Special Terms & Conditions PIM 45.pdf

PDF 167 KB Posted

Attached to
Trimble Rd. Culvert Failure Replacement
Solicitation number
QQ-126809
Issued by
New Kent County, Virginia

About this file

This Special Terms and Conditions document outlines the procurement requirements for the Commonwealth of Virginia's Trimble Road Culvert Failure Replacement project at Fort Pickett Training Area, which involves the excavation, removal, and replacement of a damaged culvert on Trimble Road north of the Range Control Range Gate entry. The solicitation requires attendance at a mandatory pre-bid conference scheduled for 2:00 p.m. on August 25, 2026, in Building 229 Conference Room, with bids accepted only from representatives present at this meeting. The contractor must complete delivery and performance within 60 calendar days after receipt of order, unless an alternative delivery timeframe is specified in the bid response. Bidders are required to provide at least three references documenting similar work experience, and any subcontracting requires prior written approval from the purchasing agency with the prime contractor retaining full liability for all work performed.

Award will be made to the lowest responsive and responsible bidder based on net prices, with unit prices, extensions, and grand totals required in bid submissions. All contractors and subcontractors must maintain proper licensing throughout the contract term and immediately notify the agency of any license revocation. For employers with more than 50 employees on average during the previous 12 months, participation in the E-Verify program is mandatory for contracts exceeding $50,000. The contractor must retain all books, records, and contract-related documents for five years after final payment and permit full access to the Commonwealth, its agents, and state auditors for examination. The Commonwealth reserves the right to cancel the contract without penalty upon 60 days' written notice and may reject any or all bids in whole or in part. Bid validity extends for 30 days from submission, and all contractors must demonstrate job site inspection prior to bidding and full operational compliance with contract specifications and applicable codes upon project completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B-1 B-1

SPECIAL TERMS AND CONDITIONS

GOODS AND NONPROFESSIONAL SERVICES

1. AUDIT: The contractor shall retain all books, records, and other documents relative to this contract for five (5) years after final payment, or until audited by the Commonwealth of Virginia, whichever is sooner. The agency, its authorized agents, and/or state auditors shall have full access to and the right to examine any of said materials during said period.

2. AWARD OF CONTRACT: All solicitations must contain one of the following award clauses to specify the method of award.

A. AWARD: An award will be made to the lowest responsive and responsible bidder. Evaluation will be based on net prices. Unit prices, extensions and grand total must be shown. In case of arithmetic errors, the unit price will govern. If cash discount for prompt payment is offered, it must be clearly shown in the space provided. Discounts for prompt payment will not be considered in making awards. The State reserves the right to reject any and all bids in whole or in part, to waive any informality, and to delete items prior to making an award.

3. CANCELLATION OF CONTRACT: The purchasing agency reserves the right to cancel and terminate any resulting contract, in part or in whole, without penalty, upon 60 days written notice to the contractor. Any contract cancellation notice shall not relieve the contractor of the obligation to deliver and/or perform on all outstanding orders issued prior to the effective date of cancellation.

4. eVA ORDERS AND CONTRACTS: The solicitation/contract will result in one (1) purchase order(s) with the applicable eVA transaction fee assessed for each order.

Vendors desiring to provide goods and/or services to the Commonwealth shall participate in the eVA eProcurement Program and agree to comply with the following: If this solicitation is for a term contract, failure to provide an electronic catalog (price list) or Punch-Out Catalog for items awarded will be just cause for the Commonwealth to reject your bid/offer or terminate this contract for default. The format of this electronic catalog shall conform to the eVA Catalog and/or Punch-Out Catalog Specification. For further information and details please email eVA-catalog- manager@dgs.virginia.gov.

5. BID ACCEPTANCE PERIOD: Any bid in response to this solicitation shall be valid for thirty (3 0 ) days. At the end of the days the bid may be withdrawn at the written request of the bidder. If the bid is not withdrawn at that time it remains in effect until an award is made or the solicitation is canceled.

6. CONTRACTOR/SUBCONTRACTOR LICENSE REQUIREMENT: By my signature on this solicitation, I certify that this firm/individual and subcontractor is properly licensed for providing the goods/services specified.

Furthermore, the contractor and subcontractors shall maintain the required license throughout the term of the contract. The contractor or their subcontractor shall immediately notify the contracting agency in writing in the event the license has been revoked.

Contractor Name:

License # Type

Subcontractor Name:

License # Type

7. CONTRACTOR REGISTRATION: If a contract for construction, removal, repair or improvement of a building or other real property is for $120,000 or more, or if the total value of all such contracts undertaken by bidder/offeror within any 12-month period is $750,000 or more, the bidder/offeror is required under Title 54.1-mailto:manager@dgs.virginia.gov

B-2 B-2

1100, Code of Virginia (1950), as amended, to be licensed by the State Board of Contractors a “CLASS A CONTRACTOR.” If such a contract is for $10,000 or more but less than $120,000, or if the total value of all such contracts undertaken by bidder/offeror within any 12-month period is $150,000 or more, but less than $750,000 or more, the bidder is required to be licensed as a “CLASS B CONTRACTOR.” If such a contract is over $1,000 but less than $10,000, or if the contractor does less than $150,000 in business in a 12-month period, the bidder is required to be licensed as a “CLASS C CONTRACTOR.” The board shall require a master tradesmen license as a condition of licensure for electrical, plumbing and heating, ventilation and air conditioning contractors. The bidder/offeror shall place on the outside of the envelope containing the bid/proposal and shall place in the bid/proposal over his signature whichever of the following notations is appropriate, inserting his contractor license number:

Licensed Class A Virginia Contractor No. Specialty Licensed Class B Virginia Contractor No. Specialty Licensed Class C Virginia Contractor No. Specialty

If the bidder/offeror shall fail to provide this information on his bid/proposal or on the envelope containing the bid/proposal and shall fail to promptly provide said contractor license number to the Commonwealth in writing when requested to do so before or after the opening of bids/proposals, he shall be deemed to be in violation of § 54.1-1115 of the Code of Virginia (1950), as amended, and his bid/proposal will not be considered.If a bidder/offeror shall fail to obtain the required license prior to submission of his bid/proposal, the bid/proposal shall not be considered.

8. DELIVERY: Delivery of goods or performance of services shall be within the number of calendar days stated below after receipt of order (ARO) by the bidder/offeror. The Agency requires the (bidder/offeror) to deliver within a reasonable time after ARO. If the bidder/offeror does not insert a stated delivery time in the blank below, the (bidder/offeror) will be deemed to offer delivery in accordance with the Agency’s desired delivery time as stated below:

Agency’s desired delivered time: 6 0 calendar days ARO

BIDDER’S/OFFEROR’S STATED DELIVERY TIME: CALENDAR DAYS ARO

9. DELIVERY AND STORAGE: It shall be the responsibility of the contractor to make all arrangements for delivery, unloading, receiving and storing materials in the building during installation. The owner will not assume any responsibility for receiving these shipments. Contractor shall check with the owner and make necessary arrangements for security and storage space in the building during installation.

10. FINAL INSPECTION: At the conclusion of the work, the contractor shall demonstrate to the authorized owners representative that the work is fully operational and in compliance with contract specifications and codes. Any deficiencies shall be promptly and permanently corrected by the contractor at the contractor’s sole expense prior to final acceptance of the work.

11. INSPECTION OF JOB SITE: My signature on this solicitation constitutes certification that I have inspected the job site and am aware of the conditions under which the work must be accomplished. Claims, as a result of failure to inspect the job site, will not be considered by the Commonwealth.

A. PREBID/PREPROPOSAL CONFERENCE - MANDATORY: A mandatory pre-bid conference will be at 2:00 p.m., August 25, 2026 at the Building 229 Conference Room. The purpose of this conference is to allow potential bidders/offerors an opportunity to present questions and obtain clarification relative to any facet of this solicitation.

Due to the importance of all bidders/offerors having a clear understanding of the specifications/scope of work and requirements of this solicitation, attendance at this conference will be a prerequisite for submitting a bid/proposal. Bids/Proposals will only be accepted from those bidders/offerors who are represented at this pre-bid conference. No one will be admitted after 2:01 p.m.

B-3 B-3

Bring a copy of the solicitation with you. Any changes resulting from this conference will be issued in a written addendum to the solicitation.

12. REFERENCES: Bidders shall provide a list of at least 3 references where similar goods and/or services have been provided. Each reference shall include the name of the organization, the complete mailing address, the name of the contact person and telephone number.

ORGANIZATION ADDRESS CONTACT PERSON TELEPHONE

1.

2.

3.

13. SUBCONTRACTS: No portion of the work shall be subcontracted without prior written consent of the purchasing agency. In the event that the contractor desires to subcontract some part of the work specified herein, the contractor shall furnish the purchasing agency the names, qualifications and experience of their proposed subcontractors. The contractor shall, however, remain fully liable and responsible for the work to be done by its subcontractor(s) and shall assure compliance with all requirements of the contract.

14. E-VERIFY PROGRAM: EFFECTIVE 12/1/13. Pursuant to Code of Virginia, §2.2-4308.2., any employer with more than an average of 50 employees for the previous 12 months entering into a contract in excess of $50,000 with any agency of the Commonwealth to perform work or provide services pursuant to such contract shall register and participate in the E-Verify program to verify information and work authorization of its newly hired employees performing work pursuant to such public contract. Any such employer who fails to comply with these provisions shall be debarred from contracting with any agency of the Commonwealth for a period up to one year. Such debarment shall cease upon the employer’s registration and participation in the E-Verify program.

If requested, the employer shall present a copy of their Maintain Company page from E-Verify to prove that they are enrolled in E-Verify.

15. FEDERALLY IMPOSED TARIFFS: In the event that the President of the United States, the United States

Congress, Customs and Border Protection, or any other federal entity authorized by law, imposes an import duty or tariff (a “tariff”), on an imported good that results in an increase in contractor’s costs to a level that renders performance under the Agreement impracticable, the Commonwealth may agree to an increase to the purchase price for the affected good. No increase in purchase price may exceed 25% of the additional tariff imposed on the goods imported or purchased by the contractor that are provided to the Commonwealth under this Agreement.

Prior to the Commonwealth agreeing to a price increase pursuant to this Section, the contractor must provide to the Commonwealth, the following documentation, all of which must be satisfactory to the Commonwealth:

- evidence demonstrating: (i) the unit price paid by contractor as of the date of award for the good or raw material used to furnish the goods to the Commonwealth under this Agreement, (ii) the applicability of the tariff to the specific good or raw material, and (iii) contractor’s payment of the increased import duty or tariff (either directly or through an increase to the cost paid for the good or raw material). The evidence submitted shall be sufficient in detail and content to allow the Commonwealth to verify that the tariff is the cause of the price change.

- a certification signed by contractor that it has made all reasonable efforts to obtain the good or the raw materials comprising the good procured by the Commonwealth at a lower cost from a different source located outside of the country against which the tariff has been imposed.

- a certification signed by contractor that the documentation, statements, and any other evidence it

B-4 B-4 submits in support of its request for a price increase under this Section are true and correct, and that the contractor would otherwise be unable to perform under this Agreement without such price increase.

- as requested by the Commonwealth, written instructions authorizing the Commonwealth to request additional documentation from individuals or entities that provide the good or the raw materials to verify the information submitted by contractor.If the Commonwealth agrees to a price increase pursuant to this Section, the parties further agree to add the following terms to this Agreement:

- During the Term and for five (5) years after the termination of this Agreement, contractor shall retain, and the Commonwealth and its authorized representatives shall have the right to audit, examine, and make copies of, all of contractors books, accounts, and other records related to this Agreement and contractor’s costs for providing goods to the Commonwealth, including, but not limited to those kept by the contractor’s agents, assigns, successors, and subcontractors.

- Notwithstanding anything to the contrary in this Agreement, the Commonwealth shall have the right to terminate this Agreement for the Commonwealth’s convenience upon 15 days’ written notice to contractor.

In the event the import duty or tariff is repealed or reduced prior to termination of this Agreement, the increase in the Commonwealth’s contract price shall be reduced by the same amount and adjusted accordingly.

- Any material misrepresentation of fact by contractor relating in any way to the Commonwealth’s payment of additional sums due to tariffs shall be fraud against the taxpayer’s of the Commonwealth and subject contractor to treble damages pursuant to the Virginia Fraud Against Taxpayers Act.

BIDDER’S/OFFEROR’S STATED DELIVERY TIME: CALENDAR DAYS ARO
*

File details come from the government source that posted it. Updated .