Specifications.pdf

PDF 26 MB Posted

Attached to
Flooring Replacement & Related Work
Solicitation number
2026-18
Issued by
Hartford County, Connecticut

About this file

This is a project manual and technical specifications document for the Town of Berlin, Connecticut, related to flooring replacement and related work at Berlin High School located at 139 Patterson Way, Berlin, CT (Bid No. 2026-18). The project involves selective demolition of existing flooring, moisture mitigation installation, and replacement of floor tiles across approximately 115,000 square feet of the school building. The scope includes removal of vinyl composite tile (VCT) flooring found to contain mold growth based on a Wiss, Janney, Elstner Associates (WJE) investigation report dated April 28, 2025, installation of moisture vapor emission control systems, and placement of new Tarkett VCT II flooring with rubber base. A pre-bid conference is scheduled for Thursday, March 26, 2026, at 3:00 p.m. at Berlin High School, with electronic sealed bids due via the Town's OpenGov Procurement portal by 2:00 p.m. on Tuesday, April 7, 2026. The contractor must commence work within ten days of contract signing and substantially complete the project by August 15, 2027, prior to the 2027-2028 school year commencement. Work is constrained to periods when the school is not in session, primarily June 15 through August 15 of 2026 and 2027, with all disruptions completed before school operations resume.

The contract requires a bid bond equal to 5 percent of the bid amount and performance and labor payment bonds each equal to 100 percent of the contract sum from a Connecticut-authorized surety company. The contractor must maintain commercial general liability insurance with limits of $2,000,000 per occurrence and $3,000,000 general aggregate, automobile liability insurance of $1,000,000 per accident, workers' compensation at statutory limits, and employers' liability insurance with $500,000 per accident limits. The Town of Berlin is exempt from Connecticut sales and use taxes, and the contractor shall not include such taxes in the bid. The flooring product specified is Tarkett VCT II with a manufacturer-extended 20-year limited warranty issued March 10, 2026. Prevailing wage rates established by the Connecticut Department of Labor apply to all mechanics, laborers, and workers on the project, with rates effective as of March 13, 2026, subject to annual adjustments each July 1st for the contract duration. All employees performing construction work must provide proof of completion of a minimum 10-hour OSHA construction safety and health course. The project is subject to Connecticut General Statutes Section 31-53 prevailing wage requirements and includes affirmative action and non-discrimination provisions applicable to state-funded public works projects.

View the file

Other files

File Type Posted
Flooring_Replacement_&_Related_Work.pdf PDF
Flooring_Replacement_&_Related_Work.pdf PDF
Drawings.pdf PDF
Drawings.pdf PDF
Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual &

Technical Specifications

FLOORING

REPLACEMENT &

RELATED WORK

BERLIN HIGH SCHOOL

139 PATTERSON WAY

BERLIN, CT

Bid No.: 2026-18

MARCH 11, 2026

15 MASSIRIO DRIVE SUITE 101

BERLIN, CONNECTICUT

TEL 860 828 9221 FAX 860 828-9223

Project Manual &

Technical Specifications

FLOORING

REPLACEMENT &

RELATED WORK

BERLIN HIGH SCHOOL

139 PATTERSON WAY

MARCH 11, 2026

PREPARED BY:

ARCHITECT:

JACUNSKI HUMES ARCHITECTS, LLC

15 MASSIRIO DRIVE

SUITE 101

BERLIN, CT 06037

TEL 860-828-9221

INTERIOR DESIGNER:

4D DESIGN & DECORATING, LLC

26 STUART DRIVE,

BLOOMFIELD, CT 06002

TEL (860) 716-2363

INDEX

FLOORING REPLACEMENT & RELATED WORK

BERLIN HIGH SCHOOL

139 PATTERSON WAY

PROJECT MANUAL

Index List of Drawings Invitation to Bid

Bidding Documents:

AIA Document A701-2018 - Instructions to Bidders Supplementary Instructions to Bidders Proposal

Contract Conditions and Forms:

AIA Document A105 - Standard Short Form of Agreement Between Owner & Contractor AIA Document A101 – Exhibit A Insurance and Bonds AIA Document A201 - General Conditions of the Contract for Construction Berlin High School Flooring Investigation Report by WJE Associates dated April 28, 2025 Connecticut Department of Labor - Prevailing Wage Rates

SPECIFICATIONS

DIVISION 1 - GENERAL REQUIREMENTS

01 01 00 SPECIAL CONDITIONS

01 04 00 PROJECT COORDINATION

01 10 00 SUMMARY OF WORK

01 30 00 SUBMITTALS AND PRODUCT SUBSTITUTIONS

01 74 00 WARRANTIES AND BONDS

TARKETT 20-YEAR LIMITED WARRANTY DOCUMENT ON FLOORING,

DATED MARCH 10, 2026

01 77 00 CLOSEOUT PROCEDURES

DIVISION 2 – SITEWORK

02 07 00 SELECTIVE DEMOLITION

DIVISION 9 - FINISHES

09 05 61.13 MOISTURE VAPOR EMISSION CONTROL

09 65 00 RESILIENT FLOORING AND BASE

END OF INDEX

LIST OF DRAWINGS

139 PATTERSON WAY

DRAWING NO. DRAWING TITLE

COVER SHEET

A-1 FIRST FLOOR PLAN AREA A

A-2 FIRST FLOOR PLAN AREA B

A-3 SECOND FLOOR PLAN AREA A

A-4 SECOND FLOOR PLAN AREA B

F-0 FINISH SCHEDULE & PATTERN PLAN DETAILS

F-1 FIRST FLOOR FINISH PLAN AREA A

F-2 FIRST FLOOR FINISH PLAN AREA B

F-3 SECOND FLOOR FINISH PLAN AREA A

F-4 SECOND FLOOR FINISH PLAN AREA B

END OF LIST OF DRAWINGS

INVITATION TO BID

139 PATTERSON WAY

BID #2026-18

The Town of Berlin is seeking qualifications and cost proposals from qualified firms for moisture mitigation, flooring replacement and related work at the Berlin High School.

Electronically sealed responses will be accepted via the Town’s OpenGov Procurement portal until 2:00 p.m. Tuesday, April 7, 2026, at which time they will be automatically opened.

Solicitation forms, project plans, and specs are available online at https://procurement.opengov.com/portal/berlinct. Interested bidders can create a free account to access bid documents and submit a bid.

Additionally, a link to our procurement portal can be found on the Town’s website www.berlinct.gov under “Departments” then selecting “Purchasing.” We do not accept submissions via e-mail or fax.

A Pre-Bid Conference will be held on Thursday, March 26, 2026, at 3:00pm, at Berlin High School, 139 Patterson Way, Berlin, CT. It is recommended that all Bidders attend.

Each proposer is responsible for checking the Town’s procurement portal to determine if the Town has issued any addenda and, if so, to complete its proposal in accordance with the RFP as modified by the addenda. The Town will reject proposals received after the date and time noted above.

As security, each Bid must be accompanied by a Bid Bond having as surety thereto, such Surety Company or Companies as are authorized to do business in the State of Connecticut, of an amount not less than 5% of the Bid.

The successful Bidder shall furnish Performance, Labor and Material Payment Bonds, each for 100% of the Contract Sum.

Bidders shall not include Federal Excise or State of Connecticut Sales Tax to which Public Buildings are exempt. After opening of the Bids, no Bid can be withdrawn for a period of sixty

(60) days.

The Town reserves the right to amend or terminate this Request for Proposals, accept all or any part of a proposal, reject all proposals, waive any informalities or non-material deficiencies in a proposal, and award the proposal to the proposer that, in the Town’s judgment, will be in the Town’s best interests.

Michael S. Ahern, P.E.

Director of Public Works

Town of Berlin

Document A701

– 2018 Instructions to Bidders

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

FEDERAL, STATE, AND LOCAL

LAWS MAY IMPOSE

REQUIREMENTS ON PUBLIC

PROCUREMENT CONTRACTS.

CONSULT LOCAL AUTHORITIES

OR AN ATTORNEY TO VERIFY

REQUIREMENTS APPLICABLE TO

THIS PROCUREMENT BEFORE

COMPLETING THIS FORM.

It is intended that AIA Document G612™–2017, Owner’s Instructions to the Architect, Parts A and B will be completed prior to using this document.

for the following Project:

(Name, location, and detailed description)

Berlin High School Flooring Replacement Berlin High School 139 Patterson Way, Berlin, CT Removal, moisture mitigation and replacement of existing floor tiles

THE OWNER:

(Name, legal status, address, and other information)

Town of Berlin 240 Kensington Road Berlin, CT

THE ARCHITECT:

(Name, legal status, address, and other information)

Jacunski Humes Architects, LLC 15 Massirio Drive, Suite 101 Berlin, CT

TABLE OF ARTICLES

1 DEFINITIONS

2 BIDDER’S REPRESENTATIONS

3 BIDDING DOCUMENTS

4 BIDDING PROCEDURES

5 CONSIDERATION OF BIDS

6 POST-BID INFORMATION

7 PERFORMANCE BOND AND PAYMENT BOND

8 ENUMERATION OF THE PROPOSED CONTRACT DOCUMENTS

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

ARTICLE 1 DEFINITIONS

§ 1.1 Bidding Documents include the Bidding Requirements and the Proposed Contract Documents. The Bidding Requirements consist of the advertisement or invitation to bid, Instructions to Bidders, supplementary instructions to bidders, the bid form, and any other bidding forms. The Proposed Contract Documents consist of the unexecuted form of Agreement between the Owner and Contractor and that Agreement’s Exhibits, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, all Addenda, and all other documents enumerated in Article 8 of these Instructions.

§ 1.2 Definitions set forth in the General Conditions of the Contract for Construction, or in other Proposed Contract Documents apply to the Bidding Documents.

§ 1.3 Addenda are written or graphic instruments issued by the Architect, which, by additions, deletions, clarifications, or corrections, modify or interpret the Bidding Documents.

§ 1.4 A Bid is a complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.

§ 1.5 The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents, to which Work may be added or deleted by sums stated in Alternate Bids.

§ 1.6 An Alternate Bid (or Alternate) is an amount stated in the Bid to be added to or deducted from, or that does not change, the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, is accepted.

§ 1.7 A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, as described in the Bidding Documents.

§ 1.8 A Bidder is a person or entity who submits a Bid and who meets the requirements set forth in the Bidding Documents.

§ 1.9 A Sub-bidder is a person or entity who submits a bid to a Bidder for materials, equipment, or labor for a portion of the Work.

ARTICLE 2 BIDDER’S REPRESENTATIONS

§ 2.1 By submitting a Bid, the Bidder represents that:

.1 the Bidder has read and understands the Bidding Documents;

.2 the Bidder understands how the Bidding Documents relate to other portions of the Project, if any, being bid concurrently or presently under construction;

.3 the Bid complies with the Bidding Documents;

.4 the Bidder has visited the site, become familiar with local conditions under which the Work is to be performed, and has correlated the Bidder’s observations with the requirements of the Proposed Contract Documents;

.5 the Bid is based upon the materials, equipment, and systems required by the Bidding Documents without exception; and

.6 the Bidder has read and understands the provisions for liquidated damages, if any, set forth in the form of Agreement between the Owner and Contractor.

ARTICLE 3 BIDDING DOCUMENTS

§ 3.1 Distribution § 3.1.1 Bidders shall obtain complete Bidding Documents, as indicated below, from the issuing office designated in the advertisement or invitation to bid, for the deposit sum, if any, stated therein.

(Indicate how, such as by email, website, host site/platform, paper copy, or other method Bidders shall obtain Bidding Documents.)

https://procurement.opengov.com/portal/berlinct or www.berlinct.gov under "Departments" then selecting "Purchasing."

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

§ 3.1.2 Any required deposit shall be refunded to Bidders who submit a bona fide Bid and return the paper Bidding Documents in good condition within ten days after receipt of Bids. The cost to replace missing or damaged paper documents will be deducted from the deposit. A Bidder receiving a Contract award may retain the paper Bidding Documents, and the Bidder’s deposit will be refunded.

§ 3.1.3 Bidding Documents will not be issued directly to Sub-bidders unless specifically offered in the advertisement or invitation to bid, or in supplementary instructions to bidders.

§ 3.1.4 Bidders shall use complete Bidding Documents in preparing Bids. Neither the Owner nor Architect assumes responsibility for errors or misinterpretations resulting from the use of incomplete Bidding Documents.

§ 3.1.5 The Bidding Documents will be available for the sole purpose of obtaining Bids on the Work. No license or grant of use is conferred by distribution of the Bidding Documents.

§ 3.2 Modification or Interpretation of Bidding Documents § 3.2.1 The Bidder shall carefully study the Bidding Documents, shall examine the site and local conditions, and shall notify the Architect of errors, inconsistencies, or ambiguities discovered and request clarification or interpretation pursuant to Section 3.2.2.

§ 3.2.2 Requests for clarification or interpretation of the Bidding Documents shall be submitted by the Bidder in writing and shall be received by the Architect at least seven days prior to the date for receipt of Bids.

(Indicate how, such as by email, website, host site/platform, paper copy, or other method Bidders shall submit requests for clarification and interpretation.)

send RFI’s to mallen@jharchitects.net

§ 3.2.3 Modifications and interpretations of the Bidding Documents shall be made by Addendum. Modifications and interpretations of the Bidding Documents made in any other manner shall not be binding, and Bidders shall not rely upon them.

§ 3.3 Substitutions § 3.3.1 The materials, products, and equipment described in the Bidding Documents establish a standard of required function, dimension, appearance, and quality to be met by any proposed substitution.

§ 3.3.2 Substitution Process § 3.3.2.1 Written requests for substitutions shall be received by the Architect at least ten days prior to the date for receipt of Bids. Requests shall be submitted in the same manner as that established for submitting clarifications and interpretations in Section 3.2.2.

§ 3.3.2.2 Bidders shall submit substitution requests on a Substitution Request Form if one is provided in the Bidding Documents.

§ 3.3.2.3 If a Substitution Request Form is not provided, requests shall include (1) the name of the material or equipment specified in the Bidding Documents; (2) the reason for the requested substitution; (3) a complete description of the proposed substitution including the name of the material or equipment proposed as the substitute, performance and test data, and relevant drawings; and (4) any other information necessary for an evaluation. The request shall include a statement setting forth changes in other materials, equipment, or other portions of the Work, including changes in the work of other contracts or the impact on any Project Certifications (such as LEED), that will result from incorporation of the proposed substitution.

§ 3.3.3 The burden of proof of the merit of the proposed substitution is upon the proposer. The Architect’s decision of approval or disapproval of a proposed substitution shall be final.

§ 3.3.4 If the Architect approves a proposed substitution prior to receipt of Bids, such approval shall be set forth in an Addendum. Approvals made in any other manner shall not be binding, and Bidders shall not rely upon them.

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

§ 3.3.5 No substitutions will be considered after the Contract award unless specifically provided for in the Contract Documents.

§ 3.4 Addenda § 3.4.1 (Paragraphs deleted) Addenda will be posted on the Town’s procurement website. All bidders are responsible for checking for any Addenda.

§ 3.4.2 Addenda will be available where Bidding Documents are on file.

§ 3.4.3 Addenda will be issued no later than four days prior to the date for receipt of Bids, except an Addendum withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids.

§ 3.4.4 Prior to submitting a Bid, each Bidder shall ascertain that the Bidder has received all Addenda issued, and the Bidder shall acknowledge their receipt in the Bid.

ARTICLE 4 BIDDING PROCEDURES

§ 4.1 Preparation of Bids § 4.1.1 Bids shall be submitted on the forms included with or identified in the Bidding Documents.

§ 4.1.2 All blanks on the bid form shall be legibly executed. Paper bid forms shall be executed in a non-erasable medium.

§ 4.1.3 Sums shall be expressed in both words and numbers, unless noted otherwise on the bid form. In case of discrepancy, the amount entered in words shall govern.

§ 4.1.4 Edits to entries made on paper bid forms must be initialed by the signer of the Bid.

§ 4.1.5 All requested Alternates shall be bid. If no change in the Base Bid is required, enter "No Change" or as required by the bid form.

§ 4.1.6 Where two or more Bids for designated portions of the Work have been requested, the Bidder may, without forfeiture of the bid security, state the Bidder’s refusal to accept award of less than the combination of Bids stipulated by the Bidder. The Bidder shall neither make additional stipulations on the bid form nor qualify the Bid in any other manner.

§ 4.1.7 Each copy of the Bid shall state the legal name and legal status of the Bidder. As part of the documentation submitted with the Bid, the Bidder shall provide evidence of its legal authority to perform the Work in the jurisdiction where the Project is located. Each copy of the Bid shall be signed by the person or persons legally authorized to bind the Bidder to a contract. A Bid by a corporation shall further name the state of incorporation and have the corporate seal affixed. A Bid submitted by an agent shall have a current power of attorney attached, certifying the agent’s authority to bind the Bidder.

§ 4.1.8 A Bidder shall incur all costs associated with the preparation of its Bid.

§ 4.2 Bid Security § 4.2.1 Each Bid shall be accompanied by the following bid security:

(Insert the form and amount of bid security.)

Bid Bond in the amount of 5% of the Bid.

§ 4.2.2 The Bidder pledges to enter into a Contract with the Owner on the terms stated in the Bid and shall, if required, furnish bonds covering the faithful performance of the Contract and payment of all obligations arising thereunder. Should the Bidder refuse to enter into such Contract or fail to furnish such bonds if required, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as a penalty. In the event the Owner fails to comply with Section 6.2, the amount of the bid security shall not be forfeited to the Owner.

§ 4.2.3 If a surety bond is required as bid security, it shall be written on AIA Document A310™, Bid Bond, unless otherwise provided in the Bidding Documents. The attorney-in-fact who executes the bond on behalf of the surety shall

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097) affix to the bond a certified and current copy of an acceptable power of attorney. The Bidder shall provide surety bonds from a company or companies lawfully authorized to issue surety bonds in the jurisdiction where the Project is located.

§ 4.2.4 The Owner will have the right to retain the bid security of Bidders to whom an award is being considered until (a) the Contract has been executed and bonds, if required, have been furnished; (b) the specified time has elapsed so that Bids may be withdrawn; or (c) all Bids have been rejected. However, if no Contract has been awarded or a Bidder has not been notified of the acceptance of its Bid, a Bidder may, beginning days after the opening of Bids, withdraw its Bid and request the return of its bid security.

§ 4.3 Submission of Bids § 4.3.1 A Bidder shall submit its Bid as indicated below:

(Indicate how, such as by website, host site/platform, paper copy, or other method Bidders shall submit their Bid.)

Via Town’s bid portal: https://procurement.opengov.com/portal/berlinct.

§ 4.3.2 Paper copies of the Bid, the bid security, and any other documents required to be submitted with the Bid shall be enclosed in a sealed opaque envelope. The envelope shall be addressed to the party receiving the Bids and shall be identified with the Project name, the Bidder’s name and address, and, if applicable, the designated portion of the Work for which the Bid is submitted. If the Bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing envelope with the notation "SEALED BID ENCLOSED" on the face thereof.

§ 4.3.3 Bids shall be submitted by the date and time and at the place indicated in the invitation to bid. Bids submitted after the date and time for receipt of Bids, or at an incorrect place, will not be accepted.

§ 4.3.4 The Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids.

§ 4.3.5 A Bid submitted by any method other than as provided in this Section 4.3 will not be accepted.

§ 4.4 Modification or Withdrawal of Bid § 4.4.1 Prior to the date and time designated for receipt of Bids, a Bidder may submit a new Bid to replace a Bid previously submitted, or withdraw its Bid entirely, by notice to the party designated to receive the Bids. Such notice shall be received and duly recorded by the receiving party on or before the date and time set for receipt of Bids. The receiving party shall verify that replaced or withdrawn Bids are removed from the other submitted Bids and not considered. Notice of submission of a replacement Bid or withdrawal of a Bid shall be worded so as not to reveal the amount of the original Bid.

§ 4.4.2 Withdrawn Bids may be resubmitted up to the date and time designated for the receipt of Bids in the same format as that established in Section 4.3, provided they fully conform with these Instructions to Bidders. Bid security shall be in an amount sufficient for the Bid as resubmitted.

§ 4.4.3 After the date and time designated for receipt of Bids, a Bidder who discovers that it made a clerical error in its Bid shall notify the Architect of such error within two days, or pursuant to a timeframe specified by the law of the jurisdiction where the Project is located, requesting withdrawal of its Bid. Upon providing evidence of such error to the reasonable satisfaction of the Architect, the Bid shall be withdrawn and not resubmitted. If a Bid is withdrawn pursuant to this Section 4.4.3, the bid security will be attended to as follows:

(State the terms and conditions, such as Bid rank, for returning or retaining the bid security.)

Returned to Bidder within one week

ARTICLE 5 CONSIDERATION OF BIDS

§ 5.1 Opening of Bids If stipulated in an advertisement or invitation to bid, or when otherwise required by law, Bids properly identified and received within the specified time limits will be publicly opened and read aloud. A summary of the Bids may be made available to Bidders.

§ 5.2 Rejection of Bids Unless otherwise prohibited by law, the Owner shall have the right to reject any or all Bids.

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

§ 5.3 Acceptance of Bid (Award) § 5.3.1 It is the intent of the Owner to award a Contract to the lowest responsive and responsible Bidder, provided the Bid has been submitted in accordance with the requirements of the Bidding Documents. Unless otherwise prohibited by law, the Owner shall have the right to waive informalities and irregularities in a Bid received and to accept the Bid which, in the Owner’s judgment, is in the Owner’s best interests.

§ 5.3.2 Unless otherwise prohibited by law, the Owner shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided in the Bidding Documents, and to determine the lowest responsive and responsible Bidder on the basis of the sum of the Base Bid and Alternates accepted.

ARTICLE 6 POST-BID INFORMATION

§ 6.1 Contractor’s Qualification Statement Bidders to whom award of a Contract is under consideration shall submit to the Architect, upon request and within the timeframe specified by the Architect, a properly executed AIA Document A305™, Contractor’s Qualification Statement, unless such a Statement has been previously required and submitted for this Bid.

§ 6.2 Owner’s Financial Capability A Bidder to whom award of a Contract is under consideration may request in writing, fourteen days prior to the expiration of the time for withdrawal of Bids, that the Owner furnish to the Bidder reasonable evidence that financial arrangements have been made to fulfill the Owner’s obligations under the Contract. The Owner shall then furnish such reasonable evidence to the Bidder no later than seven days prior to the expiration of the time for withdrawal of Bids. Unless such reasonable evidence is furnished within the allotted time, the Bidder will not be required to execute the Agreement between the Owner and Contractor.

§ 6.3 Submittals § 6.3.1 After notification of selection for the award of the Contract, the Bidder shall, as soon as practicable or as stipulated in the Bidding Documents, submit in writing to the Owner through the Architect:

.1 a designation of the Work to be performed with the Bidder’s own forces;

.2 names of the principal products and systems proposed for the Work and the manufacturers and suppliers of each; and

.3 names of persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for the principal portions of the Work.

§ 6.3.2 The Bidder will be required to establish to the satisfaction of the Architect and Owner the reliability and responsibility of the persons or entities proposed to furnish and perform the Work described in the Bidding Documents.

§ 6.3.3 Prior to the execution of the Contract, the Architect will notify the Bidder if either the Owner or Architect, after due investigation, has reasonable objection to a person or entity proposed by the Bidder. If the Owner or Architect has reasonable objection to a proposed person or entity, the Bidder may, at the Bidder’s option, withdraw the Bid or submit an acceptable substitute person or entity. The Bidder may also submit any required adjustment in the Base Bid or Alternate Bid to account for the difference in cost occasioned by such substitution. The Owner may accept the adjusted bid price or disqualify the Bidder. In the event of either withdrawal or disqualification, bid security will not be forfeited.

§ 6.3.4 Persons and entities proposed by the Bidder and to whom the Owner and Architect have made no reasonable objection must be used on the Work for which they were proposed and shall not be changed except with the written consent of the Owner and Architect.

ARTICLE 7 PERFORMANCE BOND AND PAYMENT BOND

§ 7.1 Bond Requirements § 7.1.1 If stipulated in the Bidding Documents, the Bidder shall furnish bonds covering the faithful performance of the Contract and payment of all obligations arising thereunder.

§ 7.1.2 If the furnishing of such bonds is stipulated in the Bidding Documents, the cost shall be included in the Bid. If the furnishing of such bonds is required after receipt of bids and before execution of the Contract, the cost of such bonds shall be added to the Bid in determining the Contract Sum.

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

§ 7.1.3 The Bidder shall provide surety bonds from a company or companies lawfully authorized to issue surety bonds in the jurisdiction where the Project is located.

§ 7.1.4 Unless otherwise indicated below, the Penal Sum of the Payment and Performance Bonds shall be the amount of the Contract Sum.

(If Payment or Performance Bonds are to be in an amount other than 100% of the Contract Sum, indicate the dollar amount or percentage of the Contract Sum.)

§ 7.2 Time of Delivery and Form of Bonds § 7.2.1 The Bidder shall deliver the required bonds to the Owner not later than three days following the date of execution of the Contract. If the Work is to commence sooner in response to a letter of intent, the Bidder shall, prior to commencement of the Work, submit evidence satisfactory to the Owner that such bonds will be furnished and delivered in accordance with this Section 7.2.1.

§ 7.2.2 Unless otherwise provided, the bonds shall be written on AIA Document A312, Performance Bond and Payment Bond.

§ 7.2.3 The bonds shall be dated on or after the date of the Contract.

§ 7.2.4 The Bidder shall require the attorney-in-fact who executes the required bonds on behalf of the surety to affix to the bond a certified and current copy of the power of attorney.

ARTICLE 8 ENUMERATION OF THE PROPOSED CONTRACT DOCUMENTS

§ 8.1 Copies of the proposed Contract Documents have been made available to the Bidder and consist of the following documents:

.1 AIA Document A105™–2017, Standard Form of Agreement Between Owner and Contractor, unless otherwise stated below.

(Insert the complete AIA Document number, including year, and Document title.)

.2 AIA Document A101™–2017, Exhibit A, Insurance and Bonds, unless otherwise stated below.

.3 AIA Document A201™–2017, General Conditions of the Contract for Construction, unless otherwise stated below.

.4

.5 Drawings

Number Title Date

.6 Specifications

Section Title Date Pages

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:03:41 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1097365097)

.7 Addenda:

Number Date Pages

.8 Other Exhibits:

(Check all boxes that apply and include appropriate information identifying the exhibit where required.)

(Paragraphs deleted)

Title Date Pages

[ ] Supplementary and other Conditions of the Contract:

Document Title Date Pages

.9 Other documents listed below:

(List here any additional documents that are intended to form part of the Proposed Contract Documents.)

139 PATTERSON WAY SUPPLEMENTARY INSTRUCTION TO BIDDERS

BERLIN, CT SITB - 1

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS SITB-1

SUPPLEMENTARY INSTRUCTION TO BIDDERS

1.01 GENERAL CONDITIONS

AIA Document A701, “Instructions to Bidders,” 2018 Edition, American Institute of Architects, Articles 1 through 8, are bound herein and are hereby made a part of the Contract Documents and shall apply to all Contractors and Subcontractors.

1.02 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

a. Certain Articles of the AIA Instructions to Bidders are revised or replaced by requirements of the Supplementary Instructions, listed below. Such revisions are replacements and shall take precedence over the AIA Instructions to Bidders.

b. The Following Articles, revised paragraphs and clauses have the same numerical designations occurring in the AIA Instructions to Bidders, and all additions follow in a direct numbered sequence.

ARTICLE 2 - BIDDER’S REPRESENTATIONS

Add the following as paragraph 2.1.4:

2.1.4.1 The building and site are open for public viewing during normal business hours. Each

Bidder shall visit the site of the proposed work and fully acquaint themselves with conditions relating to construction and labor so that they may fully understand the facilities, difficulties and restrictions attending the execution of the work under this Contract. Bidders shall thoroughly examine and be familiar with the drawings and the specifications. The failure or omission of any Bidder to receive or examine any form, instrument, Addendum or other documents or to visit the site and acquaint himself with conditions there existing, shall in no way relieve any Bidder from any obligation with respect to his Bid or the Contract.

ARTICLE 3 - BIDDING DOCUMENTS

3.1.2 Delete Paragraph 3.1.2.

Add the following Paragraph:

3.2.1.1 Any conflict existing between the Drawings and the Specifications and not brought to the attention of the Architect for clarification before bids are submitted shall be resolved on the basis of furnishing the greatest quantity and/or highest quality indicated, without cost to the Contract.

Add the following Paragraph:

BERLIN, CT SITB - 2

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS SITB-2

3.2.4 A Pre-Bid Conference will be held on Thursday, March 26, 2026, at 3:00 pm, at the Berlin High School, 139 Patterson Way, Berlin, CT. It is recommended that all Bidders attend.

3.3.4.1 After the award of the Contract, no substitutions will be considered for the brands specified except upon written request of the Contractor and written approval by the Architect and Owner’s concurrence. Substitutions shall be submitted including the entire system and/or assembly attached thereto.

3.3.5.1 Approval by the Owner and the Architect of any such substitution shall not relieve the

Contractor requesting the substitution of any responsibility for additional costs incurred by other trades for changes made necessary to accommodate the substituted item.

ARTICLE 4 - BIDDING PROCEDURE

Delete Paragraph 4.2.2 and substitute the following:

Surety Bonds, if required, shall be written on forms similar in content to AIA Document A310 and executed by a company authorized to transact business within the State of Connecticut, and the attorney-in-fact who executes the Bond on behalf of the Surety shall affix to the Bond a certified and current copy of his power of attorney.

ARTICLE 5 - CONSIDERATION OF BIDS

5.3.3 Prior to the award of a Contract, bidders must present satisfactory evidence that they have been regularly engaged in the business of doing such work as they propose to execute and that they are prepared with the necessary supervisory staff, capital, materials and machinery to conduct and complete the work to be contracted for in accordance with the drawings and specifications and to begin it promptly when ordered. Such evidence shall show that the Contractor has experience in the renovation of occupied buildings.

5.3.4 A bid may be rejected if the bidder cannot show that he has the necessary capital and experience and owns, controls or can produce the necessary plant to commence the work at the time prescribed and thereafter to prosecute and complete the work at the rate or time specified; and that he is not already obligated for the other work which would delay the commencement, prosecution, or completion of this work. A bid may also be rejected if the bidder has previously failed to complete a contract within the time required or has previously performed similar work in an unsatisfactory manner or does not have

BERLIN, CT SITB - 3

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS SITB-3

experience in the renovation of buildings that were occupied during the course of the work.

ARTICLE 7 - PERFORMANCE BOND AND PAYMENT BOND

Amend Paragraph 7.1.1 to read as follows:

Successful contract bidders will be required to furnish and pay for Surety in the full amount of the Contract. This Bond shall provide 100% security for faithful performance and for payment of all persons performing labor or furnishing materials in connection with this Contract and shall be executed by a company authorized to transact business within the State of Connecticut. The cost of such bonds shall be included in the Base Bid.

7.2.5 If required, the Performance Bond and Payment Bond shall remain in force in full value throughout the course of the project. No reduction in bond value shall be acceptable.

Add the following Paragraph:

7.2.6 Bids submitted in duplicate by CONTRACTORS must be made only from a copy of the

BID FORM which accompanies these Specifications and shall be made on the bidder’s official letterhead.

ADDITIONAL SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

ADD ARTICLE 9 - TIME

9.1 The Contractor to whom this Contract may be awarded will be required to commence work on the Project within ten (10) days of Contract signing. The work shall be prosecuted diligently thereafter and shall be completed in accordance with the proposal.

END OF SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

PROPOSAL

139 PATTERSON WAY

Date ____________________

To: Mr. Doug Solek Superintendent of Facilities 11 Town Farm Lane Berlin, CT 06037

Pursuant to and in compliance with your “Invitation to Bid” relating thereto, the undersigned, (Name of Firm) having visited the site and carefully examined the Drawings, Contract Documents and complete Specifications dated March 11, 2026, together with all Addenda issued and received prior to the scheduled closing time for receipt of Bids as prepared by the Architect; Jacunski Humes Architects, LLC, 15 Massirio Drive, Suite 101, Berlin, CT; hereby offers and agrees as follows:

To provide all labor, materials, equipment, appliances and whatsoever else necessary to construct and properly finish all work in connection with the, 139 PATTERSON WAY to the satisfaction of the Architect and the Owner for the Base Bid Lump Sum of:

-2-

If awarded this Contract, we will execute an Agreement with the Town of Berlin, Owner of the property.

CONTRACT TIME

If awarded the Contract, the undersigned agrees that the work will commence forthwith and shall be substantially complete within _____ calendar days from the Owner’s Notice to Proceed.

ADDENDUM

The undersigned hereby certifies that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed on this project. The Bid includes Addenda listed below and they are hereby acknowledged:

Addendum # ___ Dated ________________

Enclosed herewith, is the Bid Security in the form of:

Bid Bond ( ) Certified Check ( ) in the amount of: ($ )

COMPANY NAME: ________________________________________

ADDRESS: ________________________________________

BY: ________________________________________

(authorized signature, officer of bidder’s company)

(above name typewritten)

TITLE: ________________________________________

TELEPHONE: ________________________________________

E-MAIL: ________________________________________

END OF PROPOSAL

Document A105

– 2017 Standard Short Form of Agreement Between Owner and Contractor

Init.

AIA Document A105 – 2017. Copyright © 1993, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:07:14 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1163360116)

ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

AGREEMENT made as of the day of April in the year 2026 (In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information)

Town of Berlin 240 Kensington Road Berlin, CT and the Contractor:

(Name, legal status, address and other information) for the following Project:

(Name, location and detailed description)

Berlin High School Flooring Replacement Berlin High School Bid 2026-18 Removal, moisture mitigation and replacement of existing floor tiles

The Architect:

(Name, legal status, address and other information)

Jacunski Humes Architects, LLC 15 Massirio Drive, Suite 101 Berlin, CT

The Owner and Contractor agree as follows.

Init.

AIA Document A105 – 2017. Copyright © 1993, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:07:14 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1163360116)

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

3 CONTRACT SUM

4 PAYMENTS

5 INSURANCE

6 GENERAL PROVISIONS

7 OWNER

8 CONTRACTOR

9 ARCHITECT

10 CHANGES IN THE WORK

11 TIME

12 PAYMENTS AND COMPLETION

13 PROTECTION OF PERSONS AND PROPERTY

14 CORRECTION OF WORK

15 MISCELLANEOUS PROVISIONS

16 TERMINATION OF THE CONTRACT

17 OTHER TERMS AND CONDITIONS

ARTICLE 1 THE CONTRACT DOCUMENTS

The Contractor shall complete the Work described in the Contract Documents for the Project. The Contract Documents consist of

.1 this Agreement signed by the Owner and Contractor;

.2 the drawings and specifications prepared by the Architect, dated , and enumerated as follows:

Drawings:

Number Title Date

Specifications:

Section Title Pages

.3 addenda prepared by the Architect as follows:

Number Date Pages

AIA Document A105 – 2017. Copyright © 1993, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:07:14 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1163360116)

.4 written orders for changes in the Work, pursuant to Article 10, issued after execution of this Agreement; and

.5 other documents, if any, identified as follows:

Owner’s Invitation to Bid and all Bid Documents issued in conjunction therewith, including Addenda;

Contractor’s Bid.

ARTICLE 2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 2.1 The Contract Time is the number of calendar days available to the Contractor to substantially complete the Work.

§ 2.2 Date of Commencement:

Unless otherwise set forth below, the date of commencement shall be the date of this Agreement.

(Insert the date of commencement if other than the date of this Agreement.)

Immediately following the last day of the 2025-2026 High School year on or about June 15, 2026

§ 2.3 Substantial Completion:

Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion, as defined in Section 12.5, of the entire Work:

(Check the appropriate box and complete the necessary information.)

[ ] Not later than ( ) calendar days from the date of commencement.

[ X ] By the following date: Immediately preceding the first day of the 2027-2028 High School year on or about August 15, 2027

ARTICLE 3 CONTRACT SUM

§ 3.1 The Contract Sum shall include all items and services necessary for the proper execution and completion of the Work. Subject to additions and deductions in accordance with Article 10, the Contract Sum is:

§ 3.2 For purposes of payment, the Contract Sum includes the following values related to portions of the Work:

(Itemize the Contract Sum among the major portions of the Work.)

Portion of the Work Value

§ 3.3 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and hereby accepted by the Owner:

(Identify the accepted alternates. If the bidding or proposal documents permit the Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)

§ 3.4 Allowances, if any, included in the Contract Sum are as follows:

(Identify each allowance.)

Item Price

§ 3.5 Unit prices, if any, are as follows:

(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)

AIA Document A105 – 2017. Copyright © 1993, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 09:07:14 ET on 03/12/2026 under Order No.2114457289 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1163360116)

Item Units and Limitations Price per Unit ($0.00)

ARTICLE 4 PAYMENTS

§ 4.1 Based on Contractor’s Applications for Payment certified by the Architect, the Owner shall pay the Contractor, in accordance with Article 12, as follows:

(Insert below timing for payments and provisions for withholding retainage, if any.)

5% retainage

(Paragraphs deleted)

ARTICLE 5 INSURANCE

§ 5.1 The Contractor shall maintain the following types and limits of insurance until the expiration of the period for correction of Work as set forth in Section 14.2, subject to the terms and conditions set forth in this Section 5.1:

§ 5.1.1 Commercial General Liability insurance for the Project, written on an occurrence form, with policy limits of not less than Two Million Dollars ($ 2,000,000.00 ) each occurrence, Three Million Dollars ($ 3,000,000.00 ) general aggregate, and Three Million Dollars ($ 3,000,000.00 ) aggregate for products-completed operations hazard.

§ 5.1.2 Automobile Liability covering vehicles owned, and non-owned vehicles used, by the Contractor, with policy limits of not less than One Million Dollars ($ 1,000,000.00 ) per accident, for bodily injury, death of any person, and property damage arising out of the ownership, maintenance, and use of those motor vehicles along with any other statutorily required automobile coverage.

§ 5.1.3 The Contractor may achieve the required limits and coverage for Commercial General Liability and Automobile Liability through a combination of primary and excess or umbrella liability insurance, provided that such primary and excess or umbrella insurance policies result in the same or greater coverage as those required under Section 5.1.1 and 5.1.2, and in no event shall any excess or umbrella liability insurance provide narrower coverage than the primary policy. The excess policy shall not require exhaustion of the underlying limits only through the actual payment by the underlying insurers.

§ 5.1.4 Workers’ Compensation at statutory limits.

§ 5.1.5 Employers’ Liability with policy limits not less than Five Hundred Thousand Dollars ($ 500,000.00 ) each accident, Five Hundred Thousand Dollars ($ 500,000.00 ) each employee, and One Million Dollars ($ 1,000,000.00 ) policy limit.

§ 5.1.6 The Contractor shall provide builder’s risk insurance to cover the total value of the entire Project on a replacement cost basis.

§ 5.1.7 Other Insurance Provided by the Contractor (List below any other insurance coverage to be provided by the Contractor and any applicable limits.)

Coverage Limits Excess Liability Insurance $1,000,000.00

§ 5.2 The Owner shall be responsible for purchasing and maintaining the Owner’s usual liability insurance and shall provide property insurance to cover the value of the Owner’s property. The Contractor is entitled to receive an increase in the Contract Sum equal to the insurance proceeds related to a loss for damage to the Work covered by the Owner’s property insurance.

§ 5.3 The Contractor shall obtain an endorsement to its Commercial General Liability insurance policy to provide coverage for the Contractor’s obligations under Section 8.12.

§ 5.4 Prior to commencement of the Work, each party shall provide certificates of insurance showing their respective coverages.

AIA…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .