This is a Request for Bid specification document issued by the Montana Department of Transportation (MDT) for the demolition and removal of state-owned property located at 2098 Old Reserve Drive in Kalispell, Montana. The project involves the complete demolition of a four-bedroom, two-bathroom residence (approximately 1,000 square feet of livable space) and an associated woodshed, with all debris removal and site restoration required. The scope of work includes abatement and disposal of identified asbestos-containing materials (ACM), removal of all structures and improvements from the property, disposal of solid waste in accordance with federal, state, and local regulations, removal of septic systems and utilities, and foundation backfill with compaction testing to achieve 98% of modified Proctor specifications. The project must be completed on or before May 31, 2026, with contractors required to obtain an Asbestos Project Permit from the Montana Department of Environmental Quality (DEQ) at least ten working days prior to commencing demolition work. No specific bidders' conference date is mentioned, though contractors are encouraged to contact the procurement officer for site access arrangements by notifying Aaron Anderson at (406) 444-0872 with five days' notice.
The contract is structured as a lump-sum service contract requiring all labor, materials, equipment, and incidental costs to be included in a single bid price. Bid security of 10% of the total bid amount is required for estimates exceeding $25,000, and performance bonds equal to 100% of the contract total are required for contracts exceeding $50,000; all bonds must be from Montana-licensed surety companies with a Best's rating of no less than A-. The contractor must possess current licenses and accreditations for asbestos abatement work as required by Montana's Department of Environmental Quality and current registration with the Montana Department of Labor and Industry. The project is subject to prevailing wage rates, FHWA compliance, federal regulations regarding lead-based paint and asbestos handling (29 CFR 1926.59, 29 CFR 1926.62, and 40 CFR Parts 266-299), and state regulations under Montana Administrative Rules Title 17 Chapter 53. Payment will be rendered upon satisfactory inspection of the completed work by MDT or a third-party inspector, with no advance payments issued prior to verification of contract compliance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Prevailing Wage Rates.pdf | ||
| 1370223-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2701 Prospect ▪ PO Box 201001 Helena MT 59620-1001
Christopher Dorrington, Director
REQUEST FOR BID – HOUSE WITH ASBESTOS DEMOLITION
Location: 2098 Old Reserve Drive, Kalispell
| Subject: | Project ID: STPS 547-1(14)0 | |
| Project No.: 8134-014-000 | ||
| Designation: Old Reserve-NW of Kalispell | ||
| Parcel No.: 07 |
Background:
STPS 547-1(14)0, Old Reserve-NW of Kalispell, Parcel 22
The house located at 2098 Old Reserve Drive will either need to be demolished as part of an upcoming MDT reconstruction of Old Reserve Drive.
The improvements include an old schoolhouse turned into a 4-bedroom, 2-bathroom residence and woodshed. The house is the farthest north on the property, and the woodshed is southeast of the house. The house and woodshed have been checked as historical, and they are both NOT historical.
The square foot livable is considered 1,000 square feet. The main floor is 784 square feet, and the second floor is an additional 216 square feet. There are four bedrooms and two bathrooms. It does contain a woodstove.
The single-family residence is comprised of an original structure which has been heavily renovated and added to. The residence is built from dimensional lumber, structural support and framing. The interior of the building is finished with a variety of vinyl sheet flooring, vinyl floor tiles, wood tongue & groove flooring, rolled carpeting. The interior walls & ceilings are covered with a combination of gypsum board systems installed at different dates. Small sections of original plaster on wood and lathe are present & have been covered with newer gypsum board ceiling coverings and/or wall coverings. Multiple types of insulation materials are present within the attic and wall cavities, predominantly the building is insulated with varying types of fiberglass insulation. The structure is heated with a central cast iron fireplace and supported with baseboard electric heaters throughout the residence.
There are other structures on the property that will not be affected by the project and so they were not inspected and are not included in this project.
There is a shop, a metal shop, and a barn on the property that do not require demolition. Demolition is limited to the Residence and Log Shed (See Figure 1).
Figure 1:
Hazardous Materials and Asbestos Inspection
On behalf of MDT, GEM Environmental conducted an asbestos inspection on May 29, 2025. The following asbestos containing materials (ACM) were identified and are summarized below:
Eleven (11) HAs of Confirmed ACM (determined to be >1% asbestos) were identified and are summarized below:
· M1.2/S3.2: Drywall system (M1.2) (mud, tape, gypsum board) with 2% Chrysotile Identified in the Mud Layer, and associated smooth texture (S3.2) with 2% Chrysotile Identified. The drywall system and associated texture is located over the walls & ceilings in rooms 07, & 06. The materials are considered RACM, with approximately 1050 Square feet present.
· M1.3/S3.3: Drywall System (M1.3) (mud, tape, gypsum board), with 2% Chrysotile identified in the mud layer, and associated smooth texture (S3.3) with 2% Chrysotile identified. The drywall system and associated texture is located over the walls in room 02. The materials are considered RACM, with approximately 400 square feet.
· M1.4/S3.4: Drywall System (MM1.4) (mud, tape, gypsum board) with 2% Chrysotile identified in the mud layer, and a associated light popcorn texture (S3.4) which contains 2% Chrysotile asbestos. The drywall system and associated texture is installed as the ceiling cap in room 02. The material is RACM, with approximately 150 Square feet present.
· M1.5/S3.5: Drywall System (M1.5) (Mud, tape, gypsum board) with 2% Chrysotile identified in the mud layer, and associated smooth texture (S3.5) which contains 2% Chrysotile asbestos. The drywall system and associated texture is installed as wall and ceiling coverings in room 01. The material is RACM with approximately 450 square feet present.
· M1.5/S3.5: Drywall System (M1.6) ( Mud, tape, gypsum board) with 2% Chrysotile Identified in the mud layer, and associated smooth texture installed which contains 2% Chysotile asbestos. The drywall system and associated texture is located over the walls in rooms 04 & the walls and ceilings in room 05. The material is RACM with approximately 3000 square feet present.
· F3.1: 9x9 vinyl floor tiles, green with beige streaks with associated black mastic. With 5% Chrysotile asbestos identified in the floor tile & no asbestos detected by PLM in the black mastic layer. The vinyl floor tile system is located in rooms 01, 01-closet, 02, 02-closet, 03, 03-closet, & 04. The material is exposed in the closets, and underneath the rolled carpeting in 04. The material is assumed to be present below the wood tongue and groove flooring throughout rooms 01 & 02. The material is CAT I, with 1350 square feet present.
· M10.1: cement asbestos board, with 15% Chrysotile asbestos. Associated with the central cast iron fireplace located in room 04. The cement asbestos board is installed as a heat shield. Behind and below the fireplace. (it is installed behind the brick & grout system).
· M7.1: Window glazing, with detectable asbestos mineral fibers reported as <1% Chrysotile by PLM analysis. Is assumed to contain >1% asbestos mineral fibers and is considered RACM. Supplemental point count analysis of the material was not completed by the laboratory by error (per verbal with CEI). Since no point count data is available, the material is assumed to be >1% and is ACM. The white window glaze is present on the exterior window systems located in rooms 05 & 07 only. With approximately 65 Square feet present.
· R10.1: Hard grey caulk applied to the chimney roof penetration is assumed to contain greater than 1% chrysotile asbestos and is ACM. Approximately 3 square feet of the material is present.
MDT has done its due diligence to ensure that the structures have been inspected for the presence of asbestos. the Contractor is required to stop work immediately and notify the Remediation and Assessment, Aaron Anderson, with MDT’s Environmental Services Bureau at (406) 444-0872 if any suspicious materials not previously identified in the report are found or if the Contractor has any question(s) regarding Environmental issues related to this contract.
The asbestos inspection identified materials with lead based and lead containing surfaces. Contractor shall review the results, defined within the attached inspection report. Be familiar with and perform all work in accordance with all applicable standards provided in the Code of Federal Regulations, Title 29 Part 26, including the OSHA Hazard Communication Standard (29 CFR 1926.59), the OSHA Lead Standard (29 CFR 1926.62), and the OSHA Respiratory Standard (29 CFR 1926.134); the Resource Conservation and Recovery Act (40 CFR Parts 266-299), and Administrative Rules of Montana Title 17 Chapter 53. To obtain copies of the Federal regulations, contact the U.S. Governments Printing Office at (202) 783-3238. Questions concerning state regulations or to obtain copies of state regulations, contact the Montana Department of Environmental Quality, Hazardous Waste Program at 406-444-5300. Contractor will be entirely responsible for all health and safety requirements for workers when cutting and handling any material coated with lead-based paint.
