Specifications.pdf
PDF 8 MB Posted
- Attached to
- REHABILITATE TEMPLE BAR WELL #4
- Solicitation number
- 140P8125Q0012
About this file
This document is a comprehensive set of technical specifications for rehabilitating Well #4 at the Temple Bar site within Lake Mead National Recreation Area. The project involves inspecting, cleaning, and replacing key components of the water well system, with specific requirements including installing a new 4-inch diameter flexible downpipe, submersible pump, and motor designed to deliver approximately 200 gallons per minute to the water treatment plant. The contractor must provide NSF-61 certified equipment, perform system evaluation and flow testing, and ensure compatibility with existing water infrastructure.
Key technical specifications include using a Boreline FlexiRiser or equivalent downpipe, selecting a pump and motor that optimizes water flow without exceeding 200 GPM, and conducting a comprehensive startup validation period where equipment must operate without malfunction for 7 consecutive days. Additional requirements involve obtaining necessary permits from Arizona environmental agencies, following strict park regulations regarding equipment cleaning to prevent invasive species spread, and completing work within specified working hours. The project emphasizes environmental compliance, including mandatory desert tortoise awareness training for all personnel and careful management of the well site within the national recreation area.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAKE MEAD
NATIONAL RECREATION AREA
Boulder City, Nevada
PMIS No. 345222
Rehabilitate Temple Bar Well Number 4
CONTRACT SPECIFICATIONS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
April 21, 2025
TABLE OF CONTENTS
NO. OF PAGES
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 11 40 Work Restrictions 01 27 00 Definition of Contract Price Items 01 31 00 Project Management 01 32 14 Construction Schedule 01 33 00 Submittal Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities & Controls 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition and Abandonment
DIVISION 22 – PLUMBING
22 00 00 Plumbing General Requirements 22 05 19 Transmitters, Meters, and Gauges 22 11 00 Plumbing, Piping, and Fittings 22 11 13 Chlorination of Domestic Water Mains for Disinfection 22 11 23 Pumps
DIVISION 26 – ELECTRICAL
26 00 00 Electrical General Requirements 26 05 00 Basic Electrical Materials and Methods 26 05 19 Low Voltage Electrical Power Conductors and Cables
DIVISION 31 – EARTHWORK
31 23 33.20 Restoration of Surfaces
DIVISION 33 – UTILITIES
33 00 00 Pipe and Pipe Fittings: General Statement 33 11 00 Water utility Distribution Piping 33 12 00 Valves General Statement 33 12 16 Water Utility Distribution Valves
APPENDIX
LAKE Map and Distances PW Wells Site Maps TB Well #4 Interior Photos Transmittal Form CM-16
DIVISION 01
GENERAL REQUIREMENTS
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 5
SUMMARY OF WORK
SECTION 01 11 00
PART 1 – GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
PROJECT LOCATION: This project is located in the Lake Mead National Recreation Area. There is one site: Temple Bar (TB) developed area outside of Boulder City, Nevada.
1. Temple Bar has 3 wells, #’s 3, 4, and 6. Work will be performed on well #4.
EXISTING CONDITIONS:
There are 3 existing working water wells located at Temple Bar.
Well #3 had a depth of 240 feet when it was constructed but was rehabilitated to a depth of 126 feet following the collapse of the lower portion of the borehole in the late 1990s. The lowest pump setting possible is 116 feet, and when the static water level dropped to 89 feet, it left only 27 feet for drawdown before cavitation. The pump needs to be throttled down to 50 GPM or the pump will run dry. This well also frequently requires mechanical retrofit every few years.
Well #4 can produce slightly more than Well #3, but still cannot meet the designed flowrate at the water treatment plant and requires periodic mechanical retrofit.
Well #6 was added in 2020 to help supplement the flowrate going to the water treatment plant from wells #3 and 4. In 2020, the borehole was drilled to a depth of 292 feet and a 30 HP, 480 volt Sandfighter motor and 250SR30 pump was installed. In 2020, the static water level of the aquifer was 147 feet below land surface which has continued to decline with the overall drop in Lake Mead levels.
o 260 feet of 4-inch diameter Boreline Flexible Drop Pipe is located inside the 12-inch well casing.
o 80 feet of 10x8-inch Johnson Muni-Pak wire wrapped stainless steel screens is located from 212 to 292 feet below land surface.
