Specification Document.pdf

PDF 70 KB Posted

Attached to
Altitude Simulation System Federal contract opportunity
Solicitation number
12505B24Q0311
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area

About this file

This document is a Specification Document for an Altitude Simulation System. The system must have interior dimensions of at least 15" x 15" x 15" and exterior dimensions no greater than 60" (W) x 30" (D) x 30" (H). It must have a pressure range of 1,000' to 8,000' and include a controller unit to monitor and maintain pressure within the chamber. The system must also have an electrical access port, blank vacuum ports, and a manual control valve.

The related federal contract opportunity is a Request for Quote (RFQ) for an Altitude Simulation System. The USDA has a requirement for this system, with the location being aboard the USDA in Madison, WI. This is a Total Small Business Set Aside, with a NAICS code of 334516 (Analytical Laboratory Instrument Manufacturing). Quotes are due by 5:00 PM Eastern Time on August 15, 2024, and the basis for award is Lowest Price Technically Acceptable (LPTA). Contractors must be registered in the System for Award Management (SAM) to be eligible for award.

View the file

Other files for this federal contract opportunity

Other files attached to Altitude Simulation System, newest first.
File Type Posted
Provisions and Clauses.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Product specifications for altitude simulation unit:

• Interior dimensions (minimum dimensions): 15” x 15” 15”

• Exterior dimension (maximum dimensions): 60” (W) x 30” (D) x 30” (H)

• Pressure range (minimum): 1,000’ – 8,000’

• Features a controller unit that will monitor pressure within the chamber, recognize when pressures have diverged from a given setting, and then re-pressurize as needed.

• Whole system needs to include the pump, controller unit, and chamber.

• Requires electrical access port to use specialized equipment when chamber is pressurized.

• Blank vacuum ports for adding more options to increase potential uses in the future.

• Manual control valve to create vacuum leak necessary for bringing fresh air into the chamber.