DEQ requires that the Contractor always have a copy of the asbestos report with them on the work site.
Please refer to Figures 2-4 for the locations of Identified ACM.
Figure 2:
Figure 3:
Figure 4:
Sope of Work:
Demolition and removal of state owned house, woodshed, and improvements at the property at 1763 Old Reserve Drive, Kalispell.
CODE AND PERMIT REQUIREMENTS
1.1 Successful Contractor agrees that all work performed because of award of the project detailed herein shall meet or exceed all applicable city, county, state, and federal codes. Failure to research said codes will not relieve the successful Contractor of his/her responsibility regarding code compliance. The Contractor shall be responsible for all required permits, licenses, fees, and inspections associated with the project.
1.2 An Asbestos Project Permit and Demolition Acknowledgement Application must be filed with the Montana Department of Environmental Quality (DEQ) at least ten (10) working days prior to the start of demolition. Working days are Monday through Friday (includes holidays) but do not include the day the Permit is received by the DEQ.
1.3 No work may be initiated until this completed permit that has been vetted and approved by DEQ has been supplied to MDT.
1.4 Contractor is responsible for the abatement and disposal of identified ACM materials as part of the demolition.
SPECIFICATIONS FOR WORK
2.1 Provide all labor, materials, equipment, and incidentals necessary for the abatement/demolition/removal of the structures, which were acquired on the following highway project.
2.2 Demolition of the residence and log shed is required.
2.3 WORK SHALL CONSIST OF, BUT NOT LIMITED TO THE FOLLOWING:
2.3.1. The successful Contractor must remove the buildings and/or obstruction (and everything contained within it) from the state-owned land identified as 2098 Old Reserve in Kalispell MT on or before 5/31/2026.
If the above deadline is not met the successful Contractor will forfeit their bid and/or Contract Performance Security Bond(s).
2.3.2. All combustible material must be removed from the site. There will be no burning or incineration of waste materials on the project site. There will be no burying of salvage material on the project site. All solid waste, trash and rubbish must be hauled off the site, leaving the site in a neat condition.
2.3.3. The disposal of all solid waste will be done by the Contractor and all disposals must be done in accordance with Federal, State and Local laws and policies. The Contractor is responsible for determining how much material is present, that needs to be disposed of and may drill holes or dig around the edge of the areas when making their determination. All crawlspace or open holes must be filled in, graded, and contoured to ground level.
2.3.4 Materials with LCP/LBP coatings should be handled in accordance with applicable OSHA worker protection and EPA disposal regulations. LCP/LBP coatings should be left substantially intact during removal and disposal activities, as feasible, to reduce the potential for worker exposure and/or environmental contamination. Materials coated with LCP/LBP should not be impacted by grinding, cutting with a torch, etc.
| 2.3.5 | Contractor shall be responsible for the Project Design and for performing the abatement work in accordance with all applicable State and Federal regulations. All quantities are estimated based on rough field measurements. Contractor shall be responsible for verifying all quantities. Bids shall be based on Contractor's verified quantities of materials. |
| 2.3.5.1 | Contractor responsible for obtaining asbestos project permit from the Department of Environmental Quality (DEQ). Permit must be filled and submitted to DEQ at least two weeks prior to the start of work. |
| 2.3.5.2 | Contractor shall be responsible for the disposal of the asbestos containing waste at a licensed disposal facility accepting such waste. |
| 2.3.5.3 | Contractor shall be responsible for the cleanup and decontamination of all surfaces in the designated areas. A 3rd party may conduct clearance to verify site is clean of ACM. |
2.3.6 Non ACM material may be salvaged at the contractor’s discretion. Contractor acknowledges by salvaging materials, they assume ownership of materials and releases the State of Montana and its employees from all claims, maintenance, repair, disposal feels, environmental liabilities, injuries, and damages regarding any future use of materials salvaged from the property.
