This is a Special Provisions document for Invitation for Bids (IFB) No. 199619 issued by the City of Palo Alto for the FY 2027 Sidewalk, Curb & Gutter Project. The project encompasses repair and replacement of sidewalks, curb ramps, and installation of valley gutters across multiple city districts, with a specific focus on modernizing curb ramps to achieve ADA compliance. The contractor must assign a full-time Project Manager/Supervisor onsite and submit weekly rolling three-week look-ahead schedules tied to the Construction Schedule for review by the Construction Manager. Site-specific Traffic Control Plans (TCPs) must be submitted within five days of the Notice to Proceed for University Avenue and Cambridge Avenue locations, organized by road width, road type, and applicable features such as bike lanes and medians. Construction in the public right-of-way is prohibited from Thanksgiving through New Year's Day within designated downtown business districts on University Avenue (from Lytton Avenue to Forest Avenue and from Alma Street to Webster Street) and California Avenue (from Cambridge Avenue to Sherman Avenue and from El Camino Real to Park Boulevard). The contractor must coordinate work around holiday closures and obtain notification from residents before performing construction activities in any area.

This is a federally assisted construction project funded through Community Development Block Grant (CDBG) sources, requiring compliance with federal and state labor standards, prevailing wage requirements, and HUD Section 3 provisions. The contractor must obtain Builder's Risk insurance on a 100% completed value basis and submit certified electronic payroll records directly to the State Labor Commissioner. Contractors must comply with Executive Orders 11246 and 11375, the Davis-Bacon and Related Acts, Section 3 of the Housing and Urban Development Act of 1968, and the Copeland "Anti-Kickback" Act. Section 3 benchmarks require 25% or more of labor hours for Section 3 workers, 5% or more for Targeted Section 3 workers, 10% or more of construction dollars for Section 3 Business Concerns, and 3% or more of non-construction dollars for qualified local Section 3 businesses. All bidders must complete and submit CDBG Labor Compliance Bid Forms with their bids, including Equal Employment Opportunity Certification (HUD-92010), Federal Lobbyist Certification, Non-Segregated Facilities Certification, Non-Collusion Affidavit, Workers' Compensation Certification, and Section 3 compliance documentation. Employee interviews will be conducted on 10% of each contractor's work crew for each trade utilized on the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

IFB NO. 199619

PROJECT TITLE: FY 2027 Sidewalk, Curb & Gutter Project

These Special Provisions apply to this Project in addition to the General Conditions as indicated below. Terms used in these Special Provisions which are defined in the General Conditions have the meanings assigned to them in the General Conditions.

SECTION 1 – PROJECT STAFF

|X| At a minimum, the onsite staff assigned to this Project on a full-time basis must include the following positions and required qualifications and experience:

· Project Manager/Supervisor

SECTION 2 – PROJECT SCHEDULE

|X| The Contractor shall provide weekly rolling three-week look-ahead schedules that are tied to the Construction Schedule for review by the Construction Manager. The weekly look-ahead schedules must be submitted to the Construction Manager on a weekly basis.

SECTION 3 -- TRAFFIC CONTROL

|X| Within five (5) days of issuance of the Notice to Proceed Contractor is required to submit all Traffic Control Plans (TCP) for review and approval of the City Traffic Engineer. If City Engineer rejects a Traffic Control Plan, the contractor will resubmit a revised Plan to address comments from City Traffic Engineer.

Site-specific traffic control plans shall be submitted to the Engineer for the following locations:

· University Avenue Locations

· Cambridge Avenue Locations

Additional site-specific traffic control plans may be requested by the Engineer.

The Contractor shall provide separate traffic control plans for each roadway configuration. Generic or typical TCPs will not be accepted. TCPs shall be organized by road width, road type, and applicable features, including, but not limited to, bike lanes, center medians, and other roadway characteristics. Each TCP shall identify the applicable project Location Number(s). Where a project location contains a unique feature or condition that is not represented by other TCPs, a site-specific TCP shall be prepared and submitted for that location.

The Contractor is not allowed to perform any construction activities in an area prior to notification of residents and receiving an approved TCP.

SECTION 4 – INSURANCE REQUIREMENTS

|X| The insurance limits specified in Article 11 of the General Conditions of the IFB are modified as follows:

Builder’s Risk Insurance: Contractor must obtain, at Contractor’s sole expense, a Builder’s Risk insurance policy issued on an occurrence basis, for all-risk coverage on a one hundred percent (100%) completed value basis on the insurable portion of the Project for the benefit of City.

SECTION 5 – LABOR STANDARDS REQUIREMENTS

|X| This is a federally assisted construction project/contract and the Contractor shall agree to comply with the requirements of the Secretary of Labor and U.S. Department of Housing and Urban Development. See SPECIAL PROVISIONS, ATTACHMENT A – LABOR STANDARDS REQUIREMETNS and ATTACHMENT B – FEDERAL LABOR STANDARDS PROVISIONS (HUD-4010) for additional details.

SECTION 6 – CONSTRUCTION LIMITATIONS

|X| The Contractor shall coordinate work around holiday closures within the University Avenue and California Avenue downtown business districts. For University Avenue, the closure limits extend from Lytton Avenue to Forest Avenue and from Alma Street to Webster Street. For California Avenue, the closure limits extend from Cambridge Avenue to Sherman Avenue and from El Camino Real to Park Boulevard. Construction in the public right-of-way is not permitted from Thanksgiving through New Year’s Day. This includes street closures, lane reductions, sidewalk closures, and parking lot closures. Construction may resume following New Year’s Day.

SECTION 7 – COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) BID DOCUMENTS

|X| See SPECIAL PROVISIONS, ATTACHMENT C – CDBG LABOR COMPLIANCE BID FORMS for additional details.

· CDBG LABOR COMPLIANCE BID FORMS REQUIRED WITH BID SUBMISSION:

Bidders are required to complete, sign, and submit all forms, certifications, schedules, and attachments included in Attachment C at time of bid. Failure to complete and submit any required form, or the submission of incomplete, modified, or conditional forms, may result in the bid being determined nonresponsive.

· Contractor Information

· Contractor List of Proposed Subcontractors

· Equal Employment Opportunity Certification (form HUD-92010)

· Past Performance Certification

· Form fields within the blue rectangle must be completed regardless if the bidder has or has not participated in a previous contractor or subcontract subject to the Equal Opportunity Clause. Information should be filled out based on this project (IFB 190538A).

· Federal Lobbyist Certification

· Non-Segregated Facilities Certification

· Non-Collusion Affidavit

· Compliance with Clean Air and Water Acts

· Workers’ Compensation Certification

· HUD Form 4230 A – U.S. Department of Housing and Urban Development Report of Additional Classification and Rate

· Declaration of Intent to Comply with Section 3 Requirements

· Section 3 Business Concern Certification

· Certification of Understanding and Authorization

· Section 3 Commitment - Required if Awarded Contract and to be submitted within 1 week of Notice of Intent to Award

· CDBG LABOR COMPLIANCE BID FORMS (PROVIDED FOR REFERENCE)

· Contractor Fringe Benefit Statement

· Payroll

· Statement of Compliance

END OF SECTION

ATTACHMENT A

LABOR STANDARDS REQUIREMENTS

LABOR STANDARDS AND CIVIL RIGHTS: Contractor agrees to comply with the requirements of the Secretary of Labor and the latest amendments to: Executive Orders 11246 and 11375, as supplemented in Department of Labor regulations (41 C.F.R. chapter 60); the Copeland “Anti-Kickback” Act (18 U.S.C. § 847) as supplemented in Department of Labor regulations (29 C.F.R. part 3); Section 3 of the Housing and Urban Development Act of 1968 (12 U.S.C. §§ 1701 et seq.); Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000); Section 109 of Title I of the Housing and Community Development Act of 1974 (42 U.S.C. §§ 5301 et seq.); the Age Discrimination Act of 1975 (42 U.S.C. §§ 6101 et seq.); and Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. §§ 701 et seq.). Contractor agrees to comply with the requirements of all other applicable federal, State, and local laws and regulations.

STATE LABOR STANDARDS & WAGE REQUIREMENTS: In entering into a public works contract, or a subcontract, to supply goods, services, or materials pursuant to a public works contract, the Contractor and all subcontractors agree to follow the State Labor Standards. State Labor Standards provisions, including prevailing wage requirements, will be enforced such that the general rate of per diem wages (prevailing wage) shall be paid for each craft, classification, or type of worker needed to execute the contract to all workers employed in the execution of the contract. All contractors and subcontractors must furnish electronic certified payroll records directly to the Labor Commissioner (aka Division of Labor Standards Enforcement). The State General Prevailing Wage Determination is as established by the California Department of Industrial Relations (available at http://www.dir.ca.gov/DLSR/PWD/index.htm). The prevailing rate of per diem wages are on file at the City of Palo Alto, 250 Hamilton Avenue, Palo Alto, CA, 94301, and are available to any interested party on request.

The Contractor’s duty to pay State prevailing wages can be found under Labor Code Section 1770. et. seq. and Labor Code Sections 1775 and 1777.7 outline the penalties for failure to pay prevailing wages and employee apprentices including forfeitures and debarment.

FEDERAL PREVAILING WAGE STATEMENT: This is a federally assisted construction contract. Federal Labor Standards Provisions, including prevailing wage requirements of the Davis-Bacon and Related Acts (DBRA) will be enforced. In the event of a conflict between Federal and State wage rates, the higher of the two will prevail.

CERTIFIED PAYROLL SUBMISSION TO THE CITY OF PALO ALTO: Pursuant to the provisions of Labor Code Section 1776, Contractor shall keep and shall cause each subcontractor performing any portion of the work under this Contract to keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by Contractor or subcontractor in connection with the work. Such payroll records for Contractor and all subcontractors shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor pursuant to the provisions of Section 1776 of the Labor Code. Contractor's failure to furnish such records to City or City's authorized Labor Compliance representative in the manner provided herein for notices shall entitle City to withhold the penalty prescribed by law from progress payments due to Contractor.

Each contractor and every subcontractor and supplier shall be required to submit certified payrolls and labor compliance documentation electronically at the discretion and manner specified by the City of Palo Alto.

SECTION 3 STATEMENT: This is a HUD Section 3 covered construction contract and requires compliance with the Section 3 Business and Worker goals outlined in Section 3 of the Housing and Urban Development Act. Bidders must complete and sign the Declaration of Intent to Comply with Section 3 Requirements form and submit with bid. Failure to do so may disqualify the bid.

The awarded prime contractor and subcontractors of all tiers must work with the Labor Compliance Officer to create Section 3 Commitment and Outreach Efforts plans. The Contractor and subcontractors must, to the greatest extent possible, provide training, employment, contracting, and other economic opportunities to low and very low-income persons and local businesses.

The benchmark for Section 3 workers is set at 25% or more of the total number of labor hours to be worked on the Project. The benchmark for Targeted Section 3 workers is set at 5% or more of the total number of labor hours worked on the Project. Contractor is allowed to count the Targeted Section 3 worker hours from the Section 3 worker hours.

The benchmark for Section 3 Business Concern is set at 10% or more of the total construction dollars to be awarded to local and qualified Section 3 businesses. The benchmark for Section 3 Business Concern is set at 3% or more of the total non-construction dollars to be awarded to local and qualified Section 3 businesses.

EQUAL EMPLOYMENT OPPORTUNITY EMPLOYEE INTERVIEWS

Legal authorization for conducting employee interviews is defined in the federal Copeland “Anti-kickback” Act, which requires that employee interviews be conducted on all public works construction projects that use federal funds.

Contractors are advised that 10% of each contractor’s work crew for each trade to be utilized on this Project will be interviewed.

Invitation for Bids (IFB) Package 136 Rev. July 2023

PART 7 – SPECIAL PROVISIONS

ATTACHMENT B

FEDERAL LABOR STANDARD PROVISIONS (HUD-4010)

ATTACHMENT C

CDBG LABOR COMPLIANCE BID FORMS

Invitation for Bids (IFB) Package 136 Rev. September 29, 2026

PART 7 – SPECIAL PROVISIONS

image1.png image2.png