Attachment_6_-_LSJ_Signed.pdf
PDF 365 KB Posted
- Attached to
- Italy Sole Source Contract for 232 Multi-Functional Devices (MFDs) Federal contract opportunity
- Solicitation number
- SP7000-20-Q-1001
- Issued by
- Defense Logistics Agency
About this file
Attachment 6 - LSJ FAR 13.106-1b
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_3_-_CLIN_Structure.xlsx | XLSX spreadsheet | |
| Attachment_5_-_Full_Text_Provisions_(Vendor_COMPLETION_Required).pdf | ||
| Attachment_2_-_Delivery_Schedule.pdf | ||
| Attachment_1_-_Performance_Work_Statement_(PWS).pdf | ||
| Attachment_4_-_Performance_Work_Statement_Compliance_Form.pdf | ||
| SP7000-20-Q-1001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEFENSE LOGISTICS AGENCY
Contracting Services Office
5404 J Ave, Bldg 404 New Cumberland, PA 17070-5059
Date
Justification for Other than Full and Open Competition IAW FAR 13.106-1(b)
1. Nature and/or description of the action being approved:
2. A description of the supplies or services required to meet the agency’s needs (including the estimated value):
3. A demonstration that the proposed contractor’s unique qualifications or the nature of the acquisition requires only one source in accordance with FAR 13.106-1(b) Example: urgency, exclusive licensing agreements, brand name, industrial mobilization, or any other reasonable justification
4. A description of the market research conducted (see Part 10) and the results or a statement of the reason market research was not conducted:
5. Any other facts supporting the use of other than full and open competition, such as:
Explanation of why technical data packages, specifications, engineering descriptions, statements of work, or purchase descriptions suitable for full and open competition have not been developed or are not available
TECHNICAL PERSONNEL: I certify that any supporting data that is the responsibility of technical or requirements personnel and which form a basis for the justification are complete and accurate.
Technical Personnel
8. A statement of the actions the agency has taken to avoid this other than full and open competition action and additional other than full and open actions in the future:
Contracting Officer
7. A listing of the sources, if any, that expressed, in writing, an interest in the acquisition (Include the results of the request for information or the sources sought notification in accordance with DFARS PGI 206.302-1 or include the waiver from the HCA or designee):
6. A description of efforts made to ensure that offers are solicited from as many potential sources as is practicable, including whether a notice was or will be publicized as required by Subpart 5.2 and, if not, which exception under 5.202 applies:
CONTRACTING APPROVAL: The justification, as presented above, is accurate and complete to the best of my knowledge and belief. Additionally, I have determined that the anticipated cost to the Government will be fair and reasonable.
| Text1: 09/24/2019 |
| Text2: DLA Information Operations has a need to issue a sole source contract action to continue lease support for multi-functional devices (MFD) without using competitive procedures. An award for a new lease is in progress with the possibility of deliveries taking place earliest by December 1st, the sole source contract will cover continued lease support starting November 1, 2019 through November 30, 2019 with 2, 1 month options to cover the months of December 2019 and January 2020. |
| Text3: Continued MFD lease support for 1 months to include full service maintenance, all consumable supplies (excluding paper), key operator training, networking functionality, security accreditation along with technical and network installation support. |
POP: November 1, 2019 - November 30, 2019 Options: December 1, 2019 - January 31, 2020 Estimated value of the expected 1 month is $60,583.26 Estimated up to 3 month value is $181,749.78.
| Text5: Although other vendors are available to supply MFDs with consumables and services; there is a short time period to allow installation. There is no other vendor that would be able to deliver new devices in time for a November 1, 2019 start date. The devices are in place and need to be extended on a sole source contract. Since the devices in place are under a lease, no other vendor can service the lease of another vendor without violating the lease terms. The only way to ensure uninterrupted support to the Warfighter is to issue a contract to the current vendor. | |
| Text6: Market research indicates that an adequate competition pool exists for requirements of this type. The contract will be in place for up to 3 months to account for the time time needed to award the follow on contract, device testing, and 60 days delivery on the follow on contract. | |
| Text7: Attempting to do a short-term contract via competitive procedures would result in unacceptable delays to achieve contract award and delivery/installation of new equipment; both of which would cripple the customer. The unacceptable delays would entail removal of the 232 devices currently in place, re-competing the short term rental, and delivery of the short term rental, during which the customers would be without devices. An up to three month contract will provide adequate time for the delivery and installation of new devices. | |
| 2019-10-24T16:05:34-0400 | |
| ANGUIANO.MARIA.ELIZABETH.1455052048 |
| 2019-09-24T11:42:20-0400 | |
| LANGE.PAUL.CHARLES.1284317714 |
| Text10: A combined solicitation/synopsis will be published on the Federal Business Opportunities. |
| Text11: A Request for Information (RFI) was published on the Federal Business Opportunities website. Two large business (Sharp Electronics UK and Genuine Logitics Services) responded to the RFI. The devices are currently in place and Sharp Electronics UK is the only vendor that can provide these devices by the November 1, 2019 POP start date. |
| Text12: EMS Policy and Support is developing a new process and Tracker system that will track all active EMS contracts and actions. This system will include the contract term dates, customer engagement dates, and all details related to issues or problems with replacement requirements or contract delays. The CRS and EPC personnel will be trained on this new process/system near the FY end. This new tracker system will be used to conduct EPC and CRS personnel, weekly and monthly discussions. This new system should resolve or minimize sole source contracts for extension of MFD service. |
File details come from the government source that posted it.