Specification-draft-KIMBALL DS.docx

DOCX document 2 MB Posted

Attached to
Dockside (DS): USCGC KIMBALL FY26 Repair
Solicitation number
DOCKSIDE-REPAIRS-CGC-KIMBALL-FY26
Issued by

About this file

This document is a draft specification for dockside repairs for the USCGC KIMBALL (WMSL 756), a 418-foot Coast Guard cutter homeported in Honolulu, Hawaii, scheduled for maintenance from 19 January to 15 March 2026. The specification encompasses 15 specific work items, including fire prevention, deck covering renewal, tank cleaning and inspection, fire detection system testing, hydraulic system maintenance, and various mechanical and structural repairs. Key work items involve renewing slip-resistant deck coverings, inspecting and testing folding boom cranes, modifying auxiliary seawater piping, replacing watertight doors, and installing new deck drains.

The associated federal contract opportunity indicates the U.S. Coast Guard will issue a request for proposals around 18 August 2025, with contract award anticipated between 22-24 October 2025. The procurement will use NAICS Code 336611 with a small business size standard of less than 1,300 employees. Potential contractors are invited to submit their business size/status and past performance references by 16 June 2025 to program managers Joshua Smith and Andrew Jacobs. The Coast Guard will subsequently determine whether the requirement will be set aside for small businesses (HUBZone, Service-Disabled Veteran-Owned, or Women-Owned) or remain unrestricted, with the final solicitation to be posted on SAM.gov.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC KIMBALL (WMSL 756)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2026

Developed By: Joshua B Smith(Draft-00, 28 April 2025)

TABLE OF CONTENTSComment by Kingsley, Emily R LT USCG SFLC (USA): @Smith, Joshua Blake CWO-2 USCG SFLC (USA) should this have included the DPD MI?Comment by Smith, Joshua Blake CWO-2 USCG SFLC (USA): DPD scheduled for FQ2 FY27
Revisions Recordiii
Consolidated List of Referencesiv
Consolidated List of Government-furnished Propertyix
Consolidated List of Critical Inspection Itemsx
Principal Characteristicsxi
General Requirements1
WORK ITEM 1: Fire Prevention, Provide16
WORK ITEM 2: Deck Covering (Slip-Resistant) Hangars, Renew19
WORK ITEM 3: Deck Covering (Polymeric), Repair and Seal32
WORK ITEM 4: Deck Covering (Polymeric), Renew36
WORK ITEM 5: Deck Covering (Slip-Resistant) Stern Deck, Renew41
WORK ITEM 6: Tenting (Stern Deck), Provide53
WORK ITEM 7: Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect56
WORK ITEM 8: Fire Detection System, Inspect and Test61
WORK ITEM 9: Wave Guide Dryer Flexible Hoses, Renew76
WORK ITEM 10: Folding Boom Cranes, Biennial Maintenance, Perform81
WORK ITEM 11: Incinerator, Inspect and Test89
WORK ITEM 12: Oily Water Separator (OWS) System, Inspect and Groom93
WORK ITEM 13: Auxiliary Seawater Piping, Modify98
WORK ITEM 14: QAWTDBLD 52x66 (Mafo), Replace103
WORK ITEM 15: Deck Drain, Install110

USCGC KIMBALL (WMSL-418) DOCKSIDE AVAILABILITY FY2026

ii
(Draft-00)

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iii
(Draft-00)

Consolidated List of References The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 26B-CB-IV-801-001, Rev -, Booklet of General Plans Coast Guard Drawing 35-LRI-II-801-001, Rev -, General Arrangement Coast Guard Drawing 418A-WMSL 801-001, Rev A, Booklet of General Plans Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-100-006, Rev A, Inboard and Outboard Profiles Coast Guard Drawing 418A-WMSL-167-004, Rev A, Structural Door List, Ship Wide Coast Guard Drawing 418A-WMSL-437-001, Rev B, Electrical Flowmeter Installation Auxiliary Seawater Coast Guard Drawing 418A-WMSL-526-001, Rev A, Weather Deck Drains Diagram Coast Guard Drawing 418A-WMSL-588-001, Rev A, Aviation Facilities General Arrangements Coast Guard Drawing 418A-WMSL-593-001, Rev A, Bilge & Oil Pollution Control System Diagram Coast Guard Drawing 418A-WMSL-801-012, REV -, Booklet of general plans NSC 7 ONLY Coast Guard Drawing 418A-WMSL-801-012, REV A, Booklet of general plans NSC 7 ONLY Coast Guard Drawing 750 WMSL 588-504, Rev B, Tiedown Installation for Navy H60S/H60R Helo (Stratton) Coast Guard Drawing 750-WMSL 085-025, Rev -, Compartment Areas & Volumes NSC 3 and Follow Coast Guard Drawing 750-WMSL 100-88, Rev A, General Arrangements NSC 6 & FOLLOW (AS9100001) Coast Guard Drawing 750-WMSL-085-003, REV A, Compartment areas & volumes NSC 3 & Follow (ASC308512) Coast Guard Drawing 750-WMSL-085-014, Rev A, Tank Sounding and Moment of Inertia Tables (ASC085014G) (WMSL 756 Only) Coast Guard Drawing 750-WMSL-085-025, Rev -, Compartment Areas & Volumes NSC 3 & Follow (AS3085012) Coast Guard Drawing 750-WMSL-100-035, Rev K, Unit 2340 Structure Main Deck to 01 Level - Fr 52 to Fr 64 (ASC100234) Coast Guard Drawing 750-WMSL-100-036, Rev N, Unit 3110 Structure 1st Platform and Below Frs 65-77 (ASC100311) Coast Guard Drawing 750-WMSL-100-039, Rev M, Unit 3140 Structure Mn Dk to 01 Lvl - Fr 64 to Fr 76 (ASC100314) Coast Guard Drawing 750-WMSL-100-042, Rev J, Unit 3230 Structure - 2nd Dk to Main Deck - Fr 76 to Fr 88 (ASC100323) Coast Guard Drawing 750-WMSL-100-043, Rev L, Unit 3240 - Main Deck to 01 Level - Fr 76 to Fr 82 (ASC100324) Coast Guard Drawing 750-WMSL-100-045, Rev K, 2nd Dk to Main Dk - Fr 82 to Aft (ASC100333) Coast Guard Drawing 750-WMSL-100-084, Rev -, Topside Configuration for NSC 6 & Follow Coast Guard Drawing 750-WMSL-100-090, Rev A, General Arrangements NSC 7 and Follow (AS7100001) Coast Guard Drawing 750-WMSL-100-90, Rev A, General Arrangements NSC 7 and Follow.

Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication Details Ship Wide (ASC167001) Coast Guard Drawing 750-WMSL-300-024, Rev C, Unit 2240 - Main Dk Fr 44 to Fr 52 Arr of Elect Eqpt (ASC300224) Coast Guard Drawing 750-WMSL-320-579, Rev -, Electrical Installations Iwo New Aft Folding Cranes Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets (ASC436010) Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic (ASC436028) Coast Guard Drawing 750-WMSL-500-002, Rev E, Piping and Machinery Insulation Schedule and L/M (ASC508001) Coast Guard Drawing 750-WMSL-508-001, Rev C, Piping and Machinery Insulation Schedule and L/M (ASC508001) Coast Guard Drawing 750-WMSL-516-002, Rev K, Chilled Water System Diagram (ASC516002) Coast Guard Drawing 750-WMSL-520-001, Rev H, Seawater Cooling System Diagram (ASC520001) Coast Guard Drawing 750-WMSL-520-004, Rev E, Salt Water Cooling Unit 1320 (ASC520132-SW) Coast Guard Drawing 750-WMSL-520-005, Rev E, Salt Water Cooling Unit 2110 (ASC520211-SW) Coast Guard Drawing 750-WMSL-520-008, Rev F, Salt Water Cooling Unit 2210 (ASC520221-SW) Coast Guard Drawing 750-WMSL-520-506, Rev F, Auxiliary Seawater Piping Mods FWD Fr 52 Coast Guard Drawing 750-WMSL-526-504, Rev -, Gas Turbine Exhaust Space 02-49-01-Q Deck Drain Install Coast Guard Drawing 750-WMSL-583-508, Rev -, Installations IWO Aft Folding Cranes Coast Guard Drawing 750-WMSL-588-001, Rev -, Aviation Facilities General Arrangements (ASC588001) Coast Guard Drawing 750-WMSL-588-503, Rev E, Tiedown Installation for Navy H60S/H60R Helo (Waesche Only) Coast Guard Drawing 750-WMSL-593-011, Rev B, Solid Waste System Schematic (ASC593026) Coast Guard Drawing 750-WMSL-635-002, Rev K, Insulation Arr & Details Thermal, Acoustic, & Fire (ASC635002) Coast Guard Drawing 750-WMSL-635-502, Rev -, Insulation Arr & Details Thermal, Acoustic, & Fire (WMSL 754 & Follow) Coast Guard Fleet Drawing FL-1702-11, Rev -, Inspection of Sheaves NAVSEA Drawing 167-7379842, Rev A, Procedure & Welding Sequence for Non-Ballistic, Watertight & Airtight Quick Acting or Individually Dogged Personnel Doors NAVSEA Drawing 803-1385828, Rev P, Nozzles AFFF and Washdown Systems NAVSEA Drawing 803-5184182, Rev B, Insulation, Passive Fire Protection- Installation Details NAVSEA Drawing 803-6397268, Rev B, Doors Watertight, Quick Acting Arrangement NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation for Compartments Installation Details WMSL MH-60R/S Hangar Painting Guidance, 2018, Schlemmer G.W., AIR 4.8.1.5

COAST GUARD PUBLICATIONS

, SWBS 593, Mar 2022, Bilge Water Separator Ultra-Sep American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2020, Personnel Qualification and Certification in Nondestructive Testing American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2020, 2020, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel American Welding Society (AWS) D1.1/D1.1M, 2020, Structural Welding Code – Steel Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual Coast Guard Technical Publication (TP) 7903, SWBS 583, Oct 2021, Aft Boat Handling System –Model FB90-28 Coast Guard Technical Publication (TP) 7946, SWBS 593, May 2021, Incineration Plant - Installation, Operation, Maintenance & Spare Parts Coast Guard Technical Publication (TP) 9701, SWBS 436, Sep 2020, Fire and Smoke Detection System (For Hull 756) Coast Guard Technical Publication (TP) Coast Guard Technical Publication (TP) 7346A, SWBS 593, Mar 2022, Bilge Water Separator Ultra-Sep Fire Prevention and Response Mafo Document C9402709, 2022, Parts List Mafo Drawing C9402709, Rev B, Mafo Door: W=52” x H=66” (W=1320 x H=1676) Mafo Process Guide 013, 2022, Mafo Installation Instruction, Double Door MIL-DTL-32585A, 2021, Insulation, Thermal and Acoustic, Fibrous Glass MIL-PRF-1149E, 2019, Gasket Materials, Synthetic Rubber, 50 and 65 Durometer Hardness MIL-PRF-32482A, 2020, Watertight Door, Quick-Acting, Interior MIL-PRF-900, 2020, Rubber Gasket Material, 45 Durometer Hardness MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure

NOTE

OTHER REFERENCES

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior Deck Covering Systems The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Bare Metal Power Tool Cleaning

OTHER REFERENCES

American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2020, Personnel Qualification and Certification in Nondestructive Testing American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2020, 2020, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel American Welding Society (AWS) B1.10M/ B1.10, 2016, Guide for Nondestructive Examination of Welds American Welding Society (AWS) B1.11M/B1.11, 2015, Guide for the Visual Examination of Welds ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical Apparatus.

ASTM International (ASTM) F683, 2023, Standard Practice for Selection and Application of Thermal Insulation for Piping and Machinery ASTM Internationals (ASTM) G46, 2018, Standard Guide for Examination and Evaluation of Pitting Corrosion Code of Federal Regulations (CFR) Title 29, Part 1910, 2017, Occupational Safety and Health Standards Code of Federal Regulations (CFR) Title 29, Part 1915, 2013, Occupational Safety and Health Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 40, 2013, Protection of the Environment Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation MIL-C-24757, Nov 1990, Cloth, Fiberglass, Coated MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic) MIL-PRF-24176C, 2020, Cement, Epoxy, Metal Repair and Hull Smoothing MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric MIL-PRF-24667D, 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure National Fire Protection Association (NFPA) 72, 2025 Edition, National Fire Alarm and Signaling Code NAVAIR ENGCEN Bulletin 1, Rev J; Air Capable Ship Aviation Facilities Resume Naval Sea Systems Command (NAVSEA) 0640-LP-119-0175, 2019, NAVSEA OP 4 Rev 12, Ammunition and Explosives Safety Afloat NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation for Compartments Installation Details NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Bare Metal Power Tool Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet Abrasive Blast Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 6 (WAB)/NACE WAB-3, 2015, Commercial Abrasive Blast Cleaning US Environmental Protection Agency Method 1664, Feb 1999, N-Hexane Extractable Material and Silica Gel Treated N-Hexane Extractable Material by Extraction and Gravimetry.

