AMD0001 dated July 24, 2014
Attachment A- Questions & Answers
SPE600-14-R-0415
1. Can the information in Part A of the Supply Plan be submitted at the time of REC delivery (i.e. name and details of each facility), rather than at the time of our original proposal?
Answer: In accordance with clause L805(a)(3), Attachment I Supplemental Data Form, part (a)Supply Plan shall be submitted at the time of the original proposal. Per the Note in Attachment I, “After contract award, no deviations to the approved Supply Plan shall be permitted.”
2. For the Wind Sources NEW product, will the Environmental Protection Agency accept wind RECs generated from a wind generator located in the ERCOT control area (i.e., Texas)?
Answer: Wind Sources, NEW RECs must comply with FAR 52.225-1 Buy American Act—Supplies.
3. For the Wind Sources NEW product, will the Environmental Protection Agency accept wind RECs generated from a wind generator located in the PJM control area (i.e., PA, MD, IL, IN, WV, etc)?
Answer: Refer to answer #2.