AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO.

See Block 14

4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

6. ISSUED BY CODE SPE600 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE FACILITY CODE

SPE60014R0417

X

2014 AUG 25

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

12. ACCOUNTING AND APPROPRIATION DATA (If required)

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A NAME AND TITLE OF SIGNER (Type or print)

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

(a) By completing Items 8 and 15, and returning

DLA ENERGY

8725 JOHN J KINGMAN RD STE 4950

FT BELVOIR VA 22060-6222

USA

15C. DATE SIGNED 16C. DATE SIGNED

D. OTHER (Specify type of modification and authority)

SEE BLOCK 9B

3. EFFECTIVE DATE

See Attached Continuation Sheet(s).

(X)

CHECK ONE

PAGE OF PAGES

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CONTINUED ON NEXT PAGE

1. The schedule page for line item 0028, Red River Army Depot is hereby updated. The total contract estimated volume is increased:

From: 287,500 Dths To: 795,840 Dths

A revised schedule page is included in this amendment.

2. Notes #3, 4, and 5 are hereby added to this line item:

Note #3 – “The depot is in process of converting three coal fired boilers to natural gas. The estimated gas increase is shown above. This will require an upgrade of one of the two meters, plus an upgrade, by the pipeline company, on one of their regulators. Additionally, one of the large private companies will be getting their own meter, thus their usage will come off of the requirement. The Government anticipates the gas boilers will come on line late 2015.”

Note #4 – “The depot requests the third meter station be added to the requirement.”

Note #5 – “The supplier shall provide additional transportation capacity as necessary to meet the installation’s requirements.”

3. All other terms and conditions remain in full force and effect.

PAGE 2 OF 3 PAGESCONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED:

SPE60014R0417-0002

Line Item DWCF: No Installation

Address

City State

Zip

CenterPoint Energy Gas Transmission

795,840 215,660 580,180

Location

166,450 60,854 105,596 May Jun Jul Aug Sep Oct Nov Dec

4,100 5,000 7,152 7,652 13,252 23,698 37,198 68,398

401,746 111,656 290,090 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

69,198 61,598 53,698 28,998 14,152 13,252 11,452 10,152 9,952 23,698 37,198 68,398

227,644 43,150 184,494 Jan Feb Mar Apr May

69,198 61,598 53,698 28,998 14,152

Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

0 0 0 0 0 0 0 0 0 0 0 0

Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor

Overage Treatment Summer Volumes

Winter Volumes Shortage Treatment

Summer Volumes Winter Volumes

Note #1 Note #2

Note #3

Note #4 Note #5 The supplier shall provide additional transportation capacity as necessary to meet the installation’s requirements.

Presently Pine Bluff Main Post has 3,300 DTHs capacity on the pipeline. This is much more than they need. To save the government money the contractor will use this excess capacity to make the deliveries to Red River AD and add this as a pass through charge to Red River AD thus decreasing Pine Bluff's pipeline capacity charges.

The depot is in process of converting three coal fired boilers to natural gas. The estimated gas increase is shown on attached spreadsheet. This will require upgrade of one of the two meters already on contract, plus an upgrade by the pipeline company on one of their regulators. Additionally, one of the large private companies will be getting their own meter, thus their usage will come off of our contract. We anticipate the gas boilers will come on line late in 2015.

The depot requests the third meter station be added to this contract.

Red River does not have telemetering. The installation is willing to provide meter readings to the contractor.

Delivery Type

05/01/15 05/30/17 INSIDE FERC'S Enable Gas Transmission (2) Full Requirements/Pool. Firm

Year 2016 Annual Totals Summer Totals Winter Totals

Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option

Year 2017 Annual Totals Summer Totals Winter Totals

Estimated Usage Information (All volumes expressed in Dths)

Burner Tip

Year 2015 Annual Totals Summer Totals Winter Totals

No None 0% Alternate Fuel Type Percent Load Limits on Use Notes

Delivery Point Telemetered Rate Class Burner Tip No

Utility Account Information LDC or Pipeline

Total Contract Total Summer (Dths) Total Winter (Dths)

Texarkana

TX

75507-5000

Schedule Page By Line Item Detail

Red River Army Depot Installation Address

Red River Army Depot DODAAC /

FEDAAC:

W45G18Bldg 443

PAGE 3 of 3 PAGES