viii
(Draft-00)

Consolidated List of Government-furnished Property The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/UNIT)

10
Y
*CB-OTH Mark IV (Coast Guard Drawing 26B-CB-IV-801-001)
N/A
1 ea.
N/A
10
Y
*Long Range Interceptor II (LRI-II) Cutter Boat (Coast Guard Drawing 35-LRI-II-801-001)
N/A
1 ea.
N/A
12
Y
Monitor, Smart Bilge
NSN: 2040-01-600-0112Â
1 ea.
4,700.00
14
N
Mafo Door W=52 in x H=66 in (W=1320 x H=1676) Mafo C9402709, Mafo Naval Closures B.V., Netherlands (including associated frame/coaming and fitting) Painted w/ Powder Coating, White 17925
ACN : 2040-01-F21-6379 (Mafo P/N C9402709)
2 ea.
$123,500 incl. S&H
14
N
Microtherm OS-1000R MT OS-1000R 1200x600x10.5 mm HYB Bilge
Promat P/N 262175
13 ea
$153.90
14
N
GC PSA Tape 50mm (32.92m/RL)
Promat P/N 6015809
1 ea
$90.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center

ix
(Draft-00)

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
2
Deck Covering (Slip-Resistant) Hangars, Renew
5
Deck Covering (Slip-Resistant) Stern Deck, Renew
6
Tenting (Stern Deck), Provide
7
Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect
8
Fire Detection System, Inspect and Test
9
Wave Guide Dryer Flexible Hoses, Renew
10
Folding Boom Cranes, Biennial Maintenance, Perform
12
Oily Water Separator (OWS) System, Inspect and Groom
13
Auxiliary Seawater Piping, Modify
14
QAWTDBLD 52x66 (Mafo), Replace
x
(Draft-00)

Principal Characteristics

418' WMSL

Physical

Length overall
418' 0"
Length between perpendiculars
390' 0"
Maximum beam
54' 0"
Beam @ 01 level
47' 9-1/8"
Depth (01 level @ side to baseline)
39' 2-3/4"
01 deck camber foredeck
1/4" in 1'-0"
Minimum berth depth
20' 0"
Height of highest projection
Approximately 119'
Draft, design
14.40'
Design displacement
3925 long tons

Machinery

Two diesel engines
MTU 20V, 20-cylinder 9,730 SHP each
One gas turbine
General Electric LM2500; 29,500 SHP
Type of propulsion
CODAG
Electrical system
24 Volt DC
Two controllable pitch propellers
Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max
Two reduction gears
RENK
One cross connect gear
RENK

Hull

Hull material
5086 Aluminum

HSLA-80 Steel

ABS EH 36 Steel

ABS AH 36

Frame spacing

FWD of FR 9
2' 3"
FR 9 to FR 10
6' 9"
FR 10 to FR 98
4' 1"
FR 98 to FR 99
3'-8"

Electrical

Power
Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators
Shore tie cable
Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each

TANK CAPACITIES

Diesel oil
220,359 gal
Fresh water
12,454 gal
JP-5 Fuel
35,182 gal
61
(Draft-00)

00000_0824_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121) General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings None Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), L2022atest Version, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), L2022atest Version, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022Latest Version, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022Latest Version, Requirements for Preservation of Ship Structures Other References Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, at the Arrival Conference.

note NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken. Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

· ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

· ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm. For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet; for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

· SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

· SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is small quantity generator (H18690390036)

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage). Comment by Smith, Joshua Blake CWO-2 USCG SFLC (USA): @Smith, Joshua Blake CWO-2 USCG SFLC (USA) verify RAPID gate docs submitted in package

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (Frame References)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean
SSPC-SP-10/AMPP No. 2
£
SSPC-SP WJ-2/AMPP WJ-2
£
SSPC-SP-3
£
SSPC-SP-11
£
SSPC-SP-11 (inaccessible area)
£
Brush-blasting (non-metallic substrate)
£

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean
SSPC-SP-10/AMPP No. 2
£
SSPC-SP WJ-2/AMPP WJ-2
£
SSPC-SP-3
£
SSPC-SP-11
£
SSPC-SP-11 (inaccessible area)
£
Brush-blasting (non-metallic substrate)
£

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

4.2 Tank and Void Assessment form.

55500_1223_BJA_418

WORK ITEM 1: Fire Prevention, Provide

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide a fire plan, discuss fire safety procedures, maintain fire boundaries and fittings, conduct inspections and keep firefighting systems in a ready condition to address fires.

note Contractors are not required to fight fires aboard USCG Cutters

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings None Coast Guard Publications Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Other References MIL-C-24757, Nov 1990, Cloth, Fiberglass, Coated

3. REQUIREMENTS

3.1 Fire Plan. The Contractor must develop and implement a written fire plan in accordance with Paragraph 3.1 of SFLC Std Spec 5550, including Paragraph 3.1.3.

3. 1.1 Fire Prevention Responsible Party. The Contractor must appoint a Fire Prevention Responsible Party (FPRP) in accordance with Paragraph 3.1.4 of SFLC Std Spec 5550.

3.1.1.1. Any item in SFLC Std Spec 5550 that requires FPRP approval, also requires COR approval.

3.1.1.2. In addition to responsibilities listed in SFLC Std Spec 5550, the FPRP is responsible for the following tasks:

Conduct all inspections per paragraph 3.7 of this work item. The FPRP may designate a representative to conduct these inspections on their behalf.

Ensuring that contractor employees and sub-contractors understand the Fire Plan and all other requirements of this work item. This includes (but is not limited to) informing contractor/subcontractor employees of danger signals and egress procedures aboard the ship.

3.2 Fire Prevention and Response Conference. The Contractor must participate in the Fire Prevention and Response Conference as detailed in Paragraph 3.12 of SFLC Std Spec 5550.

3.2.1 At a minimum, the following personnel from the Contractor must attend the Fire Prevention and Response conference, the Fire Familiarization Tour and the Initial Inspection:

Ship availability superintendent

FPRP

3.2.2 The Fire Prevention and Response Conference, the Fire Responsibility Familiarization tour and the Initial Inspection must occur before the start of industrial work. Coordinate schedule with the COR.

note Requirements for the Initial Inspection are covered in Paragraph 3.7 of this work item

3.3 Fire Zones. The Contractor must comply with the fire zone requirements from Paragraph 3.2 of SFLC Std Spec 5550.

3.3.1 Paragraph 3.2.3 of SFLC Std Spec 5550 is only applicable if the requirements of Paragraph 3.2.2 of SFLC Std Spec 5550 cannot be accomplished.

3.3.2 All material boundaries must be treated as fire boundaries.

3.3.3 All fire curtains must meet the requirements of MIL-C-24757. Disregard the NFPA 105 requirement in Paragraph 3.2.2 of SFLC Std Spec 5550.

3.4 Inoperable Fittings Log. The Contractor must inform the COR via CFR of fittings that are blocked or made inoperable per Paragraph 3.3 of SFLC Std Spec 5550. The Contractor does not need to maintain a separate Inoperable Fittings Log.

3.5. Firefighting systems. The Contractor must maintain fire protection systems per Paragraph 3.4 of SFLC Std Spec 5550.

3.5.1 Contractor personnel are NOT authorized to operate fixed firefighting systems per Paragraph 3.4.6.6.1 of SFLC Std Spec 5550

3.5.2 The existing arrangement of AFFF equipment meets the requirements of Paragraph 3.4.11 of SFLC Std. Spec 5550. This paragraph is only applicable if the Contractor blocks or moves AFFF material or equipment.

3.5.3 The existing arrangement of portable fire extinguishers meets the 50-foot requirement of Paragraph 3.4.12.1 of SFLC Std Spec 5550. This paragraph is only applicable if the Contractor blocks or moves fire extinguishers.

3.6. Fire Alarm. The Contractor must comply with the requirements of Paragraph 3.7 of SFLC Std Spec 5550 if the fire alarm system will be manipulated. The “additional personnel” mentioned in Paragraph 3.7.1 of SFLC Std Spec 5550 must be provided by the Contractor.

3.7 Fire Prevention Inspections. The Contractor must conduct inspections in accordance with SFLC Std Spec 5550 Paragraph 3.11.

3.7.1 All inspections in paragraph 3.11 of SFLC Standard Spec 5550 must be conducted in the presence of a Coast Guard Inspector.

3.7.2 Disregard paragraph 3.11.1 of SFLC Std Spec 5550 and replace with the following:

Initial Inspection. The FPRP, along with the COR (or a designated representative), must conduct an initial inspection to evaluate potential fire hazards in all areas with scheduled work. This inspection must note the existing status of all items in Paragraph 3.11.2 of SFLC Standard Spec 5550. Submit the results of the initial inspection to the COR via a CFR. This inspection must occur before commencing industrial work.

4. NOTES

None

S25_NNN_634NN_ANS_0425_756

WORK ITEM 2: Deck Covering (Slip-Resistant) Hangars, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew deck covering with slip-resistant deck covering system (MIL-PRF-24667D Type V Comp. G/D/L Non-skid) for areas as listed in Table 1.

TABLE 1 SLIP-RESISTANT DECK COVERING

location
COMPo
AREA

(SQFT)*

SYSTEM/Appendix (sflc std 6310)
TOPCOAT color
PRESERVE

LEVEL

NOTE

Hangar Stbd & Port incl. Storerooms and Storage Areas (i.e. Helo Spares Storeroom Areas 01-47-1-Q, 01-52-1-Q, 01-52-2-Q, 01-52-2-Q, and FAS Storage Area 01-48-2-Q)

Decks, Foundation, Outfits, Fittings
2,400
Weather Decks (Weather Deck Non-Skid, MIL-SPEC Coating for Steel)
Dark Gray 36076

Match existing adjacent surfaces

Renew
MIL-PRF-24667D

Type V Comp. G/D/L Non-skid

*Approximated

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-100-006, Rev A, Inboard and Outboard Profiles Coast Guard Drawing 418A-WMSL-588-001, Rev A, Aviation Facilities General Arrangements Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans Coast Guard Drawing 750-WMSL-085-025, Rev -, Compartment Areas & Volumes NSC 3 & Follow (AS3085012) Coast Guard Drawing 750-WMSL-100-035, Rev K, Unit 2340 Structure Main Deck to 01 Level - Fr 52 to Fr 64 (ASC100234) Coast Guard Drawing 750-WMSL-100-039, Rev M, Unit 3140 Structure Mn Dk to 01 Lvl - Fr 64 to Fr 76 (ASC100314) Coast Guard Drawing 750-WMSL-100-084, Rev -, Topside Configuration for NSC 6 & Follow Coast Guard Drawing 750-WMSL-588-503, Rev E, Tiedown Installation for Navy H60S/H60R Helo (Waesche Only) Coast Guard Drawing 750 WMSL 588-504, Rev B, Tiedown Installation for Navy H60S/H60R Helo (Stratton) WMSL MH-60R/S Hangar Painting Guidance, 2018, Schlemmer G.W., AIR 4.8.1.5 Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Other References American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2020, Personnel Qualification and Certification in Nondestructive Testing American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2020, 2020, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel American Welding Society (AWS) B1.10M/ B1.10, 2016, Guide for Nondestructive Examination of Welds American Welding Society (AWS) B1.11M/B1.11, 2015, Guide for the Visual Examination of Welds ASTM Internationals (ASTM) G46, 2018, Standard Guide for Examination and Evaluation of Pitting Corrosion MIL-PRF-24176C, 2020, Cement, Epoxy, Metal Repair and Hull Smoothing MIL-PRF-24667D, 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure NAVAIR ENGCEN Bulletin 1, Rev J; Air Capable Ship Aviation Facilities Resume Naval Sea Systems Command (NAVSEA) 0640-LP-119-0175, 2019, NAVSEA OP 4 Rev 12, Ammunition and Explosives Safety Afloat The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Bare Metal Power Tool Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet Abrasive Blast Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s) :

· 3.3 Operational test - initial

· 3.4 Inspection

3.1.2 Tech Rep. The Contractor must provide the services of a qualified and certified Tech Reps and personnels as follows :

· NDE Tech Rep : NDE Operator/Level 1

· Preservation Tech Rep : AMPP Senior Certified Coatings Inspector (NACE CIP Level 3/SSPC PCI Level 3) with Marine Coatings Inspection Specialty

3.1.2.1 NDE Tech Rep. The Contractor must provide the services of a qualified and certified NDE Operator/Level 1 as follows:

· Perform NDE Operations.

3.1.2.1.1 Qualifications/certifications. NDE Operator/Level 1 certified and qualified in accordance with ASNT No. SNT-TC-1A. Submit the Tech Rep’s qualifications/certifications to the COR at the Arrival Conference.

3.1.2.1.2 Dates of services. Include the dates of services in which Tech Reps must be on site as per their subcontract documentation.

3.1.2.2 Preservation Tech Rep. The Contractor must provide the services of a Certified Coating Inspector having successfully completed relevant AMPP (NACE/SSPC) Programs and Trainings to:

· Serve as an Independent Coating Tech…