2.3.7 All asphalt, concrete flatwork and foundations must be removed from the site and disposed of in accordance with Federal, State, and local laws. All basements or open holes must be filled in, graded, and contoured to ground level.
2.3.8 Contractor responsible for removing septic tank and associated lines.
2.3.9 The Department is not responsible for any vandalism, theft, or damage to the properties (as listed in the bid) after the date of the site inspection. These are abandoned properties and are not monitored or secured in any way. There is no guarantee, stated or implied, that the property as viewed at the site inspection will be the same as when the Contractor starts demolition. During work, contractor is responsible for own security.
2.3.9.1 This work is the supply, placement, and compaction for backfilling the removed foundation as described in the contract or shown on the plans.
2.3.9.2 Provide material for foundation backfill consisting of a well-grade sand gravel, free of organic and other deleterious materials, meeting the ASSHTO M 145 requirements for A-2-4 group classifications of better with 100% passing the 8-inch sieve.
2.3.9.3 Provide compaction equipment meeting the following minimum requirements:
2.1.9.2.1 Single Drum vibratory roller
2.1.9.2.2 Operating weight of 16,000 lbs.
2.1.9.2.3 90 horsepower measured at the flywheel
2.1.9.2.4 During placement and compaction of subgrade apply water as necessary to aid in compaction.
2.1.9.2.5 Scarify and re-compact the subgrade after foundation removal to a depth of 4 inches. Roll the subgrade a minimum of two passes before placing fill.
2.1.9.2.6 Place foundation backfill in no greater than 8-inch loose lifts. Roll each lift with the specified compaction equipment a minimum of three passes before placing the next lift.
2.1.9.2.7 Continue placing fill until the foundation backfill is even with the existing grade after the specified compaction.
2.1.9.2.8 If rutting occurs from construction equipment on the compacted foundation backfill, increase compaction equipment passes to four. Ruts are defined as gaps greater than 2 inches as measured from a rod placed across the wheel or track path.
2.1.9.2.9 Follow MDT test methods for compaction with nuclear gauges and MDT specification for embankment testing which will be 98% compaction. Follow proctor test method MT 230 for moisture density relations of soils using a 10 lb rammer as necessary to develop a curve on the material that will be used. A 6A, 7A, or other fill material may be used. Refer to Standard Specifications Section 203.
2.1.9.2.10 Alternate construction. Place foundations backfill in no greater than 8-inch loose lifts, and pact to 98% of the modified proctor plus or minus 2% of the optimum moisture content. Provide compaction testing documentation to Rex Romero, the Kalispell District Materials Lab Supervisor, 85 5th Avenue East North, Kalispell MT 59903. His office phone number is (406) 751-2026.
2.1.9.2.11 Foundation backfill will be measured by the neat line cubic yard with no allowance for shrink or swell. Compaction is not measured for payment: include compaction and foundation backfill in the project cost.
2.1.9.2.12 The Contractor must contact Rex Romero at least 5 business days prior to beginning the foundation backfill.
2.1.9.2.13 Contractor must place a minimum of 4” of soil capable of supporting plant growth over the compacted foundation backfill.
2.1.9.2.14 No interest in the land upon which the structure is situated will pass to the Contractor.
2.3.10 It is believed there are no utilities connected to the structure; however, it is ultimately the Contractor’s responsibility to verify and make sure the utilities (water, sewer, & electricity) have been properly disconnected (Northwestern Energy: (888)467-2669).
2.3.11 Contractor responsible for verifying all estimates. Contractor is encouraged to visit the site to verify estimates and evaluate existing conditions. The improvements on 2098 Old Reserve Drive may be accessed with five days notification. Contact Aaron Anderson at 406 444 0872 to arrange for key pick up and drop off, which will occur at the MDT Kalispell facility at 85 5th Avenue East North.
2.3.12 The Contractor MUST leave the Site as neat and safe as is feasibly possible at the end of each workday. Any open holes MUST be fenced to prevent people or animals from falling into the holes at the end of each workday.
2.3.13 The Contractor is responsible for installing and maintaining appropriate traffic control devices when removing and transporting material from the site.
2.3.14 When the improvements have been removed and the Site cleaned up, Contractor must submit claim for payment to Montana Department of Transportation, Real Estate Services Section, PO Box 201001, Helena, MT 59620-1001.
2.3.15 The Department will inspect site and disburse payment upon a satisfactory inspection, which may involve a 3rd party inspector. No payments will be made prior to inspection of site and verification that all requirements of the contract have been met.
CONDITIONS
Upon selection of successful bidder and prior to commencement of work, contractor will provide to MDT current licenses and accreditations for conducting asbestos abatement work , as required by the State of Montana, Department of Environmental Quality (DEQ).
CHOOSE THE SECTIONS BELOW BASED ON THE ESTIMATE AMOUNT ON THE REQUISITION. THESE SECTIONS WILL BE LISTED IN THE PREREQUISITES IN EMACS.
· Any estimate over $25,000 requires a bid bond
· Any estimate over $50,000 requires a bid bond and a performance bond
1.1. BID/PROPOSAL SECURITY – SURETY BONDS ONLY (OVER $25,000)
Each bid/proposal must be accompanied by bid proposal security based upon 10% of the total bid/offer. This security must be in the form of a surety bond licensed in Montana with a Best's rating of no less than A-. The surety bond must be supplied on one of the two forms designated by the Montana Department of Transportation. The required forms may be found at: http://www.mdt.mt.gov/publications/forms.shtml#hig and entitled “Bid Bond”, or at http://gsd.mt.gov/ProcurementServices/procurementforms and entitled "Bid or Proposal Bond.
“THE ORIGINAL FORM MUST BE PROVIDED. FACSIMILE, ELECTRONIC OR PHOTOCOPIES ARE NOT ACCEPTABLE”.
Failure on the part of the Contractor to provide the bid security on either of the forms as designated by the Montana Department of Transportation will result in bid disqualification.
A bidder failing or refusing to enter into any awarded contract or purchase order within the required 10 working days following the Purchasing Services Section's issuance of request for documents notice shall forfeit the bid security. See Section 18-1-204(1), MCA. "Enter into any contract or purchase order" includes execution of the contract, submission of acceptable performance security and submission of any required liability insurance coverage and workers' compensation insurance coverage or exemption.
The bid security for the unsuccessful bids will be shredded unless return is requested.
1.2. CONTRACT PERFORMANCE SECURITY – SURETY BONDS ONLY (OVER $50,000)
The Contractor must provide contract performance security based upon 100% of the contract total. This security must be in the form of a surety bond licensed in Montana with a Best's rating of no less than A-. The surety bond must be supplied on the form designated by the State of Montana. The required form may be found at http://gsd.mt.gov/ProcurementServices/procurementforms and entitled "Contract Performance Bond." THE ORIGINAL FORM MUST BE PROVIDED. FACSIMILE ELECTRONIC OR PHOTOCOPIES ARE NOT ACCEPTABLE.
The contract performance security must be provided to the State of Montana within 10 working days from the Request for Documents Notice. This security must remain in effect for the entire term of the contract. A new surety bond must be issued to the State of Montana if this contract is renewed.
The original surety bond form must be provided to the following address: Purchasing Services Section, Attn: Richele Parkhurst, 424 Morey Street, Billings, MT 59101.
Ref: MCA Title 18, Chapter 4, Part 3; ARM, Title 2, Chapter 5, Sub-Chapter 5.
| Environmental Services Bureau | |
| Phone: | (406) 444–7228 |
| Fax: | (406) 444–7245 |
| An Equal Opportunity Employer | |
| Rail, Transit and Planning Division |
TTY: (800) 335–7592
Web Page: www.mdt.mt.gov
| Environmental Services Bureau | |
| Phone: | (406) 444–7228 |
| Fax: | (406) 444–7245 |
| An Equal Opportunity Employer | |
| Rail, Transit and Planning Division |
TTY: (800) 335–7592
Web Page: www.mdt.mt.gov image4.tmp image5.tmp image6.tmp image7.tmp image1.tmp image2.tmp image3.tmp image8.emf
File details come from the government source that posted it. Updated .