or by e-mail to lbbiz@longbeach.gov.

BIDS

Bids shall be submitted online through the City of Long Beach’s procurement system, Long Beach Buys, at https://longbeachbuys.buyspeed.com/bso/.

The Contract Documents are free to download through Long Beach Buys. Bids must be submitted electronically. Bidders must be registered with Long Beach Buys.

https://longbeachbuys.buyspeed.com/bso/ of the City of Long Beach Page 2 of 7

All documents to be submitted with the bid are contained in Part 1 of this Specification;

these documents shall be scanned and uploaded with the bid, and shall include a scanned copy of the full Bid document, original Bidder’s Bond, notarized Noncollusion Affidavit, a completed Iran Contracting Act of 2010 Compliance Affidavit, and a completed Equal Benefits Ordinance form.

A hard copy of the original Bidder’s Bond must be received by the time of the Bid Opening to the address shown in the Notice Inviting Bids.

Bids shall not contain any additional description or summaries of the Work to be done, and shall not be modified in any way by bidders. Alternates will not be considered, except as called for. Bids and any requests for modifications will only be accepted via Long Beach Buys.

Bidders are cautioned that the electronic bidding system will cease allowing entry at the time stated for bid opening, regardless of when entry was begun. Bidders are reminded to begin bid submission with sufficient time to complete the entries.

Bidders shall sign the bid properly, in longhand, or by providing electronic signatures.

LBUD will not consider any bid that does not meet these requirements.

Bidders shall include with their Bids in the manner described above the security described in the Notice Inviting Bids. LBUD will reject any Bid not accompanied by such Bid Security.

VENDORS CODE OF CONDUCT

Each Bidder must adhere to the City’s Vendor Code of Conduct, including, but not limited to, disclose any existing or potential conflict of interest relative to the performance of the contractual services resulting from this Invitation to Bid. Any such relationship that might be perceived or represented as a conflict should be disclosed.

The LBUD reserves the right to disqualify any Bidder on the grounds of actual or apparent conflict of interest. The Vendor Code of Conduct can be found at https://longbeach.gov/globalassets/finance/media-library/documents/business-info/purchasing-division/final-vendor-code-of-conduct-2023

WITHDRAWAL OF BID

A Bidder may withdraw their bids electronically, through the Long Beach Buys portal anytime before Bid opening.

STATEMENTS MADE AFTER BID OPENING BUT PRIOR TO AWARD OF

CONTRACT

https://longbeach.gov/globalassets/finance/media-library/documents/business-info/purchasing-division/final-vendor-code-of-conduct-2023 https://longbeach.gov/globalassets/finance/media-library/documents/business-info/purchasing-division/final-vendor-code-of-conduct-2023 of the City of Long Beach Page 3 of 7

Bidders are cautioned that comments and statements, whether oral or written, made by LBUD employees regarding the validity of bids, the waiver of deviations from Specifications, the possibility or probability of an award being made to a particular Bidder, and other similar matters are NOT binding by the LBUD. Bidders should not order materials, obtain financing or take other actions based on such comments and statements. Only authorization of a contract by the LBUD is conclusive and binding on the LBUD with respect to this bid and its resulting contract.

BIDDERS INTERESTED IN SUBMITTING MORE THAN ONE BID

No person, partnership or corporation shall be allowed to make or file or be interested in more than one bid for the Work, unless alternative bids are called for. If multiple bids are received from the same Bidder, only the most recent bid will be accepted. A person, partnership, or corporation submitting a price to a Bidder, or who has quoted prices on material to a Bidder, is not disqualified from quoting prices to other Bidders.

INTERPRETATION OF PLANS AND OTHER DOCUMENTS

If any prospective Bidder is in doubt as to the true meaning of any part of the plans, specifications, or other Contract Documents, or finds discrepancies in, or omissions from the Plans and Specifications or other Contract Documents, the Bidder may submit to LBUD a written request for an interpretation or correction. An interpretation or correction of the documents will be made solely by LBUD by Addendum. LBUD and LBUD’s employees, agents or consultants will not be responsible for any other explanation or interpretation of the documents.

