This document is a Specification Sheet for Solicitation FA489724Q0008, which describes the requirements for the upgrade of the Bowling Center at Mountain Home Air Force Base. The 366th Force Support Squadron requires the installation of 16 string machine pinsetters and 8 under lane ball return systems, along with the removal and disposal of the existing equipment. The minimum specifications for the new equipment include USBC certification, compatibility with the existing Qubica AMF BES X scoring system, and the ability to notify of operational alerts and required maintenance. The Contractor will be responsible for the installation, testing, and training of government personnel on the new equipment. The Contractor will also be responsible for the removal and disposal of the existing 16 pinsetters and 8 ball return systems. The solicitation requires the Contractor to include shipping costs and provide a minimum 3-year warranty on the string machines.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA489724Q0008-Bowling Center Upgrade.pdf | ||
| SS_JA- Bowling Center Upgrade - redacted.pdf | ||
| Wage Determination 26 Dec 23.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation
FA489724Q0008
SPECIFICATION SHEET
Pinsetter and Ball Track Upgrade 29 May 2024
1.0. GENERAL:
1.1. The 366th Force Support Squadron located on Mountain Home AFB, ID requires eight (8) pairs of String Machines and eight (8) under lane ball return tracks, as well as removal and disposal of the old equipment at the Bowling Center.
1.2. The Contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items needed to setup and install the requested sixteen (16) String Machines and eight (8) under lane ball return systems and all associated hardware.
2.0. Minimum Specifications: The String Machines and under lane ball return tracks must (at a minimum) comply with the following salient characteristics:
2.1. Physical Characteristics
2.1.1. 16 String Machines (8 Pairs) and all associated hardware
2.1.2. Pins, kickbacks and spare parts kits associated with 16 String Machines
2.1.3. Eight (8) Sets of under lane ball tracks with all associated hardware
2.2. Compatability
2.2.1. United States Bowline Congress (USBC) certified to host tournaments and run leagues.
2.2.2. Compatible with existing Qubica AMF BES X Scoring system.
2.2.3. String machines must have the capabilities to notify of operational alerts and required maintenance notification and guidance.
2.3. Warranty
2.3.1. Minimum 3-year manufacture warranty on String Machines.
3.0. INSTALLATION:
3.1. The Contractor shall install all requested equipment in accordance with (IAW) manufacturer’s specifications.
3.2. The Contractor shall ensure proper operation of the installed String Machines and under lane ball return systems.
3.3. Any equipment not functioning properly IAW manufacturers specifications shall be diagnosed and repaired by the Contractor.
3.4. The Contractor shall ensure cleanliness of Government facility is maintained at all times.
3.5. The Government will inspect facility for cleanliness prior to Contractor’s departure.
3.6. Any damage done to Government property by the Contractor shall be repaired by the
Contractor at the Contractor’s expense.
4.0. Removal:
4.1. The Contractor will remove all predisclosed trade in items.
4.2. The Contractor is responsible for removal and disposal of the sixteen (16) existing 82-90XL pinsetters and replace with eight (8) pairs of String Machine Pinsetters
4.3. The Contractor is responsible for removal and disposal of the eight (8) existing under lane ball return systems and replace with eight (8) under lane ball return systems.
4.4. Cost of disposal, estimated freight and installation should be configured into the vendor’s quote for equipment replacement
5.0. Training: The Contractor shall conduct training of entire system to Government personnel.
5.1. Following completion of installation by purchaser, the Contractor shall provide technical support if there are any issues either by telephone or in person.
5.2. The Contractor will also provide a minimum 8-hour on-site training session for staff members on all associated items installed.
6.0 Specifics:
6.1. Shipping must be included in the quotation.
6.1.1. Contractor shall deliver to the Bowling Center – John Bitrick, 680 Falcon Street, Bldg 2805, Mountain Home AFB, ID, 83648
6.1.2. The Contractor shall be responsible for ensuring the safe arrival of both the trade in parts and the newly ordered equipment.
Appendix A
Parts to be Installed
In the table below are all of the parts the vendor is responsible for providing. The list will include the name of the item(s) as well as the amount of each being provided:
Items
Quantity
EDGE String- USBC Pinspotter, Pair
EDGE String- USBC Kickbacks (per lane)
Edge String USBC Spare Parts Kit (Open Market)
5HD-HUB replacement for BES X with EDGE String
CenterPunch Lighting Conqueror X Control Interface
Flat Gutters
EDGE String AMFlite Glow Pins
Underlane Ball Return Track (XLI EDGE, EDGE String)
EDGE String PSP Training, 1 day (8hours), for new installations
Appendix B
Parts for Trade In
In the table below are all of the parts being accepted by the vendor for trade in value. The list will include the name of the item(s) as well as the amount of each being provided:
Item
Quantity
4HD-HUB Only in Conjunction with EDGE String and 5HD-HUB
CenterPunch Control Interface