The water treatment plant uses an arsenic media vessel that is designed to treat no more than
200 GPM.
All measurements given are from the most recent information available which is not up to the most recent date. Contractor to verify all existing conditions in field.
A. The intent of this contract is to: replace the pump, motor, and downpipe, and test the flowrate of well 4. All work shall be in accordance with Nevada Division of Water Resources (NDWR), Nevada Division of Environmental Protection (NDEP), and Arizona Division of Environmental Quality (ADEQ) regulations. Scope of work includes, but is not limited to, the following:
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 6
1. TB WELL #4
i. Inspect and remove floating debris.
1. Existing pump/motor to be removed for inspection, replacement and removal of floating debris.
2. Contractor to conduct camera inspection and provide digital copy of video inspection documenting screen condition and debris removal.
3. 90 out of well head, meter, analogue metere to the 100 gallons
ii. Evaluate: Conduct flow and pressure testing of well system to provide data on pressure head values at pump houses and confirm pump and motor size can provide minimum required flowrate of 200 GPM at the Temple Bar Water Treatment Plant. If minimum required flow rate is not able to be met, provide recommendation for system repairs to achieve a flow rate of 200 GPM at the Temple Bar Water Treatment Plant, in order to match the arsenic removal flow rate as close as possible. Using valves to throttle down the flowrate is not an acceptable solution. Before completing a drawdown test, the contractor will present a technical approach for the ideal test of the well. It should be a combination of stepdown and constant rate pumping tests. The government will then approve or disapprove the pumping test. Contractor must provide results of the drawdown test to COR.
iii. Install and provide the following new components:
1. 4-inch diameter flexible down pipe from well head down to pump/motor at bottom of borehole.
a. An example of an acceptable product is: Boreline FlexiRiser
b. This requirement is a brand name or equal. Equal products shall meet the following salient characteristics:
i. Constructed from high-tenacity, polyester yarns.
ii. Have a minimum theoretical short length burst pressure of 820 psi and a minimum theoretical tensile strength of 26,000 lbs.
iii. Have a maximum extension of 3% and a maximum diameter swell of 10%.
iv. Must be capable of operating in water with pH from pH3 to pH10.
v. Have at least a 50 year warranty against materials and manufacturing defects.
vi. Shall be 316 or 304 Stainless Steel materials for use with drinking water.
vii. Fittings shall be either NPT or BSP male thread for attachment to pump.
viii. Centralizer kit must be 316 or 304 Stainless Steel attached above pump.
ix. Certified by the NSF61 for use with potable water and manufacturer must possess the ISO 9000 QA registration.
2. Install a new contractor provided NSF-61 Certified Submersible Pump and Motor. The pump and motor body, shaft, and strainer shall be constructed of stainless steel. The brand makes and models of the pump and motor selected must be easily acquired by the government
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 7 in the event of an unexpected future failure. Lead times and proximity of dealers to the Las Vegas Valley is high priority. Base model and stages selected to deliver as close to 200 GPM without exceeding 200 GPM at Water Treatment Plant. The contractor shall select a pump and motor that optimizes the water flow for the water treatment plant without exceeding 200 GPM and does not exceed the capacity of the well. The government must approve the pump and motor prior to the contractor’s acquisition of the pump and motor.
3. REPLACE in-kind the 90 degree from well head. SEE APPENDIX
FOR PHOTO
4. REPLACE in-kind the analogue water meter. SEE APPENDIX FOR
PHOTO
B. Startup: Operational validation period required upon completion of work at the well.
Equipment will be tested and run in normal operations for 7 days. Components must operate without malfunction for 7 days straight. Should repairs be needed, 7-day validation period shall start over. Acceptance will be signed off after successful completion of the startup period. Pre startup sanitation will be done by NPS personnel. The contractor will not complete the sanitation of the well after installation. The well will not be tied into the water system without NPS authority.
C. The work shall meet the following requirements:
1. The contractor shall provide all materials, labor, equipment, and incidentals required to perform the work described in this specification. All materials and equipment shall be new, and Contractor furnished from outside the park. Equipment and material cut sheets shall be submitted to the NPS for approval before any construction or installation.
Follow the included approval submittal process. Construction shall follow those approved submittals.
2. All procedures will be completed in accordance with the manufacturer’s instructions.
3. All supplies and materials will be NSF Standard 61- Certified and approved for use with potable water. Contractor shall provide manufacturer documentation confirming NSF- 61 certification before installation. Certifications for the products shall be included in the Operations and Maintenance Manuals at the completion of the project.
4. All work will be performed in accordance with local and State of Arizona requirements.
5. Permit for construction shall be obtained (if needed) from the State of Arizona Division of Environmental Quality (ADEQ) prior to start of construction.
i. Contractor shall manage any permit application and closeout process with
ADEQ.
ii. Any engineering work that is needed to prepare and closeout the application shall be included in this proposal.
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 8
iii. Any engineering support shall be licensed in the State of Arizona to facilitate the application process. ADEQ requires a Arizona State Professional Engineering (PE) license and signature in the sections requiring PE signatures.
6. All wells are located in a pump house or behind secure fence. Access to be coordinated with COR and discussed at Pre-Construction meeting.
7. Pump and motor controls shall be industry standard. Contractor shall install a match or make similar to the existing well controls if replacement is necessary.
8. All associated water connections, valves, meters, electrical connections, and support structure shall be included in scope of work if replacement is needed.
9. Notify the COR of construction phasing. Close coordination between the NPS and contractor is required to coordinate the down time of the existing wells and production of water to the water plant.
i. Minimum of 2 business day (Monday - Friday) notice for any well system shutdowns. Wells may be offline over weekends. When put back online, well must be tied back into system by Friday at noon. No holiday/weekend work will be allowed.
10. Photos of all connections are to be taken and provided, documenting the progress of the construction and the suitability of each connection. This is especially important of any connection or piping that will be buried.
11. A daily log shall be prepared by the contractor representing the work that was performed that day.
i. The log shall describe the tasks performed that day and the contractor staff working.
ii. Two or more representative photos of the tasks being performed that day shall be included in each daily log.
iii. The submitted daily logs shall be in a PDF format. Emailing to the CO/COR is acceptable.
iv. The daily logs shall be sent to the CO/COR once a week. For every week worked in the field, the daily log shall be sent to the CO/COR.
1.2 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work.
1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 9
3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.
4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.
5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.
B. Government-Furnished Items: The government will furnish the following products or materials for use on this contract:
None anticipated.
1.3 PUBLIC USE OF THE SITE
A. General: The project site is not open to the public.
1.4 CONTRACTOR USE OF SITE
A. General: The two sites are located behind secure gated Maintenance areas of the park.
Security of the site shall be maintained during construction. Contractor shall at times conduct his operations to ensure the least inconvenience to the recreation area visitors and employees.
B. Contractor shall maintain function of the existing water wells and coordinate with NPS and
Utility Service Branch staff to schedule any shutoffs required to properly perform testing, inspection, cleaning, and installations.
C. Field Verification: The vendor shall field verify existing conditions affecting the work in this contract before ordering materials, including verifying all new and existing dimensions. The scheduling of field verification site visit(s) shall be coordinated with the Contracting Officer’s Representative (COR). A final inspection and operational testing verification shall be performed at the site with the COR and a representative of the Utility Systems Branch present.
D. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for interruption of existing utility service, if appropriate.
1. Contractor shall be responsible for locating and preventing damage to known utilities.
If damage occurs, repair of utility at no additional expense to the Government.
2. If damage occurs to an unknown utility, the utility shall be repaired. An equitable adjustment will be made in accordance with the Changes clause of the General Provisions.
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 10
E. Park Entry: The contractor shall furnish a list of personnel with phone contact information.
Vehicles associated with the contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
F. Site Access: The contractor shall access the project site as outlined on the attached site map.
Do not drive vehicles off road or access non-project areas without permission from the contracting officer or COR.
G. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
H. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until
5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer. Overtime will be paid per Davis Bacon Wages Regulations. No work will be performed on weekends or on federal holidays without the advanced written authorization of the CO. Request for alternate work schedules shall be submitted to the CO/COR for approvals at least 3 business days before the requested work day.
I. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
J. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified on the attached site map or as established at the preconstruction meeting.
K. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.
L. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
M. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 11
N. Refer also to Section 01 11 40 Work Restrictions and Section 01 50 00 Temporary Facilities & Controls.
O. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent.
P. Care shall be taken to ensure that fuel, oil, and other spills do not occur. If spills occur, cleanup will be completed at no additional expense to the Government.
1.5 SPECIAL PROVISIONS
A. Permitting and Fees:
1. The Contractor is responsible for obtaining and paying for all fees and costs for necessary permits and approvals for all construction activities associated with this project.
2. Permits from the Arizona Department of Environmental Quality (ADEQ) are expected and to be needed.
3. Arthur Samons, Environmental Protection Specialist, shall be listed as the owner/operator for all NDWR, NDEP, and ADEQ applications and permits.
4. Prior to beginning any site construction, apply for and receive any needed permits and approvals from NDWR and NDEP. No work shall commence prior to receiving permits and approvals. A copy of the permits and approvals shall be forwarded to the NPS for review.
B. Time Constraints:
1. Quiet Hours in the park are from 10:00 PM until 6:00 AM. The Contractor shall not operate equipment or make loud noise between these hours.
2. No work will be performed on the weekends or on federal holidays without the advanced authorization of the COR.
C. Logistics:
1. NPS Employee access should be maintained to all facilities during construction.
The Contractor shall be responsible for the security of all materials staged/stores on LAKE NRA property.
D. Environmental Compliance Requirements:
LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 12
1. The Contractor and all employees working on the Project will be required to take “Desert Tortoise Awareness Training” which will be provided by the Government at no cost to the Contractor. This training will take approximately 30 minutes or less. The Contractor shall arrange for needed trainings by giving a minimum of 5 working day notice to the COR and NPS environmental compliance contact to schedule the trainings.
2. The Contractor’s employees shall never handle a desert tortoise.
3. The Contractor and all employees shall immediately report the presence of any desert tortoise to the COR.
4. Herbicides shall not be used in or around the Project site.
5. The environmental compliance contact for this project is Kelly Wallace. For questions or additional information, contact the following people via email.
1. Kelly Wallace, Biologist: kelly_wallace@nps.gov
2. Carrie Norman, Biologist: Carrie_Norman@nps.gov
E. Equipment Washing:
1. Equipment washing is required to preclude the introduction and spread of non-native species into the Park. Therefore, all equipment shall be cleaned outside of the Park before entering the Park. Equipment leaving the park for any reason must be rewashed before returning to the job site. Equipment that is moved from the job site, but remains within the original developed area, need not be re-washed prior to returning to the job site. It is also known that there are areas inside the Park that have non-native plants and weed species infestation. Therefore, before equipment can be moved from one developed area to another, it must be washed at the location identified on the Site Plan (see attached site plan and mileage table) to ensure weeds are not spread from one developed area to another.
2. The Contractor shall clean all equipment prior to the equipment entering Lake Mead National
Recreation Area. It is recommended that cleaning be accomplished by hot water, pressure washing, using water only. All equipment surfaces shall be cleaned, with special emphasis given to the undercarriage. This includes, but is not limited to: wheel wells, bumpers, radiator grills, springs, shock absorbers, wire harnesses, skid plates, oil pans, axles, frame ledges, buckets, tracks, belly pans, etc. Cleaning shall also include all dirt and debris inside the cab, or operator area. A Shop-Vac or commercial car wash vacuum system may be used for operator compartments, provided the method used effectively removes all visible debris.
Equipment cleaning is for the purpose of removing any seed and soil accumulations to prevent the potential spread of non-native plant and weed species from outside the park to locations inside the park. Cleaning shall be performed in a manner that will reasonably remove all visible soil, plant and other foreign material. All equipment that requires washing shall be inspected by government personnel, or contractors/partners assigned to this duty, to ensure compliance.
3. Equipment that requires washing is generally defined as track or rubber-tired machinery intended for use primarily off-road. Examples include backhoes, loaders, earthmovers, LAKE – PMIS 345222 Rehab TB Well #4 01 11 00 - 13 graders, rollers, bulldozers, water trucks, etc; or four wheel drive or passenger vehicles that are driven in off road areas. Equipment may also be stationary, such as a material screening plant, conex storage containers, or a mobile office (mobile offices may be cleaned in the same manner as operator compartments as outlined in paragraph 2). The equipment is generally under the direct control of the contractor or sub-contractors, is likely to remain on the construction site for an extended period of time, and may contain adhered soil and seed from other project sites.
4. Equipment/Vehicles that do not require washing are defined as those normally used for highway driving only, and travel primarily on paved surfaces and well-maintained service roads and parking areas (this includes approved staging areas). Examples include semi-tractor trailers, dump trucks, concrete trucks, pickup trucks, fuel trucks, service trucks, etc. These delivery and passenger vehicles are generally not under the direct control of the contractor, have no earth-moving function, and do not remain on the project site. These vehicles have a low probability of carrying adhered soil and seed from other projects. However, every vehicle and piece of equipment is subject to rejection from entering the park if there are obvious signs (covered in mud, plant material adhered to it, etc.) that it could be transporting non-native species into the park.
F. Post Equipment Washing Inspections:
1. All equipment subject to inspection will be inspected by government, or other authorized personnel prior to leaving the paved surface or designated washing area identified on the Site Plan. Equipment determined to be free of soil or mud based on visual examination by government personnel will be cleared to enter the project area or proceed to other areas of the park as appropriate. The Contractor shall arrange for needed inspections by contacting the NPS inspection office no less than 5 working days prior to the inspection. Such contact shall provide sufficient time to accommodate scheduling and travel to the site. Equipment not passing initial inspection must be rewashed outside the park at no additional expense to the government.
2. A list of government Inspectors for this project will be provided by the list below. Please contact via email all members and coordinate designated representative for inspection:
a. Kelly Wallace, Biologist: kelly_wallace@nps.gov
b. Carrie Norman, Biologist: Carrie_Norman@nps.gov
1.6 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are available upon request to supplement the information specified in the contract documents: None anticipated
END OF SECTION 01 11 00
LAKE – PMIS 345222 Rehab TB Well #4
01 11 40 - 1
WORK RESTRICTIONS
SECTION 01 11 40
1.1 PARK REGULATIONS
A. General: The Contractor must comply with the following rules and conditions:
1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.
2. Ensure equipment is conspicuously marked for identification.
3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.
4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.
5. Control and provide security of Contractor-owned equipment and materials at the work site.
Report immediately missing / lost / stolen property to the park dispatch / law enforcement rangers at 702-293-8998 NON-EMERGENCY.
6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
a. Contractor will provide the Contracting Officer with a listing of its subcontractors and their associated vehicles and employees entering the park on a daily basis.
b. Contractor will provide the Contracting Officer with a listing of anticipated deliveries for each week.
7. Vehicles / Heavy Equipment:
a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
a. Contractor will schedule an inspection with compliance of all equipment entering park. (See Section 1.3 B 1. below.)
01 11 40 - 2
b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.
c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.
e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.
f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).
Oversized vehicles must not exceed the clearances along the Park road corridor.
Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).
j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.
k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11).
01 11 40 - 3
No loads heavier than the current load rating for the historic Park bridge will be permitted.
8. Emergency Medical and Accident Reporting:
a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.
Emergency number: Dial 911 as needed.
Park Dispatch: 702-293-8932 EMERGENCY
Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park and the CO shall also be notified in writing:
Park Dispatch: 702-293-8998 NON-EMERGENCY
1.2 SITE PROTECTION
A. General: The Contractor will establish a temporary chain link fence boundary to protect and secure the site during construction.
1.3 RESOURCE PROTECTION
A. General: The park is committed protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to packing / loading. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance. Contact the resource staff directly at 702-371-9673 or 702-293-8849 at least (5) five days in advance of park entry to arrange for inspection(s) outside of park boundary.
2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact park dispatch at 702-293-8998 immediately if animal is hit or injured or will not move off of the road. All contractor personnel working in Lake Mead
01 11 40 - 4
National Recreation Area must have up-to-date Lake Mead desert tortoise awareness training. Prior to starting work, contact the resource staff directly at 702-371-9673 or 702-293-8849 at least five (5) business days in advance to schedule the desert tortoise awareness training.
3. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidences of the effects of that activity on the environment.
Archaeological resources are found above and below ground and underwater. The contractor shall appoint an archaeological monitor during all ground-disturbing activities in archaeological sensitive areas. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.
END OF SECTION 01 11 40
01 27 00 - 1
DEFINITION OF CONTRACT PRICE ITEMS
SECTION 01 27 00
DEFINITION OF CONTRACT PRICE ITEMS
1.1 DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one bid item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related bid item.
1.2 LIST OF CONTRACT LINE ITEMS
A. Contract Price Item No.001 – Rehabilitate Well #4 at TB
1. This price item consists of all necessary material, labor, equipment, and startup procedures required to inspect and clean screen, perform system evaluation, and provide recommendations for repairs to achieve flowrate. Work includes, but is not limited to, installing new downpipe, submersible pump, and associated motor. This includes any demolition work and disposal of products.
2. No separate measurement will be made.
3. Payment will be made at the contract unit price.
1.3 LIST OF SCHEDULE OF VALUES (PRICE SCHEDULE)
A. Submit a schedule of values IAW Section 01 32 16 Construction Schedule.
All listed quantities shown are estimated values and shall be validated by contractor.
Item No.
Descriptions Estimated Quantities
Unit Total ($)
Rehabilitate Well #4 at TB 1 Inspect Screen 1 LS
2 Conduct Flow/Pressure Test and Evaluate System 1 LS
3 Install 4-inch Diameter Flexible Down Pipe 300 LF
4 Provide and install Pump and Motor 1 LS
5 Replace 90 deg and meter 1 LS
TOTAL (BASE CONTRACT)
TOTAL (DIFFERING SITE CONDITION REPAIRS)
END OF SECTION 01 27 00
01 31 00 - 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00
1.1 SUBMITTALS
A. Division 01 documents: The following items shall be submitted 14 calendar days after contract award. They must be submitted prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan/ Site health & Safety Plan
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman's compensation for the Contactor and all subcontractors.
8. Waste and Recycling Plan
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.2 PROJECT MEETINGS
A. Preconstruction Conference: Once the contract is awarded, an initial orientation meeting will be scheduled for a time and date that is agreeable to the Government and Contractor and will be conducted in the Lake Mead Maintenance Building. Conference meeting may also be a teleconference or TEAMS presentation if lead by the NPS. ZOOM meeting will have to be facilitated by the contractor. Discussion of the method of the conference will be made between the CO and the contractor. Lake Mead personnel will be present to go over park specific requirements of the project with the Contractor and the Contractor's supervisory and administrative team. The Notice to Proceed date will also be established at the Preconstruction Conference.
1. Agenda: Items to be discussed will include but not be limited to:
1. Park Rules and Regulations.
2. General correspondence procedures.
3. Labor standards provisions.
4. Payroll reports.
01 31 00 - 2
5. Payments to the Contractor.
6. Acceptance/rejection of work.
7. Progress Meetings.
8. Subcontractors.
9. Documents required under contract.
10. Local emergency phone number.
11. Specifications and drawings.
2. Once the Notice to Proceed date has been established, the Contractor shall submit the proposed work schedule to the government for approval.
1.3 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit an RFI utilizing the form designated by the Contracting officer.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
7. Contractor's signature.
8. Requested date for response.
9. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination of information already indicated in the Contract
Documents.
01 31 00 - 3
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.4 COORDINATION PROCEDURES
A. Coordination: Coordinate the construction operations identified in the various Sections of this Specification to ensure the efficient installation of all materials and equipment.
1. Schedule construction operations in the proper sequence required to obtain the best results where installation of one part of the Work depends on installation of other components before or after its own installation.
2. Coordinate installation of different components with subcontractors and Government personnel to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
END OF SECTION 01 31 00
01 32 14 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 14
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 SUBMITTALS
A. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
B. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit a baseline schedule, large enough to show entire schedule for entire construction period.
C. Weekly Construction Schedule: Contractor will submit an updated schedule weekly to the contracting officer and the COR.
D. Construction Schedule Updates: Prior to the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.
1.3 COORDINATION
A. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, payment requests, and other required schedules and reports.
01 32 14 - 2
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump- sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price, or 100%. The Schedule of Values will form the basis for progress payments. Each progress payment request shall include the overall percentage complete to that date.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using computerized scheduling software.
1. Construction Baseline Schedule shall show submittal review, construction start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.
2. Establish procedures for updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. Contracting Officer may request an updated Construction Schedule at any time to confirm progress of the work.
END OF SECTION 01 32 14
01 33 00 - 1
SUBMITTAL PROCEDURES
SECTION 01 33 00
1.1 GENERAL SUBMITTAL PROCEDURES
A. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. CM-16 Transmittal Form: All submittals shall be transmitted using National Park Service form CM-16 form, attached to the end of this specification section. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Complete the general information at the top of the form.
a. Provide all required information based on the submittal type
b. Attach all related documents.
c. Sign the CM-16 form in the contractor section at the bottom of the form.
2. Submittals: Complete the CM-16 form for all submittals.
a. All permits will be submitted to the Contracting Officer prior to commencement of work.
b. All materials submittals will be approved prior to installation.
i. All Water Piping, Valves, and Appurtenances
ii. All Electrical Components and Auxiliary Equipment
1. Includes Single Line Diagram Illustrating Electrical Equipment Layout and Connections
iii. All Pump and Motor Equipment Including Flexible Downpipe
iv. Technical Approach for well pumping Test
1.2 SUBMITTAL AND APPROVAL PROCEEDURES
A. All submittals shall be transmitted electronically via email to the COR, using National Park
Service form CM-16, dated 4/00.
1. A copy of the form is included at the end of this document.
2. No action will be taken on a submittal unless it is accompanied by a transmittal form.
3. All submittals shall be carefully reviewed by the Contractor prior to submission to the Government to eliminate errors.
B. Manufactures' Catalog Sheets: Submit only pertinent pages and mark each copy of standard printed data to identify products proposed for use. Submittal forms with attached
01 33 00 - 2
Manufactures' Catalog Sheets that are not marked to identify products proposed for use will be disapproved by the COR and shall be resubmitted by the Contractor.
C. Manufactures' Installation Instructions: Provide one (1) complete set of instructions to the
COR and keep another complete set of instructions at the job site until substantial completion.
D. The Contractor shall forward submittals to the COR in accordance with the milestones listed in section 01110, paragraph 1.4.
E. The COR will review and approve, or disapprove and provide comment to submittals in as short a timeframe as possible, but not to exceed 7 calendar days.
1.3 REQUIREMENTS FOR APPROVED EQUALS
A. For each "Substitution" or "Comparable Product" the Contractor submits as being "equal" to the product that has been specified, the Contractor shall submit supporting documentation that includes:
1. Statement indicating why specified material or product cannot be provided.
2. Detailed comparison of the characteristics of the proposed item with that specified.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Product data, including drawings, descriptions, fabrication, and samples as appropriate.
6. Manufacturer's literature regarding installation, operation and maintenance, schematics for electrical systems, and parts lists.
a. Describe availability of maintenance service, and state a source of replacement parts and materials.
B. A request for approval constitutes a representation that the Contractor:
1. Has investigated the proposed item and determined that it is equal to or superior in all respects to that specified.
2. Shall provide the same warranties for the proposed item as for the item specified.
3. Has determined the proposed item is compatible with interfacing items.
4. Shall coordinate the installation of the alternate item and make all changes required in other elements of the work because of the substitution.
5. Wavier all claims for additional expenses the may be incurred as a result of the substitution.
01 33 00 - 3
D. If all of the requirements listed above are not met by the Contractor, the COR will disapprove the "Substitution" or "Comparable Product" request.
END OF SECTION 01 33 00
01 35 23 - 1
SAFETY REQUIREMENTS
SECTION 01 35 23
A. General: This section includes establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Plan: After contract award and before the Pre-Construction conference, submit for review an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within ten (10) days. No progress payments will be made until the Plan is accepted.
Overhead powerlines are located on site. Accident Prevention Plan must address crane safety around overhead utility lines.
1.3 QUALITY ASSURANCE
A. Comply with contract clauses entitled "Accident Prevention" and "Permits and Responsibilities". In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.
2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
01 35 23 - 2
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of one hundred dollars ($100).
This is the start of the file's text. The full file is on GovTribe.