ENGINEER’S ESTIMATE OF QUANTITIES OR WORK

The quantities of work to be done and materials to be furnished are approximate as shown in the Contract Documents and are given as a basis for comparison of bid only.

LBUD does not expressly or by implication agree or represent that the actual amount of work will correspond with the Engineer’s estimates.

ADDENDA

Addenda issued in writing before the time in which to submit bids expires shall be covered in the bid and shall form a part of the Contract Documents.

NOTICE TO BIDDERS REGARDING THE PUBLIC RECORDS ACT

Responses to this Invitation to Bid will become public record upon opening of the bid(s) unless the bid or specific parts of the bid can be shown to be exempt by law.

Each Bidder may clearly label all or part of a bid as “TRADE SECRETS”, "CONFIDENTIAL", or “PROPRIETARY” provided that the Bidder thereby agrees to indemnify and defend the City for honoring such a designation. The failure to so of the City of Long Beach Page 4 of 7 label any information that is released by the City shall constitute a complete waiver of any and all claims for damages caused by any release of the information.

LBUD shall not be liable or responsible in any way for disclosure of any records not marked as “Trade Secrets”, “Confidential” or “Proprietary”. LBUD shall not be liable or responsible in any way for disclosure of any records so marked if disclosure is deemed to be required by law or by a court order.

EXISTING CONDITIONS AND EXAMINATION OF CONTRACT DOCUMENTS

GENERAL

Each Bidder shall visit the sites of construction so that the facilities, difficulties, and restrictions attending the execution of the Work are fully understood. Bidders shall thoroughly examine and be familiar with the drawings and specifications. Bidders shall carefully correlate observations with requirements of the Contract Documents and otherwise satisfy themselves of the expense and difficulties attending performance of the work. The failure or omission of any Bidder to receive or examine any Contract Document, form, instrument, addendum, or other document or to visit the sites and become acquainted with conditions there existing shall not relieve any Bidder from obligations with respect to the bid or to the Contract. The submission of a bid shall be taken as prima facie evidence of compliance with this section. Bidders shall not, at any time after submission of the bid, dispute or assert that there were any misunderstandings in regard to the nature or amount of work.

SITES

Contractor shall be responsible for identifying and setting up an area for temporary storage of materials and equipment during construction. Upon completion and acceptance of the Work, all equipment, unused materials, temporary facilities, and other miscellaneous items resulting from or used in the operations shall be removed.

The sites shall be restored to their original ground configuration by filling any pits or trenches and leveling soil piles or ruts. All stored materials and equipment shall be removed from the sites as part of demobilization upon completion of the Work.

At all times during the Work, Contractor shall keep the premises clean and orderly, and upon completion of the Work, repair all damage caused by equipment and leave the sites clear of rubbish or excess materials of any kind.

SITE INVESTIGATION AND REPRESENTATION

By submitting a Bid, the Bidder acknowledges satisfaction as to the nature and location of the Work, the general and local conditions, particularly those bearing upon availability of transportation, access to the sites, disposal, handling and storage of materials, availability of labor, water, electric power, roads, and uncertainties of weather, river stages, or similar physical conditions at the sites, the conformation and of the City of Long Beach Page 5 of 7 conditions of the ground, the character of equipment and facilities needed preliminary to and during the Work, and all other matters which can in any way affect the Work or the cost thereof.

By submitting a Bid, the Bidder further acknowledges satisfaction as to character, quality, and quantity of surface and subsurface materials to be encountered from its inspection of the sites and from reviewing any available records of other exploratory work. Failure by the Bidder to become acquainted with the physical conditions of the sites and all the available information will not relieve the Bidder from responsibility for properly estimating the difficulty or cost of successfully performing the Work.

The Bidder warrants by submitting a bid that, as a result of examination and investigation of all the aforesaid data, the Bidder can perform the Work in a good and workmanlike manner and to the satisfaction of the LBUD. The LBUD assumes no responsibility for any representations made by any of its employees, officers or agents during or prior to the execution of a Contract, unless (1) such representations are expressly stated in the Contract, and (2) the Contract expressly provides that the responsibility therefor is assumed by the LBUD.

AWARD OF CONTRACT OR REJECTION OF BIDS

AWARD

The award will be to the lowest responsible Bidder complying with the Contract Documents. Determination of low Bidder shall be based on the Total Bid Amount for the Project. The LBUD, however, reserves the right to reject any and all bids, and to waive any informality in bids received. The LBUD reserves the right to request clarification of any proposal term from a bidder. If, in the judgment of LBUD, a bid is unbalanced, it shall be considered sufficient grounds for rejection of the entire bid.

RESPONSIBILITY

Each Bidder must include in its bid a complete disclosure of any alleged significant prior or ongoing contract failures, any civil or criminal litigation or investigation pending which involves the Bidder or in which the Bidder has been judged guilty or liable.

Failure to comply with the terms of this provision will disqualify any bid. The LBUD reserves the right to reject any bid based upon the Bidder’s prior history with the LBUD, City or with any other party, which documents, without limitation, unsatisfactory performance, adversarial or contentious demeanor, significant failure(s) to meet contract milestones or other contractual failures.

Before award of the Contract, any Bidder, upon request from the LBUD, shall furnish a recent statement of the Bidder’s financial condition or such other evidence of qualifications as may be requested by LBUD. Failure to do so shall constitute grounds for rejection of the bid.

of the City of Long Beach Page 6 of 7

BONDS

The form of bonds that the Bidder, as Contractor, shall be required to execute are included in the Contract Documents and should be carefully examined by the Bidder.

The Contractor, simultaneously with the execution of the Contract, will be required to furnish a payment bond and a performance bond, each in an amount equal to one hundred (100) percent of the Contract Price. Said bonds shall be secured from a surety satisfactory to LBUD and who is authorized to transact business in California.

Said bonds shall continue in full force and effect for the guarantee period.

EXECUTION OF CONTRACT

The Contractor shall sign the Contract and return it to LBUD, together with the bonds and certificates of insurance and endorsements, within ten (10) calendar days after the mailing date of the Notice of Award. The date of commencement stated in the Notice of Award will constitute the beginning of the Contract Time. The Contract, bonds, certificates of insurance and endorsements and other documents to be executed by Contractor shall be executed and submitted in duplicate, one of which shall be filed with the LBUD and one returned to the Contractor. LBUD will issue a Notice to Proceed. The receipt of the Notice to Proceed will be authorization for Contractor to begin Work in the field and to start ordering equipment and material.

FAILURE TO EXECUTE CONTRACT OR SUBMIT INSURANCE

Failure by a Bidder to whom the Work is awarded to execute the Contract and file acceptable bonds and certificates of insurance coverage and endorsements as provided herein shall be just cause for the cancellation of the award and the forfeiture of the bid security, and shall make the Bidder liable to LBUD for all damages resulting from the failure, including reasonable attorney’s fees. The value of the bid security shall not be a limitation of damages.

The insurance certificates and endorsements included in the Contract Documents shall be completed, without alteration, to the satisfaction of LBUD, and delivered to LBUD by Contractor or Contractor’s insurance company within ten (10) days after the date of the Notice of Award. The insurance certificates and endorsements shall reflect coverage that complies with all insurance requirements in the Contract Documents.

MISCELLANEOUS

BID BREAKDOWN

Lump-sum and unit-price bid items shall be broken down as indicated on the bid form.

Contractor may be directed to provide greater detail of the items making up the Contract Price prior to submission of the first Progress Payment Request as indicated in the General Conditions.

of the City of Long Beach Page 7 of 7

CONTRACT TIME

The Contract Time shall be as set forth in the Notice Inviting Bids.

LIQUIDATED DAMAGES

Liquidated damages, if any, shall be as set forth in Article 17.5 of the General Conditions of the Contract Documents.

END OF INSTRUCTIONS TO BIDDERS

Board of Public Utilities Commissioners Bid of the City of Long Beach Page 1 of 12

BID TO THE BOARD OF PUBLIC UTILITIES COMMISSIONERS

OF THE CITY OF LONG BEACH FOR

PER SPECIFICATION WD-01-26

Name of Bidder_________________________________________________________

Street Address_________________________________________________________ in the City of __________________________ County of________________________

State of ____________ Zip Code________________ Phone No.__________________

TO: BOARD OF PUBLIC UTILITIES COMMISSIONERS OF THE CITY OF LONG

BEACH

Pursuant to and in compliance with your Notice Inviting Bids and the other documents relating thereto, the undersigned bidder, having familiarized itself with the Contract Documents, local conditions affecting the performance of the Work, and the cost of the Work at the place where the Work is to be done, hereby bids and shall perform within the time stipulated in the Contract Documents, and shall provide and furnish any and all of the labor, material, tools, expendable equipment, and all utility and transportation services necessary to perform the Work and complete, in a workmanlike manner all of the Work required in the Contract Documents, including Addenda, for the prices hereinafter set forth.

The undersigned, as Bidder, declares that the only persons or parties interested in this bid as principals are those named herein; that this bid is made without collusion with any person, firm, or corporation; and bidder shall, if the bid is accepted, execute a Contract with the Board of Public Utilities Commissioners of the City of Long Beach, and that Bidder shall accept in full payment thereof the following prices, to wit:

of the City of Long Beach Page 2 of 12

BID

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTS

PER SPECIFICATION

Furnish all labor, materials, equipment, applicable taxes, and incidentals necessary for the accomplishment of the following specific work items, each being the LUMP SUM PRICE, LINEAR FOOT PRICE, STIPULATED DOLLAR AMOUNT, OR EACH PRICE for the specific item:

Item No.

Description Size-Quantity Unit Unit Price Item Total

BASE BID ITEMS

1 Mobilization/Demobilization 1 LS $ $

2 Construction Survey Staking 1 LS $ $

3 Construction Information Signs 1 LS $ $

4 Excavation Safety Measures 1 LS $ $

5 Traffic Control 1 LS $ $

6 Replace Existing Striping 1 LS $ $

7 Project Record Documents 1 LS $ $

Concrete Pavement Removal and Replacement 10-inch Thick

15,250 SF $ $

9 Abandon Existing Blow-off Assemblies 1 EA $ $

Cold Mill (Grind) Existing Pavement 2-inch Thick

550 SF $ $

Construct AC Pavement Cap over Cold- Milled Surfaces and Construct Temporary Paving over Trench Cuts

550 SF $ $

CCTV Inspection of 20-inch Pipeline Prior to Pipe Bursting

2724 LF $ $

Pipe Bursting Insertion Pit (approx.

6’x40’)

4 EA $ $

Pipe Bursting Receiving Pit (approx.

6’x24’)

5 EA $ $

22-inch HDPE Pipe by Installed by Pipe Bursting and Open Trench

2724 LF $ $

Remove Existing 20-inch Cast Iron Pipe and Install 20-inch Cement Mortar Line and Coated Steel Pipe

51 LF $ $

17 20-inch Butterfly Valve 1 EA $ $

4-inch Lateral, Blow-off and Plug Assemblies

1 EA $ $

2-inch Manual Air Relief/Blow-off Assemblies

2 EA $ $

20 Connection to Existing Piping 1 LS $ $ of the City of Long Beach Page 3 of 12

Item No.

Description Size-Quantity Unit Unit Price Item Total

SUBTOTAL (BID ITEMS 1-20)

OPTIONAL ITEMS

21 OPTIONAL - Field Orders 1 Allowance $50,000 $50,000

22 OPTIONAL - Reimbursement for Permit Fees

1 Allowance $5,000 $5,000

OPTIONAL - Reimbursement for Modification to Owner-Provided Traffic Control Plans

1 Allowance $5,000 $5,000

OPTIONAL – Additional Underground Concrete, Slurry, or Cement-Treated Base Removal

1 Allowance $25,000 $25,000

OPTIONAL – Allowance to Excavate and Dispose of Contaminated Soils

1 Allowance $25,000 $25,000

SUBTOTAL (BID ITEMS 21-25)

TOTAL AMOUNT BID (BID ITEMS 1 Through 25) $

Signature of Bidder

Name/Title

Date

It is understood that the foregoing quantities are estimated only and are solely for the purpose of facilitating the comparison of bids, and that the Contractor’s compensation will be computed upon the basis of the actual quantities in the completed Work.

Each individual bidder shall review the Plans and Specifications, and all other portions of the Contract Documents, and shall include all items necessary to complete the Work, including the assumption of all obligations, duties, and responsibilities necessary to the successful completion of the Contract, and the furnishing of all materials and equipment required to be incorporated in and form a permanent part of the Work: tools, equipment, supplies, transportation, facilities, labor, superintendence, and services required to perform and complete the Work; and bonds, insurance and submittals; all as per the requirements of the Contract Documents, whether or not expressly listed or designated.

of the City of Long Beach Page 4 of 12

STATEMENTS BY BIDDER

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTS PER SPECIFICATION

Bidder shall indicate opposite each item listed below the name of the manufacturer and product model number proposed to be used for the Work. An award to the Bidder will not imply approval by the Owner of a manufacturer or supplier listed by the bidder. However, if a manufacturer or supplier is acceptable to the Owner, the Bidder shall furnish the items from the manufacturer or supplier indicated. Any manufacturer or supplier listed in the Contract may be substituted, changed, or omitted by the successful bidder, subject to the approval of the Owner, without subjecting the Owner to any liability for the substitution, change or omission.

The listing of any manufacturer or supplier in the Contract does not, and is not intended to grant any right, title, or interest in the Contract for the benefit of the named manufacturer or supplier. Each Bidder shall inform in writing each named manufacturer or supplier that the named manufacturer or supplier is listed for information purposes only and that the manufacturer or supplier may be substituted, changed or omitted by the Bidder in accordance with the law and subject to the approval of the Owner, without subjecting the Owner to any liability for the substitution, change or omission. The Bidder shall reimburse the Owner for any expenses incurred by the Owner as a result of the Bidder’s failure to notify each named manufacturer or supplier.

The listing of lead times for delivery is for informational purposes only and will not affect the Contract Time(s) specified herein or entitle the Bidder, who becomes the Contractor, to extensions(s) of time. The Bidder is responsible for obtaining delivery of all items at times that will ensure completion within the Contract Time(s).

A. Lead time for delivery from date of signing the Contract shall be as follows:

Item Lead Time

20-inch CML&C Steel Pipe and Fittings

22-inch HDPE DR 17 Pipe and Fittings

20-inch Butterfly Valve of the City of Long Beach Page 5 of 12

B. The Bidder intends to furnish materials supplied by the following manufacturers:

(Bidder shall list one manufacturer only for each item.)

Item Manufacturer

20-inch CML&C Steel Pipe and Fittings

22-inch HDPE DR 17 Pipe and Fittings

20-inch Butterfly Valve

C. Person who inspected site of the Work for the Bidder:

Name__________________________ Date of Inspection:__________________

Name__________________________ Date of Inspection:__________________

D. It is agreed that, if requested by the Owner, the Bidder shall furnish a notarized financial statement, references, and other information, sufficiently comprehensive to permit an appraisal of Bidder’s current financial condition.

E. The Bidder shall furnish the following information. Failure to comply with this requirement will render the Bid non-responsive and may cause its rejection.

Additional sheets may be attached if necessary.

1) Street Address ________________________________________________

2) Type of Firm: Individual _____________________________________

Partnership _____________________________________ Limited__________ General_________

Limited Liability Company__________ State___________

Joint Venture_____________________________________

Corporation _____________________________________

State of Incorporation or Partnership __________________

3) Telephone ________________________________________________ of the City of Long Beach Page 6 of 12

4) Contractor’s license: Primary Class______ Lic. No. ____________________

Supplemental classifications held, if any:_______________________________

5) DIR Public Works Contractor Registration No. ___________________________

6) Number of years as a contractor in construction work of this type:____________

7) Three projects of this complexity recently completed by the Bidder and/or the

Subcontractor(s):

a. Bidder or Subcontractors Name:

Type of Project:

Work Performed:

Contract Amount::

Date Completed:

Owners Name:

Contact Name and Phone No.:

b. Bidder or Subcontractors Name:

Work Performed:

Contract Amount::

Date Completed:

c. Bidder or Subcontractors Name:

Work Performed:

Contract Amount::

of the City of Long Beach Page 7 of 12

Date Completed:

of the City of Long Beach Page 8 of 12

ADDENDA ACKNOWLEDGMENT

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTSPER SPECIFICATION

Bidder shall signify receipt of all addenda (if any) here:

Addenda Nos.

Respectfully submitted, Bidder’s Legal Name

By ________________________________________

Title _______________________________________

Street Address

Telephone Number

Contractor’s License Number

Dated:______________________________________

NOTE: If Bidder is a corporation, the legal name of the corporation shall be set forth above, together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation, if Bidder is a partnership, the true name of the partnership shall be set forth above, together with the signature of the general partner or partners authorized to sign contracts on behalf of the partnership; if the Bidder is an individual, his/her signature shall be placed above; if the Bidder is a joint venture, the name of the joint venture shall be set forth above with the signature of an authorized representative of each venturer; if the Bidder is a limited liability company, the legal name of the company shall be set forth above with the signature of a principal authorized to bind the Company.

of the City of Long Beach Page 9 of 12

CERTIFICATION OF BIDDER’S QUALIFICATIONS

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTSPER SPECIFICATION

WD-01-26

The undersigned Bidder certifies that Bidder is, at the times of bidding, and shall be throughout the period of the Contract, licensed by the State of California to do the type of work required under the terms of the Contract Documents. Bidder further certifies that Bidder is skilled and regularly engaged in the general class and type of work called for in the Contract Documents.

The Bidder represents that Bidder is competent, knowledgeable and has special skills regarding the nature, extent and inherent conditions of the Work to be performed. Bidder further acknowledges that there are certain peculiar and inherent conditions that exist in the Work which may create, during the Work, unusual, peculiar, or unsafe conditions hazardous to persons and property.

Bidder expressly acknowledges that Bidder is aware of such peculiar risks and that it has the skill and experience to foresee and to adopt protective measures to adequately and safely perform the Work with respect to such hazards.

Furthermore, Bidder hereby certifies to the Owner that all representations, certifications, and statements made by the Bidder, as set forth in this Bid, are true and correct and are made under penalty of perjury.

Signed this _____ day of _______________, 20_____

Name of Bidder

Contractor’s License No.

Contractor’s License Expiration Date

Signature of Bidder

Title of the City of Long Beach Page 10 of 12

NONCOLLUSION DECLARATION TO BE EXECUTED

BY BIDDER AND SUBMITTED WITH BID

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTS (WD-01-26) –

DRAWING NO. MC-5265

The undersigned declares:

I am the (1) _______________ of (2) ___________, the party making the foregoing bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on (3) _________, at

(4) __________, (5) __________.

(6)_________________________________ (7)

(1) Title

(2) Name of Bidder

(3) Date

(4) City

(5) State

(6) Signature of person signing on behalf of Bidder (must be authorized to sign contracts)

(7) Printed name of person signing on behalf of Bidder of the City of Long Beach Page 11 of 12

LIST OF SUBCONTRACTORS

ORANGE AVENUE TRANSMISSION MAIN IMPROVEMENTSPER SPECIFICATION

WD-01-26

In accordance with the requirements provided in the "Subletting and Subcontracting Fair Practices Act" Division 2 Part 1, Chapter 4 of the California Public Contract Code, the Bidder shall set forth hereon the name and location of the place of business of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvement, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications, in an amount in excess of one‐half of 1 percent of the prime contractor's total bid or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one‐half of 1 percent of the prime contractor's total bid or ten thousand dollars ($10,000), whichever is greater. The prime contractor shall set forth thereon the portion of the work (type and dollar value) that will be done by each subcontractor. The prime contractor shall list only one subcontractor for each portion as defined by the prime contractor in his or her bid. Information requested, other than the sub contractor's name and location of business and the portion of work that will be done by each subcontractor may be submitted by the prime contractor within 24 hours after the deadline for submission of bids.

Name

Type of Work

Address

City

Dollar Value of Subcontract $

Phone No.

License No.

DIR Public Works Contractor Registration No.

Name Type of Work of the City of Long Beach Page 12 of 12

BIDDER’S BOND

BOARD OF PUBLIC UTILITIES COMMISSIONERS OF THE CITY OF LONG BEACH

KNOW ALL MEN BY THESE PRESENTS: That we, _______________________, as Principal, and _______________________, a corporation, organization and existing under and by virtue of the laws of…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .