Special Conditions for NAL (002).docx
DOCX document 8 MB Posted
- Solicitation number
- 1232SA21R0009
About this file
This document outlines a federal contract opportunity for design-build services to replace boilers at the National Agricultural Library in Beltsville, Maryland. The project involves replacing three existing 5000 MBH boilers with new high-efficiency boilers, along with associated mechanical equipment, piping, and construction work. The contract is estimated to exceed $1 million with a 365-day performance period. The solicitation will use a two-phase design-build process and be set aside for small businesses. Phase one will evaluate past performance and management approach to shortlist up to four firms, who will then submit detailed technical proposals and pricing for phase two. The Department of Agriculture is the contracting agency. Proposals are due by July 20, 2021 and shall be submitted electronically to the specified email address.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| STATEMENT OF WORK.docx | DOCX document | |
| SF 1442 - SOLICITATION - VERSION 4.pdf | ||
| WAGE DETERMINATION.pdf | ||
| SOLICITATION - SECTIONS B - M.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment I
SPECIAL CONDITIONS FOR NATIONAL AGRICULTURAL LIBRARY (NAL)
USDA/ARS/NAL
2-01 TECHNICAL REPRESENTATIVE: The Contracting Officer's Representative (COR) will be a United States Department of Agriculture, Agricultural Research Service, employee or authorized representative, appointed by the Contracting Officer (CO). The duties of the COR will be delineated in a letter prepared by the CO, and a copy will be provided to the contractor no later than concurrent with issuance of the Notice-to-Proceed.
2-02 CONTRACT DRAWINGS AND SPECIFICATIONS: The contract drawings and specifications are the property of the Government and shall not be used for any purpose other than that indicated by the specifications.
2-03 NAL REGULATIONS: The contractor shall be responsible for providing and placing all barricades, lighting, and safety devices during construction activities.
2-04 SAFETY:
a. The contractor shall have prior approval from the COR before any exit or exit access is obstructed or closed. The closing or obstructing of exits is discouraged and shall be prevented whenever feasibly possible. No padlock, chain, or other securing device will be used to prevent escape from the egress side of an exit or exit access while the construction area is occupied. This does not preclude securing the area at night as long as it does not affect the exit from non-construction areas.
b. The contractor shall immediately call 9-911 and the COR, and the Safety, Occupational Health and Environment Staff(SOHES) at 301-504-5557 on any Maryland Department of the Environment (MDE) or Environmental Protection Agency (EPA) reportable spill of hazardous substances or materials, and oils or other petroleum pollutants. The contractor shall then institute appropriate spill control measures/procedures as soon as possible. The contractor is responsible for all spill mitigation/cleanup expenditures associated with the spill/release.
c. The contractor shall comply with all confined space entry procedures that are required while performing work for NAL.
d. The contractor shall comply with all Lockout/Tagout procedures that are required while performing work for NAL.
e. The contractor shall report to the COR all OSHA reportable injuries and illnesses to contractor employees within 24 hours of the injury or illness. All lost-time
SPECIAL CONDITIONS FOR NATIONAL
AGRICULTURAL LIBRARY (NAL) 1
USDA/ARS/NAL
cases shall be reported to the appropriate authorities and the COR within 8 hours. An updated copy of the OSHA Injury and Illness Log shall be provided by the contractor at least monthly. A copy of the contractor's accident investigation reports shall be forwarded to the COR within 24 hours of the accident time.
f. The contractor shall maintain on-site complete safety procedures and documentation, and ensure he implements a continuous program of employee safety education and awareness through use of training sessions, literature, posters, and work site inspection.
2-05 HAZARDOUS MATERIALS:
a. All work performed using hazardous materials that off-gas or produce toxic/volatile organic compounds shall be accomplished outside normal work hours, unless it is possible to contain the toxic material, or vent the volatile organic compounds to the outside.
(Volatile=vaporizable; off-gasing)
b. A plan for containment and prevention of release of hazardous material must be submitted to the COR and approved prior to commencement of any activities involving toxic materials or volatile organic compounds. Examples of tasks where off-gasing of toxic materials and volatile organic compounds will occur include painting with epoxy or enamel base paints, installing carpet using an organic base mastic, installing epoxy resin fiberglass duct, use of adhesives, use of some cleaning agents, and caulking with a solvent-based material. These examples are only a few of the possible operations that can generate toxic material or volatile organic compounds in occupied buildings and that may require work to be performed outside of normal work hours.
c. The contractor shall provide the COR with copies of all Material Safety Data Sheets (MSDS) for all hazardous materials to be used, prior to the start of work.
2-06 DUST CONTROL: During construction, dust is inevitable in certain remodeling operations; therefore, the contractor shall control dust particles by sealing off areas with dust-tight barriers, plastic covers, and dust-free materials, as indicated by the contract and/or applicable Federal, State, and Local regulations. If protective barriers are not used in an area utilized by employees, then the dust produced from the operation shall be immediately vacuumed with a HEPA-type vacuum cleaner. Protection of furniture, equipment, and carpeting by use of clean drop cloths is mandatory. All furniture and carpeting shall be thoroughly cleaned to the satisfaction of the COR at the completion of the remodeling operation and returned to its original condition.
2-07 DELETED
SPECIAL CONDITIONS FOR NATIONAL
AGRICULTURAL LIBRARY (NAL) 2
USDA/ARS/NAL
2-08 MOVING AND PROTECTION OF PROPERTY: The contractor shall be responsible for moving and protecting the furnishings in the work area and for placing the furnishings in their original position and condition upon completion of the work. The contractor shall use clean drop cloths and other means to protect the property and floor. Any and all damage to Government property, resulting directly or indirectly by the contractor's operations, shall be repaired or creopl.aced by the contractor at no additional cost to the Government and to the satisfaction of the CO 2-09 CONTRACTOR'S EMPLOYEES' PARKING: The contractor's employees shall park in the Visitor's Parking Lot, and shall not interfere with ongoing Government operations. The contractor's employees shall comply with all signs/traffic regulations indicating "No Parking", fire zones, etc., and shall not park in unauthorized areas.
2-10 CONTRACTOR'S EMPLOYEES' RESTRICTIONS: The contractor's employees shall be restricted to areas within this scope of work, plus direct routes to and from the site as may be approved in the Pre-Construction Conference regarding work scheduling and material handling.
2-11 STAGING AREA: The staging area will be identified by the COR. Upon completion of all work outlined in the contract drawings and specification, the contractor shall remove all materials and equipment from NAL. The contractor shall restore the staging area to its original and/or previous condition.
2-12 EQUIPMENT, TRAILERS, AND TEMPORARY OFFICES: The contractor shall ensure that large specialized equipment, temporary offices, and trailers used on the job are identified with both the name and telephone number of the owner and/or lessor. Job site locations must be coordinated with the COR.
2-13 AVAILABILITY AND USE OF UTILITY SERVICES: The contractor will be responsible for all temporary utilities, including electric, water, sewer, communications, etc., for their staging area and construction activities at its sole expense. The contractor should provide a separately metered power feed to provide electric service with the billing directly to the contractor. The contractor will be responsible for all temporary onsite distribution. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required. Before final acceptance of the last sequence of construction, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
The contractor shall not be permitted to use Government telephone service.
2-14 IDENTIFICATION OF UNDERGROUND UTILITIES: It shall be the contractor's responsibility to have all underground utilities marked before any excavation or crane activity begins. He must contact Miss Utility to locate the telephone and gas lines. A notification of72 hours in advance shall be given to the NAL Engineering Office (301-504-7941) to locate the drainage, steam, water, electric, and sewer lines. If the contractor fails to have these services performed, it will be the contractor's responsibility to make temporary repairs immediately, and
SPECIAL CONDITIONS FOR NATIONAL
AGRICULTURAL LIBRARY (NAL) 3
USDA/ARS/NAL
permanent repair within 24 hours, at no expense to the Government. Any repairs made to the underground utilities by the contractor shall be inspected by a Government representative before any backfilling.
2-15 INTERRUPTION OF UTILITIES/FACILITIES:
a. The contractor shall not interrupt NAL's existing utilities on the roof or in the ground without first obtaining prior written permission from the COR. A written request for a desired minor outage shall state the reason, date, and duration of the proposed outage, and be submitted a minimum of 2 working days prior to the proposed outage. Major outages that require more than normal preparation will be scheduled by the NAL Engineer, in coordination with the COR and may require up to 2 weeks prior written request from contractor, for written approval from COR.
b. The contractor shall make all temporary and final connections to existing utility services, furnish all material, perform all excavation, backfilling, mechanical tamping, and all other labor incidental to making the connections.
2-16 SUPERVISION OF WORK: The superintendent/foreman must be able to read, write, speak, and fully understand the English language, and have full authority to act for the contractor.
2-17 PERSONNEL BEHAVIOR: Contractor personnel shall conduct themselves in a professional manner, with a minimum of noise and confusion. Boisterous or discriminatory conduct and profane language on the job site is strictly prohibited. Cooperation with building occupants shall be deemed essential to assure the progress of the Government's work.
Contractors shall wear proper attire at all times.
2-18 WORK OUTSIDE REGULAR HOURS: If the contractor desires to conduct work outside normal duty hours or on Saturday, Sunday, or Federal legal holidays, an application must be submitted at least 2 working days in advance to the CO. This shall allow ample time for satisfactory arrangements to be made for inspecting the work progress. Costs incurred by the contractor for overtime and Government inspection requested for his own convenience shall be borne by the contractor. It is the purpose of this section to prevent excessive overtime and to completely prohibit overtime work which is not supervised and/or inspected by the Government's authorized personnel.
2-19 SEVERE WEATHER WARNING REQUIREMENTS: When a severe weather warning has been issued for the area in which construction is being performed, the contractor shall take immediate action to secure structures, materials, and equipment on the job site. This action will ensure protection from damage as a result of strong surface winds, thunderstorms, or other weather-related conditions. These requirements are applicable 24 hours a day, 7 days a week.
SPECIAL CONDITIONS FOR NATIONAL
AGRICULTURAL LIBRARY (NAL) 4
USDA/ARS/NAL
2-20 ENVIRONMENTAL PROTECTION: The contractor shall provide and maintain environmental protection during the life of the contract as defined herein. Environmental protection shall be provided to correct conditions that might endanger the environment during construction operations.
a. DEFINITION OF CONTAMINANTS:
(1) (2)
SEDIMENT: Earth that has been eroded and transported by runoff water.
SOLID WASTE: Discarded solid materials resulting from construction activities.
(3) RUBBISH: A variety of combustible and noncombustible wastes such as paper, boxes, glass, crockery, metal and lumber scrap, tin cans, etc.
(4) DEBRIS: Combustible and noncombustible wastes such as asbestos, ashes, and waste materials resulting from demolition and construction work.
(5) SANITARYWASTES:
(a) SEWAGE: Waste which is considered domestic sewage.
(b) GARBAGE: Refuse and scraps resulting from preparation of food.
(6) RUBBLE: Fill materials generated from concrete, masonry, asphalt construction, and natural earth resulting from excavations.
(7) HAZARDOUSWASTE: A hazardous waste is any material or substance not excluded from regulation as a hazardous waste. Hazardous waste exhibits the characteristics of hazardous substances and could be a mixture of solid waste and hazardous waste. Any discarded commercial chemical product or chemical compound is to be considered hazardous waste in terms of handling and disposal procedures.
b. TEMPORARY CONSTRUCTION: Upon completion and acceptance of the construction, the contractor shall remove all signs of temporary construction facilities such as work areas, structures, foundations of temporary structures, stockpiles of excess or waste materials, temporary sedimentation and erosion control devices, and any other traces of construction.
AGRICULTURAL LIBRARY (NAL) 5
c. EROSION AND SEDIMENT CONTROL MEASURES:
USDA/ARS/NAL
(1) BURN-OFF: Bum-off of ground cover will not be permitted.
(2) Sediment control shall conform to the State of Maryland sediment control rules and regulations.
(3) STORMWATER POLLUTION PREVENTION: The contractor shall take all steps necessary to prevent pollutants from coming in contact with stormwater discharge. The most significant high risk areas for stormwater contamination must be identified by the USDA and the contractor prior to commencing work. Preventive measures and best management practices (BMPs) shall be developed and implemented in potential risk areas.
d. CONTROL AND DISPOSAL OF SOLID, CHEMICAL, AND SANITARY WASTES: Wastes shall be placed in closed metal containers which are emptied on a regular schedule. Handling and disposal shall be conducted in a manner to prevent contamination of the site and other areas.
DISPOSAL OF RUBBISH AND DEBRIS: Materials defined in paragraph a.(3) and a.(4) above shall be disposed of OFF USDA/BARC PROPERTY.(1)
(a) In the event the contractor or subcontractor should dump rubbish/debris at any area of USDA, the contractor shall be required to retrieve this rubbish/debris and dispose of OFF USDA PROPERTY at a certified landfill.
(b) The contractor shall provide proof of an approved, certified landfill prior to the removal of lead contaminated materials and asbestos material. All dump tickets from the approved landfill shall be provided to the COR.
(2) GARBAGE: The contractor shall dispose of all garbage OFF USDA PROPERTY. Garbage shall be kept in sealed metal containers and disposed of daily. The preparation, cooking, or disposal of food on the project site is strictly prohibited.
(3) SEWAGE , ODOR, AND PEST CONTROL: Chemical toilets or comparably effective units shall be utilized in accordance with Federal, State, and Local regulations. Wastes shall be periodically collected and removed from NAL by a licensed sewage disposal contractor. Measures shall be taken to control pests and to mask or eliminate undesirable odors. Chemical toilets shall be cleaned/serviced by a licensed company at least every 2 weeks.
SPECIAL CONDITIONS FOR NATIONAL
AGRICULTURAL LIBRARY (NAL) 6
USDNARS/NAL
(4)
DISPOSAL OF HAZARDOUS WASTE: Materials defined in paragraph 2-20 a.(7) shall be disposed of utilizing the following guidelines:
Hazardous waste must be disposed of at an EPA approved Treatment, Storage, and Disposal Facility (TSDF) in accordance with applicable Federal, State, and Local regulations.a.
b. Prior to transporting waste off-site, the contractor must:
[1] Submit a Waste Profile Sheet to the Beltsville Area (BA), SOHES, Environmental Unit (EU) for review and signature.
Note: The EU will enter the applicable EPA ID number on the Waste Profile Sheet which will be returned to the contractor.
[2] If applicable, provide a copy of the TCLP results from analysis performed to identify the waste as hazardous (e.g., lead concentrations above 0.5 mg/!).
[3] Notify the EU's Compliance Officer at 301-504-5557 twenty-four hours before hazardous waste is to be removed from the site to ensure someone will be available to check the shipment and sign the appropriate paperwork.
c. To transport the waste off-site, the contractor must:
[1] Provide a completed Hazardous Waste Manifest and its supporting documentation to the EU's Inspector during the loading of the transportation vehicle. If the shipment is approved, the EU's Inspector will sign the Manifest and supporting documents. All waste will be transported in accordance with Federal, State, and Local Department of Transportation regulations.
[2] Provide appropriate copies of the Hazardous Waste Manifest and supporting documents to the EU's Inspector.
Note: If the shipment is not approved, the Manifest will not be signed and the material may not be removed from the site. All cost incurred due to an unapproved shipment will be the responsibility of the contractor.
AGRICULTURAL LIBRARY (NAL) 7
USDA/ARS/NAL
e. LEAD CONTAMINATED MATERIALS: A test for lead content/presence in the stack paint was performed by he USDA. Lead levels of0.023% were detected, a value that does not render the materials as hazardous. Results of this test are included in Section 230513.
Prior to initiating the demolition around the existing stack area, the Contractor shall perform a TCLP analysis of material surrounding the existing stack to determine whether special handling and disposal of the material is required.
If the test results indicate that the material is hazardous, the contractor will notify the COR of this condition so that the USDA can issue a contract modification for the proper handling and disposal of the hazardous material.
Debris containing lead contamination at 0.5 mg/I or higher, determined by either analysis prior to or after demolition/renovation, must be handled as Hazardous Waste in accordance with paragraph 2-20 d (4) above. Transportation of this material off-site must be accomplished by an approved DOT method. In most cases, lead contaminated debris will be placed in a sift-proof, roll-off container or trailer, covered by a secured tarp. As stated above, if shipment is not approved due to improper methodology or inadequate transportation vehicle, the Manifest will not be signed and the material may not be removed. Costs incurred for the delay in shipment will be the responsibility of the contractor.
f. NOISE: The maximum use of "low-noise emission products," as certified by the Environmental Protection Agency, shall be required when available. Blasting or the use of explosives will not be permitted.
g. CLEAN AIR/CLEAN WATER: The contractor shall not utilize equipment that has emissions which exceed limitations under the Clean Air Act and the facility's Title 5 Permit. Steps shall be taken to prevent the discharge of pollutants into or on any land or water.
2-21 PRELIMINARY AND FINAL INSPECTIONS: The contractor shall coordinate with the COR at least 14 calendar days in advance of project completion to allow scheduling of the preliminary and subsequent final inspections.
2-22 SITE RESTORATION: Restoration of any areas damaged by the contractor shall be accomplished immediately after the roof and stack replacement are completed. Final grading, including the placing of topsoil if required, shall be accomplished as specified in the contract or agreed to by the COR. Required landscaping, sodding, or seeding shall be accomplished at the earliest possible time after completion, as stipulated in the Technical Provisions of the contract.
AGRICULTURAL LIBRARY (NAL) 8
USDA/ARS/NAL
2-23 CUTTING, WELDING, BRAZING, AND HOT WORK OPERATIONS: When cutting, welding, soldering, or brazing operations are performed, the contractor shall fill out the NAL bum permit. The completed permit, signed by COR shall be furnished to the COR and posted at the job site. Cutting and welding equipment to be used shall be in satisfactory operating condition and in good repair. Fully charged and operable fire extinguishers, appropriate for the type of possible fire, shall be available at the work area. Fire watchers shall be familiar with the facilities and procedures for sounding an alarm in the event of a fire. All work shall be carried out in conformance with Section SIB, National Fire Protection Association. Failure to comply with the standard, or the practice of unsafe work procedures, will be cause for a temporary delay of work by the COR, Job Inspector, Safety Manager, or the NAL Project Representative.
2-24 TRUCK HAULING ON NAL: The contractor shall be responsible for covering open-bodied vehicles that are transporting sand, gravel, fill materials, dirt, construction debris and any other material which may become airborne and/or possibly create air pollution while on NAL.
2-25 SMOKING RESTRICTIONS: Smoking by contractor personnel shall be prohibited inside all areas of NAL. Smoking is permitted only in designated smoking areas outside the building.
2-26 WEEKENDS/AFTER HOURS/NOTIFICATION OF EMERGENCIES: The contractor shall supply names and telephone numbers of contractor personnel that could be contacted in the event of an emergency during non-work hours.
AGRICULTURAL LIBRARY (NAL) 9
image6.png image7.png image8.png image9.png image1.png image2.png image3.png image4.png image5.png