This document is a Supplemental Quality Assurance Provision (SQAP) issued by the Defense Logistics Agency (DLA) Energy for fuel and lubricant contracts. The SQAP contains multiple generalized technical guidance provisions and inspection/acceptance procedures applicable to bulk fuel, bulk fuel system icing inhibitor (FSII), bulk lube oil, and posts, camps, and stations programs.
Key provisions include: Geographic requirements mandating compliance with federal, state, and local environmental regulations at delivery locations; Certificate of Analysis (COA) requirements not older than 90 days from solicitation issue date, containing sample test date, test results, test methods, and laboratory signature; ASSIST database access instructions for locating defense specifications and qualified product lists; Direct Delivery Fuels Purchase Program requirements specifying that domestic locations accept "typicals" or specification sheets for aviation fuel, gasoline (including E85), diesel (including BDI/B20), and heating oil, while overseas locations and Marine Gas Oil (MGO) require Certificates of Analysis for all products. Product-specific SQAPs are included for Turbine Fuel, Aviation (JP-5) per MIL-DTL-5624X (February 2024) and Fuel, Naval Distillate (F-76) per MIL-DTL-16884R (January 2025), detailing specification modifications, additive requirements, test procedures, geographic-specific flash point requirements, traceability documentation, and batch sampling procedures with submission to Naval Air Station Patuxent River. Inspection and acceptance provisions establish Government rights to inspect and test supplies at any point prior to acceptance, limit sample requests to six one-gallon samples or two five-gallon samples annually per line item, require contractor-maintained inspection systems, and establish acceptance at destination for FOB destination items or at origin for FOB origin items. Additional provisions address point of inspection and acceptance, nonconforming supplies procedures requiring deviations or waivers with minimum $500 administrative fees, and inspection office assignments by geographic region (Americas East Code 110, Americas West Code 120, Europe and Africa Code 200, Pacific Code 300, Middle East Code 400).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment - E - Bunkers Notes.pdf | ||
| Attachment - C - Facilities Sheet.pdf | ||
| Attachment - A - Schedule.pdf | ||
| Mombasa Solicitation OSP and Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATKINS.RENRICK.L.10
24389320
Digitally signed by
ATKINS.RENRICK.L.1024389320
Date: 2025.03.11 15:58:35 -04'00'
ROSE.JAMAAL.R.10502
93366
Digitally signed by
ROSE.JAMAAL.R.1050293366
Date: 2025.03.11 14:30:04 -04'00'
BANISZEWSKI.DANIE
L.J.1287388698
Digitally signed by
BANISZEWSKI.DANIEL.J.1287388698
Date: 2025.03.13 08:11:54 -06'00'
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
Prescribed by: eSOP 4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
ENERGY QAP C16.01 02/06/2026
C16.01 TURBINE FUEL, AVIATION (JP5) (DLA ENERGY FEB 2026)
National Stock Number: Product Nomenclature: DLA Energy Product Code:
9130-00-273-2379 Turbine Fuel, Aviation, JP-5 JP5
9130-01-499-9521 Turbine Fuel, Aviation, JP-5 (Bunker JP5 fuel overseas locations only)
(a) Product shall meet MIL-DTL-5624X, Turbine Fuel, Aviation, Grade JP-5 (NATO F-44), dated February 12, 2024.
(b) SPECIFICATION MODIFICATION: The requirements of Table I in the specification are modified as follows:
(1) PROPERTIES:
(i) Conformance to specification requirements at the custody transfer point is required, however, prior to shipment, a laboratory hand blend of JP-5 fuel with all additives required by this contract shall be tested to verify compliance with the required specification (except for Micro- Separometer (MSEP)). MSEP analysis shall be performed per the Contractor's election in MIL-DTL-5624X, dated February 12, 2024.
(2) SYNTHETIC BLEND COMPONENT (SBC) and CO-HYDROPROCESSED SYNTHESIZED KEROSENE:
(i) If a fuel containing an SBC or a co-hydroprocessed synthesized kerosene is being offered, notification shall be made to the contracting point of contact with submission of relevant details regarding the blend percentage and which Annex of ASTM D7566 for the SBC used, and which feedstocks and co-processing percentage for co-hydroprocessed synthesized kerosene. Only SBCs approved in ASTM D7566, MIL-DTL-83133L, MIL-DTL-5624X, and co-hydroprocessed synthesized kerosene produced from approved feedstock and percentage in ASTM D1655, MIL-DTL-83133L, and MIL-DTL-5624X shall be acceptable to the government
(3) TEST MODIFICATIONS:
(i) Filtration Testing: Round upwards when reporting the filtration time, in minutes. For example, a filtration time of 4 minutes, 22 seconds, would be reported as 5 minutes.
(ii) Flash Point Testing: The referee procedure for performing flash point testing of JP-5 shall be the manual method of the latest revision of ASTM D93, as opposed to the automated version of ASTM D93.
(iii) Micro-Separometer Testing:
(A) Prior to initial production under this contract, the Contractor shall elect, on a one-time basis, which MSEP limit to meet for the balance of the contract. If the Contractor introduces Fuel System Icing Inhibitor (FSII) and/or Corrosion Inhibitor/Lubricity Improver (CI/LI) after verification of product conformance with the MSEP requirement, the product is not required to meet a fixed limit on subsequent MSEP tests. This process will be repeated if the composition of the fuel changes due to changes in processing or blending operations.
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
DISTRIBUTION
STATEMENT - A
APPROVED FOR
PUBLIC RELEASE
DISTRIBUTION IS
"UNLIMITED"
PREPARED BY DATE
2/10/2026
ITEM
C16.01 TURBINE FUEL, AVIATION (JP5)
REVIEWED BY DATE
02/10/2026
NSN
MULTIPLE
CODE ID NO.
52838
APPROVED BY DATE
02/10/2026
SIZE
A
SCALE
1:1
DRAWING NUMBER
MACLANE.SKYLLAR.BRYA
NNA.1252141827
Digitally signed by
MACLANE.SKYLLAR.BRYANNA.1252141827
Date: 2026.02.10 06:37:51 -05'00'
NICHOLS.MATTHEW.STEP
HEN.1267972229
Digitally signed by
NICHOLS.MATTHEW.STEPHEN.1267972229
Date: 2026.02.10 06:41:24 -05'00'
BANISZEWSKI.DANIEL.J.12
87388698
Digitally signed by
Date: 2026.02.10 08:57:50 -07'00'
4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
(4) LOCATION:
(i) All batches of JP-5 that are presented for Government acceptance at origin and for subsequent shipment through a multiproduct pipeline, shall meet a minimum flash point requirement of 62.5°C. This requirement is meant to address multiproduct commercial pipelines and does not apply to multiproduct systems within a facility.
(ii) In the U.S. all JP-5 deliveries in California, Oregon, Washington, and Alaska shall have a minimum Flash Point of 62.5oC at the custody transfer point.
(iii) All JP-5 procured for delivery to Australia shall have a minimum Flash Point of 61.5°C at the origin custody transfer point.
(iv) For JP-5 delivered to Kodiak Island, Alaska, the maximum total acid number shall be 0.020 mg KOH/g.
(v) For the deep freeze program, for Antarctic operations of the Department of Defense and other federal agencies; whereby JP-5 sulfur content shall not exceed 0.0015 mass-percent (15 ppm).
(c) ADDITIVES: Additives are required for deliveries of JP-5, per MIL-DTL-5624X, dated February 12, 2024, unless addition is excluded by specific solicitation line item, applicable contract clause, or another contractual requirement.
(1) FSII included in jet fuel shall conform to MIL-DTL- 85470C, Inhibitor, Icing, Fuel System, High Flash, dated March 5, 2024. The CI/LI additive(s) used shall conform to MIL-PRF-25017H Inhibitor, Corrosion/Lubricity Improver, Fuel Soluble, w/Amendment 1, dated August 4, 2011, and revalidated May 25, 2021.
(2) Line injection of additives (FSII and CI/LI) from shipping tank to delivery conveyance or other free on board (FOB) point is permitted under the following conditions:
(i) Additives must be proportionately injected throughout the entire loading process to ensure the additive is homogeneously blended into the jet fuel. The Contractor shall maintain records evidencing the homogeneous blending of all line injected additives. Such methods may include meter or tank gauge readings or test results taken at intervals to provide confidence in the injection process.
(ii) When FSII is required, additive concentration must be verified based on a representative sample from each shipping conveyance.
(d) OTHER REQUIRMENTS:
(1) ADDITIONAL SAMPLING: The government may request a sample of JP5 during each quarter of contract performance not to exceed 5 gallons. Samples shall be shipped in a 5-gallon epoxy lined can (preferred) or five 1-gallon epoxy lined cans. (NOTE: These samples are in addition to those required in accordance with Quality Assurance Provision (QAP) E1). The sample shall be shipped to
Naval Air Station HAZMART 5-Gallon TEST SAMPLE 22680 Hammond Road Bldg. 2385 Patuxent River, MD 20670 Attn: Terrence Dickerson, AB44100 Fuels & Lubricants Phone: (301) 757-0447; Email: terrence.w.dickerson.civ@us.navy.mil
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DISTRIBUTION STATEMENT - A
APPROVED FOR PUBLIC RELEASE
DISTRIBUTION IS "UNLIMITED"
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
SIZE
A
SCALE
1:1
CODE ID NO.
52838
DRAWING NUMBER
4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
The paperwork provided with these samples shall include the following information:
Contract Number Contractor's Name Product Refinery Location Quantity of Tank/Batch Full-Specification Test Report
(2) BATCH SAMPLING: The Contractor shall provide one 20 mL sample per each individual tank in a procurement batch upon completion.
The Sample shall be shipped within 30 days of the procurement batch delivery. A batch is defined as: A specific quantity of product that is processed or utilized as a single unit and tested to meet test criteria and specifications.
(i) For each 20 mL sample provided by the Contractor, the Contractor shall also submit a Refinery Certificate of Quality (RCQ), or
Certificate of Analysis (CoA), as applicable, with the JP-5 sample when submitting to the US Naval Air Station. The RCQ or CoA for each individual tank shall be representative of Level A testing for the JP-5 product.
NOTE: The above sample is in addition to those required in accordance with Quality Assurance Provision (QAP) E1
The sample from each tank/batch shall be either an all-level sample or a composite of upper, middle, and lower samples. A copy of the batch's full-specification test report shall accompany each sample. The sample container shall be any 20 mL amber borosilicate vial with a polytetrafluoroethylene (PTFE) lined screw cap. A tracking number for the samples shall be provided to: Terrence Dickerson at terrence.w.dickerson.civ@us.navy.mil or (301) 757-0447. Samples shall be shipped to:
20mL TEST SAMPLE 22680 Hammond Road Bldg. 2385 Patuxent River, MD 20670
Contractor's Name Product Refinery Location Quantity of Tank/Batch
For samples containing synthetic components, include the following additional information:
Manufacturer of synthetic component Batch Number Date of Test Report Quantity of Tank/Batch Percent Composition Production Process of Synthetic Component Feedstock Full-Specification Test Report
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DISTRIBUTION STATEMENT - A
APPROVED FOR PUBLIC RELEASE
DISTRIBUTION IS "UNLIMITED"
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
SIZE
A
SCALE
1:1
CODE ID NO.
52838
4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
S ENERGY QAP C16.23 July 2026 D. Baniszewski
C16.23 FUEL, NAVAL DISTILLATE (F-76) (DLA ENERGY JUL 2026)
National Stock Number: Product Nomenclature: DLA Energy Product Code:
9140-00-273-2377 Fuel, Naval Distillate F76
(a) Naval Distillate Fuel (F-76) shall conform to the requirements of Military specification MIL-DTL-16884R dated 03 Jan 2025. Nomenclature for Naval Distillate Fuel (F-76) is shown above.
(b) SPECIFICATION MODIFICATIONS:
(1) PROPERTIES: The F-76 supplied under this contract shall not contain un-hydrotreated light cycle oils or contain any stabilizer additives, or any other additive or material not explicitly allowed per section 3.2 of MIL-DTL-16884R.
(2) SYNTHETIC COMPONENTS: For F-76 containing a synthetic component, the synthetic component shall be certified to Tables A-I and A-II of MIL-DTL-16884R; for synthesized iso-paraffins, the synthetic component shall be certified to Tables B-I and B-II of MIL-DTL-16884R. It is not necessary to analyze each batch of the synthetic component for compliance with Table A-II (or Table B-II, as applicable) once it is demonstrated that the process scheme is adequately controlled and if no significant changes to existing production operations have been made, such as a turnaround event on a refinery unit used to produce the synthetic component or a change in feedstock material. The signed F-76 synthetic component certification page shall be supplied for each shipment which includes synthetic paraffinic materials, attesting that no changes to the production process have been made, and certifying that the last certificate of analysis, dated and including Table A-II (or Table B-II, as applicable) results, is still valid.
(3) TEST MODIFICATIONS:
(i) Flash Point: All batches of F-76 that are presented for Government acceptance at origin shall meet a minimum flash point requirement of 62.5 degrees Celsius (°C).
(ii) FAME: F-76 offered from a location other than where refined (excludes synthesized material as defined in section 3.2.2 and 3.2.3 of MIL- DTL-16884R) requires testing for FAME content by the latest revisions of test methods ASTM D7963, BS EN 14078, or IP 579. The latest revision of ASTM D7963 is considered to be the referee test method.
(4) LOCATION: In Australia, all deliveries of F-76 shall have a minimum Flash Point of 62.5°C at the custody transfer point.
(c) ADDITIVES:
(1) Lubricity Improver Additive (LIA) - Lubricity additives are allowed in F-76. The LIA additive(s) used shall conform to MIL-PRF- 32490A, Performance Specification, Additive, Lubricity Improver, Distillate Fuel, dated 24 May 2019 and found in ASSIST and shall be listed in the electronic Qualified Products List (QPL)-32490, located in the Qualified Products Database (QPD) found at https://assist.dla.mil/ (or http:// quicksearch.dla.mil) . Instructions on how to use ASSIST are located in QAP C1.02. Either Grade A, Grade B, or Grade C material is suitable for treatment of desulfurized F-76. Additive concentration shall not exceed the maximum allowable concentration applicable to the specific additive selected for inclusion in finished F-76.
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
DISTRIBUTION
STATEMENT - A
APPROVED FOR
PUBLIC RELEASE
DISTRIBUTION IS
"UNLIMITED"
PREPARED BY DATE
7/21/2026
ITEM
C16.23 Fuel, Naval Distillate (F-76)
REVIEWED BY DATE
07/21/2026
NSN
9140-00-273-2377
CODE ID NO.
52838
APPROVED BY DATE
07/21/2026
SIZE
A
SCALE
1:1
DRAWING NUMBER
6593540
MACLANE.SKYLLAR.BRYA
NNA.1252141827
Digitally signed by
MACLANE.SKYLLAR.BRYANNA.1252141827
Date: 2026.07.21 08:35:09 -04'00'
NICHOLS.MATTHEW.STEP
HEN.1267972229
Digitally signed by
NICHOLS.MATTHEW.STEPHEN.1267972229
Date: 2026.07.21 09:16:50 -04'00'
BANISZEWSKI.DANIEL.J.12
87388698
Digitally signed by
Date: 2026.07.21 10:05:32 -06'00'
4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
S ENERGY QAP C16.23 July 2026 D. Baniszewski
(i) For pipeline deliveries only. Most pipelines do not allow the addition of diesel lubricity additives to be shipped via their system; therefore, the following guidelines apply:
(ii) For F-76 shipped via pipeline that does not allow LIA, no LIA is to be added to the fuel. Lubricity shall not be a criterion for acceptance in this scenario. Lubricity improver will be injected into the fuel upon receipt.
(iii) Information pertaining to qualification of additives not currently listed on QPL-32490 may be obtained from Commander, Naval Sea Systems Command, ATTN: SEA 05S, 1333 Isaac Hull Avenue, SE, Stop 5160, Washington Navy Yard, DC 20376-5160, USA, or by e-mailing CommandStandards@navy.mil.
(d) DYES AND MARKERS: Red dye required in off-highway diesel fuel in accordance with 40 CFR Part 80 as modified by the Environmental Protection Agency's interim final rule published in the Federal Register dated July 14, 1994 shall not be added to F-76. The finished product shall show no visual evidence of red dye. This F-76 product is for military, off-highway use only and must be segregated at all times from any diesel fuel used on-highway. NOTE: Red dye does not apply to Atlantic/Europe/Mediterranean or Western Pacific Overseas Bulk purchase programs unless offering refinery is located in the United States or one of its possessions.
(e) OTHER REQUIREMENTS:
(1) Unless otherwise indicated by the Contractor in writing, prior to award, the product offered shall be required to fully meet all applicable specifications. The supplier shall provide to the receiving vessel a �Statutory Sample� of at least 400 mL in volume, taken from the receiving vessel's inlet bunker manifold, together with a Bunker Delivery Note (BDN). This sample will be sealed and carry a sample tag that provides the documentation required per MARPOL 73/78, Annex VI Regulation 18.
(2) ADDITIONAL SAMPLING: The government may request a sample of F-76 during each quarter of contract performance not to exceed 5 gallons. Samples shall be shipped in a 5-gallon epoxy lined can (preferred) or five 1-gallon epoxy lined cans. (NOTE: These samples are in addition to those required in accordance with Quality Assurance Provision (QAP) E1). The sample shall be shipped to:
5-gallon TEST SAMPLE 22680 Hammond Road Bldg. 2385 Patuxent River, MD 20670 Attn: Terrence Dickerson, AB44100 Fuels & Lubricants Phone: (301) 757-0447; Email: terrence.w.dickerson.civ@us.navy.mil
Contractor's Name Product Refinery Location Quantity of Tank/Batch Full-Specification Test Report
(3) BATCH SAMPLING: The Contractor shall provide one 20 mL sample per each individual tank in a procurement batch upon completion.
The Sample shall be shipped within 30 days of the procurement batch delivery. A batch is defined as: A specific quantity of product that is processed or utilized as a single unit and tested to meet test criteria and specifications.
(i) For each 20 mL sample provided by the Contractor, the Contractor shall also submit a Refinery Certificate of Quality (RCQ), or Certificate of Analysis (CoA), as applicable, with the F-76 sample when submitting to the US Naval Air Station. The RCQ or CoA for each individual tank shall be representative of Level A testing for the F-76 product.
NOTE: This sample is in addition to those required in accordance with Quality Assurance Provision (QAP) E1
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DISTRIBUTION STATEMENT - A
APPROVED FOR PUBLIC RELEASE
DISTRIBUTION IS "UNLIMITED"
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
SIZE
A
SCALE
1:1
CODE ID NO.
52838
6593540
4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
S ENERGY QAP C16.23 July 2026 D. Baniszewski
The sample from each tank/batch shall be either an all-level sample or a composite of upper, middle, and lower samples. A copy of the full-specification test report shall accompany each sample. The sample container will be any 20 mL amber borosilicate vial with a polytetrafluoroethylene (PTFE) lined screw cap. A tracking number for the samples shall be provided to: Terrence Dickerson at terrence.w.dickerson.civ@us.navy.mil or (301) 757-0447. Samples shall be shipped to:
20mL TEST SAMPLE 22680 Hammond Road Bldg. 2385 Patuxent River, MD 20670
Contractor's Name Product Refinery Location Quantity of Tank/Batch
For samples containing synthetic components, include the following additional information:
Manufacturer of synthetic components Batch Number Date of Test Report Quantity of Tank/Batch Percent Composition Production Process of Synthetic Component Feedstock Full-Specification Test Report
(4) TRACEABILITY:
(i) F-76 fuel supplied under this contract shall maintain traceability with respect to additives and materials, which is defined as the ability to trace the individual batch of fuel back to the original point of manufacture through documentation.
(ii) All traceability documentation shall be sufficient to guarantee that at no point any unauthorized materials or additives have been blended into the final product or any of its associated blend components per section 3.2 Material of MIL-DTL-16884R.
(iii) For all F-76 supplied, the traceability documentation shall consist of statement(s) attesting to the materials composition, which includes materials derived from non-petroleum sources, additives and their concentration levels. Additives and concentrations to be reported include LIAs outlined in section d.1 above and any trace additives resulting from existing tank heels, product trail-back in a multiproduct system, all product blending operations, etc.
(A) Attestation of Co-Processed Materials: The offeror shall explicitly disclose whether any portion of the F-76 product or any constituent blend component, has been produced by means of co-processing petroleum derived feedstocks with materials identified in section 3.2.4 of MIL-DTL-16884R, dated 03 Jan 2025. Failure to disclose the presence of co-processed materials shall constitute a non-conforming product.
(1) The offeror must identify the type and specific source (ex. palm oil, soybean oil, tallow, etc.) of the feed stock utilized.
(2) The maximum percentage of co-processed materials shall constitute a non-conforming product.
(iv) If F-76 is produced by means of blending, the traceability requirement and documentation for additives and materials shall apply to each blending component used from the point of manufacture through the blend operation. Materials composition, additives and their concentration levels shall be included. The requirement and intent of traceability for blend components is not to obtain full certificates of analysis of each individual blend component, but for certification that no unapproved additives or materials are present in blend components used.
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DISTRIBUTION STATEMENT - A
APPROVED FOR PUBLIC RELEASE
DISTRIBUTION IS "UNLIMITED"
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
SIZE
A
SCALE
1:1
CODE ID NO.
52838
4155.05-001 Sponsor: J3
REVISIONS
REV DESCRIPTION DATE APPROVED
S ENERGY QAP C16.23 July 2026 D. Baniszewski
(v) The form titled: �F-76 Traceability Signature Page� (attached below) shall be used to document conformance with the provisions of this traceability paragraph. The offeror/supplier shall comply with this requirement utilizing one of the three options below and notification shall be provided to both the contracting office and QT@dla.mil during the pre-award phase which option was chosen for compliance. Documents provided in conjunction with individual shipments shall be uploaded into Wide Area Work Flow as attachments under the quality tab.
(A) OPTION 1 - As part of the offeror submission package the offeror shall provide the traceability signature page from each entity in the supply chain providing and/or handling F-76 product and/or blending components all the way back to the point of manufacture. For each individual shipment, the supplier will submit a traceability page signed only by the awardee.
(B) OPTION 2 - As part of the offer submission package the offeror shall provide the traceability signature page, signed only by the offeror. Upon award and prior to the first shipment the awardee shall provide the signed traceability signature page from each entity in the supply chain providing and/or handling F-76 product and/or blending components all the way back to the point of manufacture. For each individual shipment, the supplier will submit a traceability page signed only by the awardee.
(C) OPTION 3 - As part of the offeror submission package, the offeror shall provide the traceability signature page, signed only by the offeror. For each individual shipment, the awardee shall provide the signed traceability signature page from each entity in the supply chain providing and/or handling F-76 product and/or blending components all the way back to the point of manufacture.
(vi) Regardless of the option chosen, the traceability sheet signed by offeror shall be submitted to both the contracting office and to QT@dla.mil during pre-award phase.
(vii) For OPTION 1 or OPTION 2, the purpose of the awardee submitting a signed traceability page with each shipment is to confirm that the initial traceability certification is still valid at the time of F-76 product shipment.
(A) If at any point during the contract period the traceability information provided under OPTION 1 or OPTION 2 becomes invalid (i.e. the supply chain is altered or the source of F-76 product or a blending component changes), the supplier shall notify both the contracting office and QT@dla.mil and updated documentation shall be provided.
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DISTRIBUTION STATEMENT - A
APPROVED FOR PUBLIC RELEASE
DISTRIBUTION IS "UNLIMITED"
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN RD
FORT BELVOIR, VIRGINIA 22060-6222
SIZE
A
SCALE
1:1
CODE ID NO.
52838
F-76 Traceability Signature Page
Contract or Solicitation Number:
CLIN:
Order Number:
Shipment Number:
Traceability OPTION selected per paragraph (4)(v) (circle or otherwise indicate which one of the three options is chosen):
OPTION 1 OPTION 2 OPTION 3.
F-76 fuel supplied under the above contract, CLIN, order number and shipment number maintains traceability with respect to the materials composition, additives and their concentration levels. This signed statement certifies that at no point have any unauthorized un- hydrotreated light cycle oils, other unauthorized materials, or additives been blended into the final product or any of its associated blend components per the most recent revision of MIL-DTL-16884 at date of contract award. All materials and additives are listed below. The percentage of each material as defined in sections 3.2, 3.2.2, and 3.2.3 (i.e. refined hydrocarbon distillate fuel, Fischer-Tropsch, Hydroprocessed Renewable Diesel, etc.) and the concentration level for each additive are also shown. For the purposes of the offeror submission this signed statement attests that no unapproved additives or materials will be added to batches or components of batches of F-76 for delivery under government contracts.
Signature:
Printed Name:
Title:
Company Name:
Date:
Additive Concentration Responsible Party for Injection
F-76 Synthetic Component Certification
Contract or Solicitation Number:
CLIN:
Order Number:
Shipment Number:
Synthetic paraffinic materials supplied as indicated with the above contract, CLIN, order number, and shipment number is derived from either Fischer-Tropsch (FT) or Hydroprocessed Renewable Diesel (HRD) methods. This signed statement certifies that since the last certificate of analysis (COA) no changes have been made requiring a resubmission; including table A-II or B-II in the respective appendixes of MIL-DTL-16884R, dated 03 Jan 2025. Table A-II or B-II is required for initial approval and when there are changes to feedstock material, production location, or production processes . In addition, no turnaround events have been executed on any units utilized to produce the synthetic paraffinic materials since the last COA, including table A-II or B-II, properties were tested. Please supply the date of the most recent COA and an identifying number for that report in the space provided below.
DATE OF COA: _ LAB REPORT ID NUMBER
Signature:
Printed Name:
Title:
Company Name:
Date:
PAGE 1 OF 3DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
REV DESCRIPTION DATE APPROVED
B Energy QAP E5.01 09/22/2026 M.MIZRAHI
REVISIONS
E5.01 INSPECTION AND ACCEPTANCE OF SUPPLIES (SHIPS' BUNKERS) (SEPTEMBER 2026)
(a) INSPECTION.
(1) The Contractor shall maintain a written inspection system acceptable to the Government covering all supplies under this contract and shall tender to the Government, for acceptance, only supplies that have been found by the Contractor to conform to the contract requirements. A copy of the written inspection system shall be in English. As part of that plan, the Contractor shall be able to provide, for review by the Government, laboratory test data from its suppliers verifying that the supplies being furnished meet the contract requirements. The Government has the right to perform reviews and evaluations, as reasonably necessary, to ascertain compliance with this paragraph. Such reviews and evaluations by the Government shall be conducted in a manner that does not unduly delay contract performance. The right of review, whether exercised or not, does not relieve the Contractor of its obligations under the contract.
(2) The Government has the right to inspect and/or test all supplies called for by the contract, to the extent practicable, at any time or place prior to acceptance. Unless otherwise noted, inspection will be performed by the receiving activity based on documents required to be supplied by the Contractor at the time of delivery. The Government assumes no contractual obligation to perform any inspection or test for the benefit of the Contractor, unless specifically set forth in this contract.
(3) The Government may require the Contractor to provide the following samples of fuel being supplied under this contract, free of cost to the Government, to a testing location to be identified at the time of the request. The samples may be requested by the Contracting Officer or the Quality Manager, as identified in the LIST OF INSPECTION OFFICES FOR DLA ENERGY CONTRACTS contract provision. The conditions under which the sample shall be taken (i.e., location, type) shall be included in the request and any testing performed shall be at the expense of the Government.
(i) A one (1) gallon sample under each line item. Requests for this type of sample shall be limited to no more than six (6) per year (per line item) during the life of the contract. However, if the Government deems that there is an issue with product quality under a specific line item, the Government reserves the right to increase the total number of samples to a maximum of twelve (12) per year for that line item.
(ii) A five (5) gallon sample under each line item. These samples are collected for the purpose of gathering data on world-wide bunker quality. Requests of this type shall be limited to no more than two (2) (per line item) per contract period. These samples shall be shipped to the following address:
ATTN: AB44100 FUELS AND LUBRICANTS
NAVAL AIR STATION PATUXENT RIVER
HAZMART BUILDING 2385
22680 HAMMOND ROAD
PATUXENT RIVER, MD 20670-1534
(4) If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties.
(5) The Government may perform quality validation on samples taken at the point of acceptance (i.e., ship's manifold). In cases where on-site testing is available, acceptance shall not be conclusive until the results of the on-site tests confirm that the product conforms to the contract requirements. One representative sample, typically three (3) gallons, will be taken and split into three (3) sealed one (1) gallon samples. One sample shall be offered to the Contractor's representative. One sample shall be submitted by the Contractor's representative, at no cost to the Government, to a Government approved laboratory for analysis. The remaining sample shall be retained by the Contractor's representative for a minimum of ninety (90) days.
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DISTRIBUTION
STATEMENT - A
APPROVED FOR
PUBLIC RELEASE
DISTRIBUTION IS
"UNLIMITED"
DATE
09/22/2026
APPROVED BY
DATE
09/22/2026
DATE
09/22/2026
PREPARED BY
DRAWING NUMBER
6756126
SCALE
1:1
CAGE
52838
SIZE
A
NSN
MULTIPLE
ITEM
E5.01 INSPECTION AND ACCEPTANCE OF SUPPLIES (SHIP
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN ROAD
FORT BELVOIR, VIRGINIA 22060-6222
REVIEWED BY
MIZRAHI.MARK.13621
09295
Digitally signed by
MIZRAHI.MARK.1362109295
Date: 2026.09.22 12:54:54 -04'00'
JAINDL.JASON.ANDRE
W.1271153461
Digitally signed by
JAINDL.JASON.ANDREW.1271153461
Date: 2026.09.22 12:06:10 -04'00'
NICHOLS.MATTHEW.S
TEPHEN.1267972229
Digitally signed by
NICHOLS.MATTHEW.STEPHEN.1267972229
Date: 2026.09.22 12:25:04 -04'00'
PAGE 2 OF 3DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
REV DESCRIPTION DATE APPROVED
B Energy QAP E5.01 09/22/2026 M.MIZRAHI
REVISIONS
Except as otherwise provided in the contract, the Government shall bear the expense of Government inspections or tests made at other than the Contractor's or subcontractor's facilities. In the event the test results on the sample taken at the acceptance point do not conform to contract specifications, the Government may exercise its rights and direct the Contractor to immediately remove the product at the Contractor's expense.
Detainment of the Government vessel for the removal of nonconforming product will be at the Contractor's expense.
(6) When supplies are not ready for inspection or test at the time specified by the Contractor, the Contracting Officer may charge the Contractor for any additional cost incurred by the Government related to that inspection or test. The Contracting Officer may also charge the Contractor for any additional cost incurred by the Government when prior rejection makes reinspection or retest necessary.
(7) If this contract provides for the performance of Government quality assurance at source, and if requested by the Government, the
Contractor shall furnish advance notification of the time when Contractor inspections or tests will be performed in accordance with the terms and conditions of the contract and when the supplies will be ready for Government inspection. The Government's request shall specify the period and method of the advance notification and the Government representative to whom it shall be furnished.
(8) The contractor may provide, at no additional cost to the Government, transportation to/from/between contractor facilities and operations to a DLA Energy representative performing official duties relating to the administration of the contract..
(9) A copy of the latest full specification analysis for the shipping tank shall be provided to the customer at the time of each delivery. If the latest shipping tank analysis is not available, the full specification certificate of quality for the most recent product delivered into that shipping tank shall be provided. Additionally, when product is supplied by barge, the following analysis results shall be provided on a barge composite sample:
Appearance, Color, Density, and Flash Point.
(b) ACCEPTANCE.
(1) Acceptance of the supplies furnished hereunder will take place at destination notwithstanding that inspection by the Government may take place elsewhere prior to acceptance.
DISTRIBUTION STATEMENT - A
APPROVED FOR PUBLIC RELEASE
DISTRIBUTION IS "UNLIMITED"
SUPPLEMENTAL QUALITY ASSURANCE PROVISION
(SQAP)
DRAWING NUMBER
6756126
SCALE
1:1
CAGE
52838
SIZE
A
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN ROAD
FORT BELVOIR, VIRGINIA 22060-6222
PAGE 3 OF 3DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
INSTRUCTIONS
a. Developing a QAP/SQAP unique to an individual National Stock Number (NSN) or a Local Stock Number (LSN):
(1) Develop the SQAP using DLA Form 1889, downloaded from the Official DLA Forms website:
https://www.dla.mil/Working-With-DLA/Forms/DLFormList/. For the initial release of a QAP/SQAP, leave the REVISIONS block blank. When revising QAP/SQAP, update the REVISIONS block as appropriate.
(2) Enter the title of the SQAP in the DESCRIPTION block. This title should be the clear reason the SQAP was created. For DLA Energy, the applicable document number should be included in this block, as DLA Energy QAPs are numbered per contract clauses, materials, and geographic regions. (See the appropriate procurement guidance prescription list.)
(3) QA Requirements should be typed in the area below the Revisions block.
(a) If more information is needed or images are required, add a continuation page and add text or image(s) below the revision block.
(b) If files need to be attached, use the Attachment button to select and attach necessary files.
(4) Select the MSC responsible for the NSN or LSN by selecting the respective name in the address block. This will auto populate Commercial and Government Entity Code (CAGE).
(5) Enter “Multiple NSNs or LSNs” in the ITEM block.
(6) Enter “Multiple NSNs or LSNs” in the NSN block.
(7) SIZE and SCALE blocks are automatically populated; do not change.
(8) For non-Energy MSCs, enter the document number of the QAP in the DRAWING NUMBER block. The entire document number MUST NOT EXCEED 21 characters (due to system constraints) and will include the acronym QAP or SQAP. Examples of multi-use QAP/SQAPs include QAP-020, QAP-E09, and SQAP-SER1.
(9) Specialists electronically sign and date the “Prepared By” block ONLY.
(10) DLA Weapons Support and DLA Troop Support, Team Leaders or First Line Supervisors electronically sign and date the “Reviewed by” and “Approved By” blocks. NOTE: DLA Troop Support Construction & Equipment (C&E) PS will forward the SQAP to another PS for review and signature.
DLA Energy personnel will follow guidance provided in the DLA Energy Procurement Instruction (DEPI).
(11) Initiate a new form for those revisions when or if content changes happen by following the instructions directly above.
(a) The REV block should be updated alphabetically, beginning with “A.”
(b) Select DATE from the dropdown calendar.
(c) APPROVED block should be the First Initial and Last Name of the individual making the changes to the SQAP.
b. Developing a QAP/SQAP for multiple NSNs or LSNs:
(1) Develop the SQAP using DLA Form 1889, downloaded from the Official DLA Forms website:
https://www.dla.mil/Working-With-DLA/Forms/DLFormList/. For the initial release of a QAP/SQAP, leave the REVISIONS block blank. When revising QAP/SQAP, update the REVISIONS block as appropriate.
(2) Enter the title of the SQAP in the DESCRIPTION block. This title should be the clear reason the SQAP was created. For DLA Energy, the applicable document number should be included in this block, as DLA Energy QAPs are numbered per contract clauses, materials, and geographic regions. (See the appropriate procurement guidance prescription list.)
(3) QA Requirements should be typed in the area below the Revisions block.
(a) If more information is needed or images are required, add a continuation page and add text or image(s) below the revision block.
(b) If files need to be attached, use the Attachments button to select and attach necessary files.
(4) Select the MSC responsible for the NSN or LSN by selecting the respective name in the address block. This will auto populate Commercial and Government Entity Code (CAGE).
(5) Enter “Multiple NSNs or LSNs” in the ITEM block.
(6) Enter “Multiple NSNs or LSNs” in the NSN block.
(7) SIZE and SCALE blocks are automatically populated; do not change.
(8) For non-Energy MSCs, enter the document number of the QAP in the DRAWING NUMBER block. The entire document number MUST NOT EXCEED 21 characters (due to system constraints) and will include the acronym QAP or SQAP. Examples of multi-use QAP/SQAPs include QAP-020, QAP-E09, and SQAP-SER1.
(9) Specialists electronically sign and date the “Prepared By” block ONLY.
(10) DLA Weapons Support and DLA Troop Support, Team Leaders or First Line Supervisors electronically sign and date the “Reviewed by” and “Approved By” blocks. NOTE: DLA Troop Support Construction & Equipment (C&E) PS will forward the SQAP to another PS for review and signature.
DLA Energy personnel will follow guidance provided in the DLA Energy Procurement Instruction (DEPI).
(11) Initiate a new form for those revisions when or if content changes happen by following the instructions directly above.
(a) The REV block should be updated alphabetically, beginning with “A.”
(b) Select DATE from the dropdown calendar.
(c) APPROVED block should be the First Initial and Last Name of the individual making the changes to the SQAP.
PAGE 1 OF 2DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
REV DESCRIPTION DATE APPROVED
A Energy QAP E12 08/28/2026 M.MIZRAHI
REVISIONS
ENERGY QAP E12 (AUG 2026) POINT OF ACCEPTANCE
(a) For Free on Board (FOB) origin contract items, acceptance of the supplies furnished hereunder shall take place at origin.
(b) For FOB destination contract items, acceptance of the supplies furnished here under shall take place at destination.
(c) Acceptance shall take place as stated above, unless specifically stated otherwise in the contract.
DISTRIBUTION
STATEMENT - A
APPROVED FOR
PUBLIC RELEASE
DISTRIBUTION IS
"UNLIMITED"
DATE
09/01/2026
APPROVED BY
DATE
08/28/2026
DATE
08/28/2026
PREPARED BY
DRAWING NUMBER
6808238
SCALE
1:1
CAGE
52838
SIZE
A
NSN
MULTIPLE
ITEM
E12 POINT OF ACCEPTANCE
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN ROAD
FORT BELVOIR, VIRGINIA 22060-6222
REVIEWED BY
MIZRAHI.MARK.13621
09295
Digitally signed by
MIZRAHI.MARK.1362109295
Date: 2026.09.01 10:09:37 -04'00'
ALONZO.JASON.12716
78823
Digitally signed by
ALONZO.JASON.1271678823
Date: 2026.08.28 12:24:48 -04'00'
NICHOLS.MATTHEW.S
TEPHEN.1267972229
Digitally signed by
Date: 2026.08.28 12:34:09 -04'00'
PAGE 2 OF 2DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
INSTRUCTIONS
a. Developing a QAP/SQAP unique to an individual National Stock Number (NSN) or a Local Stock Number (LSN):
(1) Develop the SQAP using DLA Form 1889, downloaded from the Official DLA Forms website:
https://www.dla.mil/Working-With-DLA/Forms/DLFormList/. For the initial release of a QAP/SQAP, leave the REVISIONS block blank. When revising QAP/SQAP, update the REVISIONS block as appropriate.
(2) Enter the title of the SQAP in the DESCRIPTION block. This title should be the clear reason the SQAP was created. For DLA Energy, the applicable document number should be included in this block, as DLA Energy QAPs are numbered per contract clauses, materials, and geographic regions. (See the appropriate procurement guidance prescription list.)
(3) QA Requirements should be typed in the area below the Revisions block.
(a) If more information is needed or images are required, add a continuation page and add text or image(s) below the revision block.
(b) If files need to be attached, use the Attachment button to select and attach necessary files.
(4) Select the MSC responsible for the NSN or LSN by selecting the respective name in the address block. This will auto populate Commercial and Government Entity Code (CAGE).
(5) Enter “Multiple NSNs or LSNs” in the ITEM block.
(6) Enter “Multiple NSNs or LSNs” in the NSN block.
(7) SIZE and SCALE blocks are automatically populated; do not change.
(8) For non-Energy MSCs, enter the document number of the QAP in the DRAWING NUMBER block. The entire document number MUST NOT EXCEED 21 characters (due to system constraints) and will include the acronym QAP or SQAP. Examples of multi-use QAP/SQAPs include QAP-020, QAP-E09, and SQAP-SER1.
(9) Specialists electronically sign and date the “Prepared By” block ONLY.
(10) DLA Weapons Support and DLA Troop Support, Team Leaders or First Line Supervisors electronically sign and date the “Reviewed by” and “Approved By” blocks. NOTE: DLA Troop Support Construction & Equipment (C&E) PS will forward the SQAP to another PS for review and signature.
DLA Energy personnel will follow guidance provided in the DLA Energy Procurement Instruction (DEPI).
(11) Initiate a new form for those revisions when or if content changes happen by following the instructions directly above.
(a) The REV block should be updated alphabetically, beginning with “A.”
(b) Select DATE from the dropdown calendar.
(c) APPROVED block should be the First Initial and Last Name of the individual making the changes to the SQAP.
b. Developing a QAP/SQAP for multiple NSNs or LSNs:
(1) Develop the SQAP using DLA Form 1889, downloaded from the Official DLA Forms website:
https://www.dla.mil/Working-With-DLA/Forms/DLFormList/. For the initial release of a QAP/SQAP, leave the REVISIONS block blank. When revising QAP/SQAP, update the REVISIONS block as appropriate.
(2) Enter the title of the SQAP in the DESCRIPTION block. This title should be the clear reason the SQAP was created. For DLA Energy, the applicable document number should be included in this block, as DLA Energy QAPs are numbered per contract clauses, materials, and geographic regions. (See the appropriate procurement guidance prescription list.)
(3) QA Requirements should be typed in the area below the Revisions block.
(a) If more information is needed or images are required, add a continuation page and add text or image(s) below the revision block.
(b) If files need to be attached, use the Attachments button to select and attach necessary files.
(4) Select the MSC responsible for the NSN or LSN by selecting the respective name in the address block. This will auto populate Commercial and Government Entity Code (CAGE).
(5) Enter “Multiple NSNs or LSNs” in the ITEM block.
(6) Enter “Multiple NSNs or LSNs” in the NSN block.
(7) SIZE and SCALE blocks are automatically populated; do not change.
(8) For non-Energy MSCs, enter the document number of the QAP in the DRAWING NUMBER block. The entire document number MUST NOT EXCEED 21 characters (due to system constraints) and will include the acronym QAP or SQAP. Examples of multi-use QAP/SQAPs include QAP-020, QAP-E09, and SQAP-SER1.
(9) Specialists electronically sign and date the “Prepared By” block ONLY.
(10) DLA Weapons Support and DLA Troop Support, Team Leaders or First Line Supervisors electronically sign and date the “Reviewed by” and “Approved By” blocks. NOTE: DLA Troop Support Construction & Equipment (C&E) PS will forward the SQAP to another PS for review and signature.
DLA Energy personnel will follow guidance provided in the DLA Energy Procurement Instruction (DEPI).
(11) Initiate a new form for those revisions when or if content changes happen by following the instructions directly above.
(a) The REV block should be updated alphabetically, beginning with “A.”
(c) APPROVED block should be the First Initial and Last Name of the individual making the changes to the SQAP.
PAGE 1 OF 2DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
REV DESCRIPTION DATE APPROVED
B ENERGY QAP E21.01 08/28/2026 M. MIZRAHI
REVISIONS
ENERGY QAP E21.01 (AUG 2026) POINT OF INSPECTION
(a) This Energy Quality Assurance Provision (QAP) applies to the Bulk Fuel, Bulk FSII, Bulk Lube Oil and Posts, Camps, and Stations Programs.
(b) When government inspection is deemed necessary, it shall be performed, prior to acceptance, by the office specified in the Energy QAP E22, List of Inspection Offices for DLA Energy Contracts or the Energy QAP E22.01, Quality Representative Energy QAP provision of this contract, whichever is applicable.
(1) For Free on Board (FOB) origin contract items, inspection will normally be performed at origin, however, the Government reserves the right to perform an inspection at any point prior to acceptance.
(2) For FOB destination contract items, inspection will normally be performed at destination, however, the Government reserves the right to perform an inspection at any point prior to acceptance.
(3) For FOB destination contract items for aviation fuels delivered via waterborne transport, pipeline, rail car, tank truck, tank wagon and Bulk Fuel Container (BFC) and non-aviation fuels delivered by waterborne transport, a preliminary inspection for product quality will normally be performed at origin, with final inspection normally being at destination. However, the Government reserves the right to perform an inspection at any point prior to acceptance.
(4) On contract items for delivery of drummed or packaged products, FOB origin or FOB destination, a preliminary inspection for product quality will normally be performed at the point of manufacturing or blending, with final inspection normally being at the FOB point. However, the Government reserves the right to perform an inspection at any point prior to acceptance.
(c) When the Contractor is informed by the responsible Inspection Office that government inspection is deemed necessary, the Contractor shall ensure that the Inspection Office is provided with sufficient information and advance notification to facilitate such inspection. When government inspection is necessary at a contractor or subcontractor (commercial or government) facility, the Contractor shall notify the Inspection Office of the necessary requirements to access those facilities and shall help facilitate such access. After initial notification, the Contractor shall keep the Inspection Office informed of any changes that may affect that inspection.
DISTRIBUTION
STATEMENT - A
APPROVED FOR
PUBLIC RELEASE
DISTRIBUTION IS
"UNLIMITED"
DATE
09/01/2026
APPROVED BY
DATE
08/28/2026
DATE
08/28/2026
PREPARED BY
DRAWING NUMBER
6664414
SCALE
1:1
CAGE
52838
SIZE
A
NSN
MULTIPLE
ITEM
E21.01 POINT OF ACCEPTANCE
DEFENSE LOGISTICS AGENCY, ENERGY
8725 JOHN J. KINGMAN ROAD
FORT BELVOIR, VIRGINIA 22060-6222
REVIEWED BY
MIZRAHI.MARK.13621
09295
Digitally signed by
MIZRAHI.MARK.1362109295
Date: 2026.09.01 10:13:16 -04'00'
ALONZO.JASON.12716
78823
Digitally signed by
ALONZO.JASON.1271678823
Date: 2026.08.28 12:27:23 -04'00'
NICHOLS.MATTHEW.S
TEPHEN.1267972229
Digitally signed by
Date: 2026.08.28 12:34:52 -04'00'
PAGE 2 OF 2DLA FORM 1889, AUG 2026
4155.05-001 Sponsor: J3
SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)
PREVIOUS EDITION IS OBSOLETE Add Page Delete Page Attachments
INSTRUCTIONS
a. Developing a QAP/SQAP unique to an individual National Stock Number (NSN) or a Local Stock Number (LSN):
(1) Develop the SQAP using DLA Form 1889, downloaded from the Official DLA Forms website:
https://www.dla.mil/Working-With-DLA/Forms/DLFormList/. For the initial release of a QAP/SQAP, leave the REVISIONS block blank. When revising QAP/SQAP, update the REVISIONS block as appropriate.
(2) Enter the title of the SQAP in the DESCRIPTION block. This title should be the clear reason the SQAP was created. For DLA Energy, the applicable document number should be included in this block, as DLA Energy QAPs are numbered per contract clauses, materials, and geographic regions. (See the appropriate procurement guidance prescription list.)
(3) QA Requirements should be typed in the area below the Revisions block.
(a) If more information is needed or images are required, add a continuation page and add text or image(s) below the revision block.
(b) If files need to be attached, use the Attachment button to select and attach necessary files.
(4) Select the MSC responsible for the NSN or LSN by selecting the respective name in the address block. This will auto populate Commercial and Government Entity Code (CAGE).
(5) Enter “Multiple NSNs or LSNs” in the ITEM block.
(6) Enter “Multiple NSNs or LSNs” in the NSN block.
(7) SIZE and SCALE blocks are automatically populated; do not change.
(8) For non-Energy MSCs, enter the document number of the QAP in the DRAWING NUMBER block. The entire document number MUST NOT EXCEED 21 characters (due to system constraints) and will include the acronym QAP or SQAP. Examples of multi-use QAP/SQAPs include QAP-020, QAP-E09, and SQAP-SER1.
(9) Specialists electronically sign and date the “Prepared By” block ONLY.
(10) DLA Weapons Support and DLA Troop Support, Team Leaders or First Line Supervisors electronically sign and date the “Reviewed by” and “Approved By” blocks. NOTE: DLA Troop Support Construction & Equipment (C&E) PS will forward the SQAP to another PS for review and signature.
DLA Energy…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .